The invention discloses a manufacturing method of concrete prefabricated comprehensive pipe gallery, which includes pouring technology and maintenance technology after pouring. When pouring, the temperature of the formwork should be determined at 5 35 (?) C, and the maintenance of the prefabricated parts should be carried out after the whole pouring is completed. Initial vibration of edge angle, bottom plate and roof was carried out by inserting tamping rod, and then the attached vibrator was used to vibrate intermittently for 30S. The sequence of intermittent vibration was weak vibration, strong vibration and weak vibration (attachment type vibrator was the main part, insertion type vibrating rod was the auxiliary part, while cutting material was the side of tamping); the maintenance temperature was raised by steam combination, and steam generator was used to produce steam pipe to raise the maintenance temperature. The outlet is arranged at the bottom of the corridor, and holes are evenly arranged on the pipeline to ensure uniform temperature. The steam curing process is maintained in the order of static stop, heating, constant temperature and cooling.
【技术实现步骤摘要】
混凝土预制综合管廊的制造方法
本专利技术属于城市综合管廊施工
,特别涉及一种混凝土预制综合管廊的制造方法。
技术介绍
城市地下综合管廊已经有180多年的历史,最早修建管廊的国家是法国,它集自来水,通讯、电力、污水处理、燃气输入管道、以及供热等管道于一身。但我国大部分管廊的施工均采用就地现浇的方式进行,地下综合管廊预制在国内处于起步阶段,可使用的规范均参考市政,建筑、管道安装工程等规范进行设计施工,暂无完善的设计、施工、验收等规范。由于受到运输的限制,国内主要管廊预制以单仓和双仓形式较多,一般生产3米以下管廊方涵。三仓大型管廊,宽度达到10.3米的预制管廊国内较少。目前国内大型地下综合管廊均采用现浇的方式进行施工,现场浇筑的特点是:受场地的限制养护条件艰难,设计要求养护14d,养护用水量大且养护管道不方便布设,现场浇筑混凝土质量得不到保证,混凝土抗渗性能不如工厂预制混凝土好,易发生渗漏,管廊易出现施工裂缝,涵体侧壁通裂等,产品质量不易控制,施工成本较高。
技术实现思路
本专利技术的目的在于:针对上述现有技术存在的问题,提供了一种混凝土预制综合管廊的制造方法,具备产品质量易控制,材料可控,产品成本较现浇低,施工周期短,社会效益好,环境污染较小等优势。本专利技术的技术方案是这样实现的:一种混凝土预制综合管廊的制造方法,所述方法包括以下步骤:S1:浇筑条件检测,浇筑前测量混凝土入模温度夏天为5-35℃,冬天为10-35℃,模板温度为5-35℃;并测定浇筑时的环境温度温,确定环境温度低于35℃时才开始浇筑;S2:底板混凝土浇筑,使用门吊、料斗和滑槽先从燃气仓进行浇 ...
【技术保护点】
1.一种混凝土预制综合管廊的制造方法,其特征在于:所述方法包括以下步骤:S1:浇筑条件检测,浇筑前测量混凝土入模温度夏天为5‑35℃,冬天为10‑35℃,模板温度为5‑35℃;并测定浇筑时的环境温度温,确定环境温度低于35℃时才开始浇筑;S2:底板混凝土浇筑,使用门吊、料斗和滑槽先从燃气仓进行浇筑,再依次浇筑综合仓和污水仓;浇筑过程中使用振动棒引导混凝土并振捣密实,混凝土的坍落度控制在160‑200mm范围内;确保底板混凝土浇筑密实后,在芯室内安装底部盖板,防止芯室内混凝土翻涌;综合仓底板和污水仓底板混凝土浇筑方法与燃气仓一致;S3:腹板混凝土浇筑,底板混凝土浇筑完成后,开始浇筑腹板混凝土;腹板混凝土浇筑以附着式振动器为主,插入式振动器配合振捣,腹板内侧的振捣应较腹板外侧延长振捣时间;S4:待整体浇筑完成后,进行预制件的养护,并制作完成合格的综合管廊预制件。
【技术特征摘要】
1.一种混凝土预制综合管廊的制造方法,其特征在于:所述方法包括以下步骤:S1:浇筑条件检测,浇筑前测量混凝土入模温度夏天为5-35℃,冬天为10-35℃,模板温度为5-35℃;并测定浇筑时的环境温度温,确定环境温度低于35℃时才开始浇筑;S2:底板混凝土浇筑,使用门吊、料斗和滑槽先从燃气仓进行浇筑,再依次浇筑综合仓和污水仓;浇筑过程中使用振动棒引导混凝土并振捣密实,混凝土的坍落度控制在160-200mm范围内;确保底板混凝土浇筑密实后,在芯室内安装底部盖板,防止芯室内混凝土翻涌;综合仓底板和污水仓底板混凝土浇筑方法与燃气仓一致;S3:腹板混凝土浇筑,底板混凝土浇筑完成后,开始浇筑腹板混凝土;腹板混凝土浇筑以附着式振动器为主,插入式振动器配合振捣,腹板内侧的振捣应较腹板外侧延长振捣时间;S4:待整体浇筑完成后,进行预制件的养护,并制作完成合格的综合管廊预制件。2.根据权利要求1所述的混凝土预制综合管廊的制造方法,其特征在于:底板混凝土浇筑过程中先使用Φ50振动棒引导混凝土并振捣密实,振捣完毕后在底板承插口位置使用Φ30捣动棒捣固,并确保底板捣固后,厚度应低于设计厚度5-10mm,腹板混凝土浇筑时可自行填充。3.根据权利要求2所述的混凝土预制综合管廊的制造方法,其特征在于:腹板外侧的振捣应密插、短振、勤振,插入点的间隔200mm,振捣棒的插入深度应插入上一层浇筑混凝土的50~100mm;隔墙与底板的连接处使用附着式...
【专利技术属性】
技术研发人员:刘志明,门忠,王江,彭良,何富聪,龙中祥,李炀,张华乔,游亮,赵境贤,周柏臣,唐敏,雷春梅,邓如丽,李清,张阳,贾晓冬,张敏,朱江,杜焕坚,
申请(专利权)人:中铁八局集团桥梁工程有限责任公司,
类型:发明
国别省市:四川,51
还没有人留言评论。发表了对其他浏览者有用的留言会获得科技券。