The invention discloses a construction method of a shield pipe gallery, which relates to the construction field of the pipe gallery. The main technical points of the scheme are as follows: when the shield machine excavates into hard rock section, holes are arranged on the rock surface of hard rock section, and drilling is carried out. The holes arranged in hard rock section need to form cross-network pipe which is connected transversely and vertically; the holes in hard rock section are sealed and blocked vertically; and the holes in hard rock section are sealed and blocked vertically. The liquid water is injected into the top of the hole, and the cross network pipe of the hard rock section is cooled by refrigeration equipment, so that the liquid water is cooled and frozen, and the rock of the hard rock section is split by the expansion of the liquid water. The technical effect is that the rock can be effectively split by using ice blasting technology, and the construction period can be greatly shortened by further processing with hydraulic splitter. At the same time, the problems such as low efficiency of shield tunneling, severe tool wear and difficulty of tool change in such strata can be solved.
【技术实现步骤摘要】
盾构管廊的施工方法
本专利技术涉及管廊的施工领域,特别涉及一种盾构管廊的施工方法。
技术介绍
目前综合管廊的施工方法有以下几种。一、明挖现浇法:利用支护结构支挡条件下,在地表进行地下基坑开挖,在基坑内施工做内部结构的施工方法。其具有工艺简单、施工方便、工程造价低的特点,但雨天、北方地区冬季无法施工;施工作业时间长:土方大。适用于城市新建区的管网建设。二、明挖预制拼装法:是一种较为先进的施工方法,要求有较大规模的预制厂和大吨位的运输及起吊设备,施工技术要求、工程造价较高。特点是施工速度快,施工质量易于控制。现浇法与预制拼装法施工造价大致相当三、浅埋暗挖法:是在距离地表较近的地下进行各类地下洞室暗挖的一种施工方法。埋层浅,地层岩性差,存在地下水,环境复杂等地区适合此法。在明挖法和盾构法不适应的条件下,浅埋暗挖法显示了巨大的优越性。它具有灵活多变,对道路、地下管线和路面环境影响性小,拆迁占地少,不扰民的特点,适用于己建区的改造;四、顶管法:当管廊穿越铁路、道路、河流或建筑物等各种障碍物时,采用的一种暗挖式施工方法。在施工时,通过传力顶铁和导向轨道,用支撑于基坑后座上的液压千斤顶将管线压入土层中,同时挖除并运走管正面的泥土。适用于软土或富水软土层。无需明挖土方,对地面影响小;设备少、工序简单、工期短、造价低、速度快;适用于中型管道施工,但管线变向能力差,纠偏困难:五、盾构法:使用盾构在地中推进,通过盾构外壳和管片支撑四周围岩,防止发生隧道内的坍塌,同时在开挖面前方用刀盘进行土体开挖,通过出土机械运出洞外,靠推进油缸在后部加压顶进,并拼装预制混凝土管片,形成隧道结构 ...
【技术保护点】
1.一种盾构管廊的施工方法,其特征在于:包括以下操作步骤:S1,首先在盾构开挖前对掘进范围内的不良地质段进行勘测,确定软土段和硬岩段的具体区域;S2,根据确定的硬岩段区域,选取软土段开挖并进行必要的围护结构,形成始发井和接受井;在不具有软土段时,通过竖井利用钻爆法开挖硬岩地层并进行必要的围护结构,形成始发井和接受井;S3,将盾构机吊装至始发井内,利用盾构机对软土部分进行开挖掘进,完成管节安装及路面回填;S4,盾构机开挖至硬岩段时,在硬岩段的岩石表面进行布孔,并进行钻孔施工,硬岩段布置的孔需要形成横向与竖向贯穿连通的交叉网管;S5,对硬岩段横向的孔洞进行密封堵塞,并竖向的孔洞上方注入液态水;S6,利用制冷设备对硬岩段的交叉网管进行冷却,使液态水冷却结冰,硬岩段的岩石因液态水结冰膨胀而分裂;S7,将密封堵塞的行业横向孔洞打开,利用液压分裂机进一步将岩石分裂;S8,凿除并进行清理,把底部石磕清除干净,在凿除清理过程中建立支护结构;S9,清理完成后,利用盾构机掘进,完成管节安装及路面回填;S10,盾构机掘进至接受井,再始发,循环施工,完成S3~S9步骤。
【技术特征摘要】
1.一种盾构管廊的施工方法,其特征在于:包括以下操作步骤:S1,首先在盾构开挖前对掘进范围内的不良地质段进行勘测,确定软土段和硬岩段的具体区域;S2,根据确定的硬岩段区域,选取软土段开挖并进行必要的围护结构,形成始发井和接受井;在不具有软土段时,通过竖井利用钻爆法开挖硬岩地层并进行必要的围护结构,形成始发井和接受井;S3,将盾构机吊装至始发井内,利用盾构机对软土部分进行开挖掘进,完成管节安装及路面回填;S4,盾构机开挖至硬岩段时,在硬岩段的岩石表面进行布孔,并进行钻孔施工,硬岩段布置的孔需要形成横向与竖向贯穿连通的交叉网管;S5,对硬岩段横向的孔洞进行密封堵塞,并竖向的孔洞上方注入液态水;S6,利用制冷设备对硬岩段的交叉网管进行冷却,使液态水冷却结冰,硬岩段的岩石因液态水结冰膨胀而分裂;S7,将密封堵塞的行业横向孔洞打开,利用液压分裂机进一步将岩石分裂;S8,凿除并进行清理,把底部石磕清除干净,在凿除清理过程中建立支护结构;S9,清理完成后,利用盾构机掘进,完成管节安装及路面回填;S10,盾构机掘进至接受井,再始发,循环施工,完成S3~S9步骤。2.根据权利要求1所述的盾构管廊的施工方法,其特征在于:在步骤S6中的制冷设备采用干冰制冷或液氮制冷,制冷的温度达到零下100℃~零下200℃。3.根据权利要求1所述的盾构管廊的施工方法,其特征在于:所述液态水中在制冷前添加制冷剂,制冷剂可以是R410a、R134a、R407C、R2、R22、R12的其中一种或任意多种的组合。4.根据权利要求1所述的盾构管廊的施工方法,其特征在于:所述始发井和接受井的围护结构采用φ1000@1200mm钻孔灌注桩,其桩长19m,和φ800@500mm高压旋喷止水桩,其桩长14m;围护桩顶设1100...
【专利技术属性】
技术研发人员:蓝柳毅,范碧森,盛晓进,王杰,刘荣地,陈骊,崔村,
申请(专利权)人:浙江汉领建设有限公司,
类型:发明
国别省市:浙江,33
还没有人留言评论。发表了对其他浏览者有用的留言会获得科技券。