The invention relates to the field of bridge construction technology, in particular to a prefabricated assembly Bridge integrated rapid construction method. Bridge erecting machine is built on the bridge deck which has been assembled. Prefabricated pier columns, prefabricated cap beams and steel girders are transported to the deck which has been assembled by girder transporter. Prefabricated pier columns are lifted by bridge erecting machine to the platform which is poured on the ground. After the fixed connection between prefabricated pier columns and caps is completed, the bridge erecting machine lifts steel girders to two adjacent prefabricated cap beams along the bridge, and then lays the bridge deck on the steel girders. The slab completes the assembly of the bridge segment, and then lifts the prefabricated cap beam to the prefabricated pier column which is fixed with the cap. The driving bridge erector travels one span along the completed bridge segment to assemble the next bridge segment, and proceeds in turn until all the segments are assembled. The invention can complete the installation of all components such as prefabricated pier columns, prefabricated cap beams, steel main beams and so on, realize the simultaneous construction of the upper and lower structures of bridges, and effectively improve the construction efficiency on site.
【技术实现步骤摘要】
一种预制装配式桥梁一体化快速施工方法
本专利技术涉及桥梁施工
,具体地指一种预制装配式桥梁一体化快速施工方法。
技术介绍
在桥梁建设领域,预制装配式桥梁能有效提高现场施工速度,保障结构构件的质量,提高结构耐久性,应用范围和前景广阔。在预制装配式桥梁的现场施工中,通常采用架桥机来架设上部结构,采用履带吊来架设墩柱、盖梁等下部结构,施工过程中需大量人工辅助,施工效率低,且对既有交通影响大。桥梁上部结构和下部墩柱通常需要两次施工,严重制约桥梁的施工效率,且工程量巨大,需要耗费大量的人力物力,使桥梁修筑成本大幅度上升。而且对于一些地域环境恶劣的情况,下部墩柱搭建极为困难。
技术实现思路
本专利技术的目的就是要解决上述
技术介绍
中提到的现有技术存在架桥效率低、一体化程度低的问题,提供一种预制装配式桥梁一体化快速施工方法。本专利技术的技术方案为:一种预制装配式桥梁一体化快速施工方法,其特征在于:在已拼装完成的桥面上搭建架桥机,通过运梁车运送预制墩柱、预制盖梁和钢主梁至已拼装完成的桥面上,架桥机吊运预制墩柱至浇筑于地面的承台上,待预制墩柱与承台完成固定连接后,架桥机吊运钢主梁至顺桥向相邻两根预制盖梁上,然后在钢主梁上铺设桥面板完成该跨桥段的拼装,再吊运预制盖梁至与承台完成固定连接的预制墩柱上,驱动架桥机沿已拼装完成的桥段行进一跨进行下一跨桥段的拼装,依次进行直至所有的桥段拼装完成进一步的在已拼装完成的桥面上搭建架桥机的方法为:通过龙门吊将架桥机的主桁架吊运至已拼装完成的桥面上,将主桁架的后支腿下端支撑于已拼装完成的桥面上、将其上端通过螺栓连接固定在主桁架后端,将主桁架的 ...
