The invention belongs to the field of building construction, in particular to a construction method for anti-seepage of the post cast strip of the basement floor, which comprises the following steps: Step 1, the construction of the foundation cushion; step 2, the construction of the SBS waterproof additional layer and the SBS waterproof layer; step 3, the construction of the cement mortar protective layer; step 4, the installation of the reinforcement support frame, the waterstop steel plate and the quick closing net; step 5, the expansion when encountering water Installation of waterstop; step 6: installation of profile steel support; step 7: Construction of self waterproof structure bottom plate; step 8: installation of post cast strip protective board; step 9: Construction of post cast strip concrete. The anti-seepage construction method of the post pouring belt of the basement floor improves the concrete pouring quality, has strong anti-seepage ability, solves the problem of removing garbage and miscellaneous materials in the post pouring belt during the post pouring belt maintenance, settlement and stress deformation, eliminates the leakage risk of the post pouring belt, ensures the waterproof quality easily, has reasonable process structure, convenient operation, high working efficiency and strong operability.
【技术实现步骤摘要】
一种地下室底板后浇带防渗施工方法
本专利技术属于建筑施工领域,具体涉及一种地下室底板后浇带防渗施工方法。
技术介绍
目前,在地下室底板后浇带的施工中,常规的技术是混凝土垫层、卷材防水、保护层、结构自防水层依次施工。但因后浇带的结构设计需至少养护6周以上后浇筑后浇带混凝土,后浇带新旧两种混凝土结合缝处处理不当易渗漏,后浇带内多层钢筋网造成后浇带养护、沉降、应力变形期间后浇带内垃圾、杂料清除难。
技术实现思路
针对现有技术中存在的技术问题,本专利技术的目的在于提供一种地下室底板后浇带防渗施工方法,为了实现上述目的,本专利技术所采用的技术方案为:一种地下室底板后浇带防渗施工方法,包括以下步骤:步骤一、基础垫层的施工:先依次对基坑土层找平、压实,安装基础垫层模板,接着浇筑基础垫层混凝土,压实抹光,之后将基础垫层模板进行拆除,最后对基础垫层混凝土进行履盖养护;步骤二、SBS防水附加层、SBS防水层的施工:先施工SBS防水附加层,所述SBS防水附加层宽度视后浇带宽度每边各加500mm,之后施工整体SBS防水层;步骤三、水泥砂浆保护层施工:施工水泥砂浆保护层,压实抹光,之后进行履盖养护,接着施工自防水结构底板钢筋;步骤四、钢筋支撑架、止水钢板、快易收口网安装:钢筋支撑架分上、下两层,先安装下层钢筋网,然后安装钢筋支撑架、止水钢板,接着安装上层钢筋网,之后在上、下层钢筋网与止水钢板间安装快易收口网;步骤五、遇水膨胀止水条安装:在下层钢筋网与钢筋支撑架接触下口安装遇水膨胀止水条,所述遇水膨胀止水条安装前,遇水膨胀止水条与基础垫层接合处嵌满密封胶;步骤六、型钢支架安装:先依次安装 ...
【技术保护点】
1.一种地下室底板后浇带防渗施工方法,其特征在于,包括以下步骤:步骤一、基础垫层(1)的施工:先依次对基坑土层找平、压实,安装基础垫层(1)模板,接着浇筑基础垫层(1)混凝土,压实抹光,之后将基础垫层(1)模板进行拆除,最后对基础垫层(1)混凝土进行履盖养护;步骤二、SBS防水附加层(2)、SBS防水层(3)的施工:先施工SBS防水附加层(2),所述SBS防水附加层(2)宽度视后浇带宽度每边各加500mm,之后施工整体SBS防水层(3);步骤三、水泥砂浆保护层(4)施工:施工水泥砂浆保护层(4),压实抹光,之后进行履盖养护,接着施工自防水结构底板钢筋(5);步骤四、钢筋支撑架(9)、止水钢板(10)、快易收口网(8)安装:钢筋支撑架(9)分上、下两层,先安装下层钢筋网,然后安装钢筋支撑架(9)、止水钢板(10),接着安装上层钢筋网,之后在上、下层钢筋网与止水钢板(10)间安装快易收口网(8);步骤五、遇水膨胀止水条(6)安装:在下层钢筋网与钢筋支撑架(9)接触下口安装遇水膨胀止水条(6),所述遇水膨胀止水条(6)安装前,遇水膨胀止水条(6)与基础垫层(1)接合处嵌满密封胶;步骤六、型钢 ...
【技术特征摘要】
1.一种地下室底板后浇带防渗施工方法,其特征在于,包括以下步骤:步骤一、基础垫层(1)的施工:先依次对基坑土层找平、压实,安装基础垫层(1)模板,接着浇筑基础垫层(1)混凝土,压实抹光,之后将基础垫层(1)模板进行拆除,最后对基础垫层(1)混凝土进行履盖养护;步骤二、SBS防水附加层(2)、SBS防水层(3)的施工:先施工SBS防水附加层(2),所述SBS防水附加层(2)宽度视后浇带宽度每边各加500mm,之后施工整体SBS防水层(3);步骤三、水泥砂浆保护层(4)施工:施工水泥砂浆保护层(4),压实抹光,之后进行履盖养护,接着施工自防水结构底板钢筋(5);步骤四、钢筋支撑架(9)、止水钢板(10)、快易收口网(8)安装:钢筋支撑架(9)分上、下两层,先安装下层钢筋网,然后安装钢筋支撑架(9)、止水钢板(10),接着安装上层钢筋网,之后在上、下层钢筋网与止水钢板(10)间安装快易收口网(8);步骤五、遇水膨胀止水条(6)安装:在下层钢筋网与钢筋支撑架(9)接触下口安装遇水膨胀止水条(6),所述遇水膨胀止水条(6)安装前,遇水膨胀止水条(6)与基础垫层(1)接合处嵌满密封胶;步骤六、型钢支架(11)安装:先依次安装型钢支架(11)槽钢、角钢主体,然后安装型钢支架(11)角钢支脚,支脚座落在垫块(7)上;步骤七、自防水结构底板(12)施工:安装自防水结构底板(12)模板,施工自防水结构底板(12)混凝土,振捣密实,之后进行履盖养护;步骤八、后浇带防护木板(13)安装:在型钢...
【专利技术属性】
技术研发人员:陶金福,龙旭,
申请(专利权)人:中国十七冶集团有限公司,
类型:发明
国别省市:安徽,34