The invention relates to a construction method of plastic film between two walls for seepage interception of sand embankment foundation, which closes the seepage interception curtain of sand embankment foundation constructed by at least including seepage prevention groove (1), plastic film (2), backfilling clay (3), unit wall of upstream mixing pile (4), seepage interception wall of backwater mixing pile (5) and seepage interception wall of overlapping mixing pile (6). The characteristics are as follows: Firstly, the vertical groove line is determined; secondly, the vertical groove line is constructed; thirdly, the mixing pile is constructed; fourthly, the unit wall of the upstream mixing pile (4) and the cut-off wall of the backwater mixing pile (5) are closed and overlapped. The invention can solve the problem of overlapping treatment of vertical plastic seepage curtain and deep mixing pile seepage curtain, so as to form a more economical and applicable combined seepage curtain. The invention has remarkable application benefits and has broad market prospects.
【技术实现步骤摘要】
一种用于砂土堤基截渗的两墙夹塑膜施工方法
本专利技术属于水利工程堤防截渗施工
,特别是涉及一种用于砂土堤基截渗的两墙夹塑膜施工方法。技术背景垂直铺塑截渗和深层搅拌桩截渗是我国水利工程中较为常见的堤防截渗技术。在垂直截渗施工过程中,截渗膜或混凝土截渗墙通常被埋设在堤坝迎水侧的坝根,以切断坝根下方地层中的渗水通道,保护堤坝的安全,其施工流程成熟,截渗效果较好。然而对于多数河堤和江堤而言,单独运用上述方法施工存在困难,原因如下:1、因地质、地貌、水文及人为建筑设施等因素作用,整个堤防并非直线规则分布,多处堤段存在急弯处和大的拐点,如图1所示。而在垂直铺塑截渗施工过程中,铺塑开槽机只能沿导轨运行,在堤身急弯和拐点处施工设备不能圆滑开槽,因此垂直铺塑在施工至堤身转角处时无法沿堤身转弯,该现象会导致堤防全线的截渗帷幕不能封闭,不能完全截断渗流通道。这就使得单一应用垂直铺塑截渗工艺难以满足堤防全线的截渗要求。2、多数堤防迎水侧护堤种植大量的防浪林,用于防浪护堤和抢险取材,是防洪工程的重要组成部分和抵御洪水的有效屏障。但这些防浪林的枝干茂盛,空中覆盖范围大,加之附近高压 ...
【技术保护点】
1.一种用于砂土堤基截渗的两墙夹塑膜施工方法,是对至少包括防渗槽(1)、塑膜(2)、回填粘土(3)、迎水侧搅拌桩单元墙(4)、背水侧搅拌桩截渗墙(5)和两侧搭接搅拌桩截渗墙(6)构建的砂土堤基截渗帷幕进行封闭处理,其特征在于,具体步骤如下:第一步,确定垂直铺塑开槽线:精准确定并记录防渗槽(1)的开槽起始点和防渗槽槽孔背水侧的位置线,为搅拌桩机找准塑膜(2)位置进行施工定位;第二步,进行垂直铺塑施工:将塑膜(2)铺贴于背水侧的槽壁,自开挖防渗槽(1)的起始点计,在其10~15米长度范围内向防渗槽(1)中添加回填粘土(3),使回填粘土(3)在塑膜(2)迎水侧槽孔内固结;第三步, ...
【技术特征摘要】
1.一种用于砂土堤基截渗的两墙夹塑膜施工方法,是对至少包括防渗槽(1)、塑膜(2)、回填粘土(3)、迎水侧搅拌桩单元墙(4)、背水侧搅拌桩截渗墙(5)和两侧搭接搅拌桩截渗墙(6)构建的砂土堤基截渗帷幕进行封闭处理,其特征在于,具体步骤如下:第一步,确定垂直铺塑开槽线:精准确定并记录防渗槽(1)的开槽起始点和防渗槽槽孔背水侧的位置线,为搅拌桩机找准塑膜(2)位置进行施工定位;第二步,进行垂直铺塑施工:将塑膜(2)铺贴于背水侧的槽壁,自开挖防渗槽(1)的起始点计,在其10~15米长度范围内向防渗槽(1)中添加回填粘土(3),使回填粘土(3)在塑膜(2)迎水侧槽孔内固结;第三步,进行搅拌桩施工:在第二步所述的垂直铺塑施工完成14天后,沿垂直铺塑截渗帷幕两侧分别设置迎水侧搅拌桩单元墙(4)和背水侧搅拌桩截渗墙(5)两排搅拌桩;所述迎水侧搅拌桩单元墙(4)与塑膜(2)之间设有因防止迎水侧搅拌桩单元墙(4)接触塑膜(2)而破坏塑膜(2)的安全距离;所述背水侧搅拌桩截渗墙(5)与塑膜(2)之间设有因防止背水侧搅拌桩截渗墙(5)接触塑膜(2)而破坏塑膜(2)的安全距离;迎水侧搅拌桩单元墙(4)与回填粘土(3)之间形成能够使垂直铺塑截渗帷幕与深层搅拌桩截渗帷幕无缝对接的搭接宽度;第四步,将迎水侧搅拌桩单元墙(4)与背水侧搅拌桩截渗墙(5)封闭搭接:沿垂直铺塑截渗帷幕前端将第三步所述的迎水侧搅拌桩单元墙(4)和背水侧搅拌桩截渗墙(5)交回并形成封闭对接,然后两侧搭接搅拌桩截渗墙(6)在垂直铺塑...
【专利技术属性】
技术研发人员:孙树林,吴正松,姜华,孙建东,张德恒,