【技术保护点】
1.一种预制装配式桥梁一体化快速施工方法,其特征在于:在已拼装完成的桥面上搭建架桥机,通过运梁车(13)运送预制墩柱(9)、预制盖梁(10)和钢主梁(11)至已拼装完成的桥面上,架桥机吊运预制墩柱(9)至浇筑于地面的承台(14)上,待预制墩柱(9)与承台(14)完成固定连接后,架桥机吊运钢主梁(11)至顺桥向相邻两根预制盖梁(10)上,然后在钢主梁(11)上铺设桥面板完成该跨桥段的拼装,再吊运预制盖梁(10)至已与承台(14)完成固定连接的预制墩柱(9)上,驱动架桥机沿已拼装完成的桥段行进一跨进行下一跨桥段的拼装,依次进行直至所有的桥段拼装完成。
【技术特征摘要】
1.一种预制装配式桥梁一体化快速施工方法,其特征在于:在已拼装完成的桥面上搭建架桥机,通过运梁车(13)运送预制墩柱(9)、预制盖梁(10)和钢主梁(11)至已拼装完成的桥面上,架桥机吊运预制墩柱(9)至浇筑于地面的承台(14)上,待预制墩柱(9)与承台(14)完成固定连接后,架桥机吊运钢主梁(11)至顺桥向相邻两根预制盖梁(10)上,然后在钢主梁(11)上铺设桥面板完成该跨桥段的拼装,再吊运预制盖梁(10)至已与承台(14)完成固定连接的预制墩柱(9)上,驱动架桥机沿已拼装完成的桥段行进一跨进行下一跨桥段的拼装,依次进行直至所有的桥段拼装完成。2.如权利要求1所述的一种预制装配式桥梁一体化快速施工方法,其特征在于:在已拼装完成的桥面上搭建架桥机的方法为:通过龙门吊(12)将架桥机的主桁架(1)吊运至已拼装完成的桥面上,将主桁架(1)的后支腿(5)下端支撑于已拼装完成的桥面上、将其上端通过螺栓连接固定在主桁架(1)后端,将主桁架(1)的前支腿(2)支撑于搁置于地面上的支撑座(2.4)上、将其上端与主桁架(1)前端固定连接。3.如权利要求1所述的一种预制装配式桥梁一体化快速施工方法,其特征在于:架桥机吊运预制墩柱(9)至浇筑于地面的承台(14)上的方法为:运梁车(13)将倾倒至水平状态的预制墩柱(9)运送至已拼装完成的桥面上,通过主桁架(1)上的天车沿顺桥向方向吊运预制墩柱(9)至待安装承台(14)上方,驱动天车使处于水平状态的预制墩柱(9)调整至竖直状态,沿竖直方向下放预制墩柱(9)至承台(14)上,将预制墩柱(9)与承台(14)灌浆浇筑在一起。4.如权利要求3所述的一种预制装配式桥梁一体化快速施工方法,其特征在于:驱动天车使处于水平状态的预制墩柱(9)调整至竖直状态的方法为:在运梁车(13)将倾倒至水平状态的预制墩柱(9)运送至已拼装完成的桥面上后,同步驱动主桁架(1)上的前天车(6)和后天车(7)至预制墩柱(9)的上方,将前天车(6)吊索的下端锚固在预制墩柱(9)的前端,后天车(7)吊索的下端锚固在预制墩柱(9)接近后端的侧部,顺桥向吊运至待安装承台(14)上方后,驱动后天车(7)使预制墩柱(9)的后端缓慢下降,直至预制墩柱(9)翻转成竖直状态。5.如权利要求1所述的一种预制装配式桥梁一体化快速施工方法,其特征在于:驱动架桥机沿已拼装完成的桥段行进一跨的方法为:调整主桁架(1)前半部分的支点位置,抬升前支腿(2)使其与支撑座(2.4)脱离,抬升后支腿(5)使其桥面脱离,调整主桁架(1)的重心位置,卸载位于前、后支腿之间的中后支腿(4)下端的第二顶升油缸(4.6)使中后支腿(4)下端的行走滚轮(4.5)支撑于桥面轨道(4.7)上,驱动中后支腿(4)沿轨道(4.7)运行使主桁架(1)沿顺桥向方向行进一跨,搬运支撑座(2.4)至前支腿(2)下方,调整前支腿(2)的高度使其下端支撑于支撑座(2.4)上,然后将后支腿(5)、中后支腿(4)下端支撑于已完成拼装的桥段桥面上。6.如权利要求5所述的一种预制装配式桥梁一体化快速施工方法,其特征在于:调整主桁架(1)前半部分的支点位置的方法为:将位于前支腿(2)和中后支腿(4)之间的中前支腿(3)的上下两端分别与主桁架(1)和位于已拼装完成的桥面前端下方的预制盖梁(10)解除固定连接,驱动中前支腿(3)沿主桁架(1)行进至该钢主梁(11)前方与之相邻的已浇筑固定在承台(14)上的预制墩柱(9)上方,将中前支腿(3)的下端锚固在下方的预制盖梁(10)上。7.如权利要...
【专利技术属性】
技术研发人员:张鸿,张永涛,杨秀礼,翟世鸿,徐杰,夏昊,王敏,郑和晖,程茂林,卢勇,姚清涛,华晓涛,孟奎,刘修成,朱明清,
申请(专利权)人:中交第二航务工程局有限公司,
类型:发明
国别省市:湖北,42