The invention discloses a construction equipment for a high-speed railway double track tunnel inverted arch, belonging to the technical field of tunnel construction equipment. For construction equipment of tunnel invert of the invention, including Zhanqiao, arch frame and end beams, the ends of beam and arch frame connected to form a whole, the end beams and / or arch frame are connected to the Zhanqiao, and the end beam and arch frame movement self in Zhanqiao. For the construction equipment of tunnel invert the accurate positioning, mobile positioning fast, high level of mechanization, low labor intensity, low construction cost; one can invert the whole pouring completed, high construction efficiency, high engineering quality, and can provide guarantee for the rapid excavation of tunnel; tunnel construction organization optimization and process for partition, standardized operation and safe and civilized construction; the construction is convenient, the traditional construction technology breakthrough arch back, ensure the arch continuous construction quality, is beneficial to popularization and application.
【技术实现步骤摘要】
【技术保护点】
1.一种用于高速铁路双线隧道仰拱的施工设备,其特征在于:它包括栈桥(2)、仰拱模架(5)和端头梁(1),所述端头梁(1)与仰拱模架(5)连接形成一整体,所述端头梁(1)和/或仰拱模架(5)连接于栈桥(2)上,且端头梁(1)与仰拱模架(5)在栈桥(2)上自行移动。
【技术特征摘要】
【专利技术属性】
技术研发人员:张勇,王云波,刘仁智,马辉,梅志荣,胡守斌,兰文峰,陈仁超,马雷,张金柱,王磊,王洪涛,张军伟,陈时刚,文志勇,
申请(专利权)人:中铁二局股份有限公司,中铁二局集团有限公司,
类型:发明
国别省市:90
还没有人留言评论。发表了对其他浏览者有用的留言会获得科技券。