The invention discloses a construction method for the first dismantling of the underground pipe gallery and the side wall formwork. The main steps are to remove the side wall formwork and supporting system in the process of construction, while removing the non vertical stress bar of the roof template support system, such as sweeping rods and scissors braces. The construction method of the invention can not only affect the vertical force of the supporting system, but also facilitate the operation of the operators to conduct material cleaning operations, and effectively improve the turnover rate of building templates, steel pipes, fasteners and other materials.
【技术实现步骤摘要】
地下管廊、管沟侧壁模板先拆的施工方法
本专利技术属于一种建筑工程模板支撑系统的施工方法,具体涉及一种地下管廊、管沟侧壁模板先拆的施工方法。
技术介绍
随着我国城市建设的不断推进,市政设施综合利用意识的增强,各地正在大力发展地下综合管廊,即在城市地下建造一个隧道空间,将电力、通信,燃气、供热、给排水等各种工程管线集于一体,它是城市生命线基础设施的核心。现阶段,针对有墙壁、顶板的地下管廊、管沟,常规的施工方法为:墙壁侧模与顶板模板及支撑系统形成整体,待顶板砼强度满足设计及规范要求后再一并拆除侧壁及顶板模板和支撑系统。这种施工方法虽然具有良好的稳定性,但施工周期长,人力物力投入大。
技术实现思路
为解决上述问题,本专利技术提供了一种地下管廊、管沟侧壁模板先拆的施工方法,步骤简单,操作方便,能有效提高施工效率。本专利技术的技术方案如下:地下管廊、管沟侧壁模板先拆的施工方法,具体步骤如下:步骤一,将侧壁模板支撑系统和顶板模板支撑系统分开搭设,使用丝扣可调顶托将侧壁模板支撑系统和顶板模板支撑系统连成一个整体;步骤二,在保证稳定性、整体性的前提下,侧壁砼浇筑3~5天后,拆模不损伤砼棱角的情况下,先拆除侧壁模板及支撑系统;同时拆除顶板模板支撑系统的扫地杆、剪刀撑等非垂直受力杆件。与现有技术相比,本专利技术的优点为:1)与现有技术相比本专利技术先拆施工法提前进行侧壁模板的拆除,有效的提高了建筑模板、钢管、扣件等材料的周转率;2)本专利技术施工方法有利于作业人员通行进行材料清理作业,提高施工效率。具体实施方式下面结合具体实施例对本专利技术做进一步地描述。实施例1现有技术施工地下管 ...
【技术保护点】
地下管廊、管沟侧壁模板先拆的施工方法,其特征在于,具体步骤如下:步骤一,将侧壁模板支撑系统和顶板模板支撑系统分开搭设,使用丝扣可调顶托将侧壁模板支撑系统和顶板模板支撑系统连成一个整体;步骤二,在保证稳定性、整体性的前提下,侧壁砼浇筑3~5天后,拆模不损伤砼棱角的情况下,先拆除侧壁模板及支撑系统;同时拆除顶板模板支撑系统的扫地杆、剪刀撑等非垂直受力杆件。
【技术特征摘要】
1.地下管廊、管沟侧壁模板先拆的施工方法,其特征在于,具体步骤如下:步骤一,将侧壁模板支撑系统和顶板模板支撑系统分开搭设,使用丝扣可调顶托将侧壁模板支撑系统和顶板模板支撑系统连成...
【专利技术属性】
技术研发人员:徐小钦,
申请(专利权)人:中国十七冶集团有限公司,
类型:发明
国别省市:安徽,34