The invention provides a construction method for the installation of a cross seat monorail track beam, including the following steps: 1) the hoisting of the track beam: the construction of the track beam, the construction of the pier column, the construction of the cap beam, the construction of the scaffold, the position of the track Liang Yunshu, the installation of the stable hoop, the hoop hoop, the installation of the temporary support and the permanent support and the installation of the temporary fixer. Loosening the rope; 2) the track beam installation: the alignment of the track beam, the post pouring section steel plate welding, the post pouring section construction, the pivot beam between the left and right track beams, the middle cross section beam of the construction span, the temporary fixing device, the temporary support and the support. The construction method can solve the problems of hanging point, temporary support, temporary fixing and linear adjustment when the track beam is hoisted. It can adapt to the erection and installation of track beams and complex terrain rail beams with different specifications, and the safety risk of construction is small.
【技术实现步骤摘要】
跨座式单轨轨道梁安装的施工方法
本专利技术属于轨道梁施工
,具体涉及一种跨座式单轨轨道梁安装的施工方法。
技术介绍
轨道交通是指运营车辆需要在特定轨道上行驶的一类交通工具或运输系统,如由传统火车和标准铁路组成的铁路交通系统。随着火车和铁路技术的多元化发展,轨道交通呈现出越来越多的类型,不仅遍布于长距离的陆地运输,也广泛运用于中短距离的城市公共交通中。跨座式单轨交通属于中等运量轨道交通系统,其具有噪音低、爬坡能力强、转弯半径小、快速便捷、占地少、造价低、利于环境保护等优点,是现代化城市快速轨道立体交通的一种新形式,一般广泛应用于地铁、轻轨等轨道交通系统中。在跨座式单轨交通系统施工时,轨道梁即是承重结构,又是行走轨道,因此轨道梁的吊装施工是工程的难点和重点;尤其对于曲线段轨道梁,由于其为非直线结构,吊装时重心难以控制,且架设到桥墩后,临时固定困难,安全风险巨大;另外对于复杂地形轨道梁的架设和安装,由于可能会采用不同规格的轨道梁,如单榀轨道梁的长度、高度、重量及架设高度往往不同,现有的架桥机架设施工技术很难满足施工要求,因此轨道梁的吊装、架设、固定是跨座式轨道梁吊装的施工难题。
技术实现思路
针对上述问题,本专利技术提供了一种跨座式单轨轨道梁安装的施工方法,可解决轨道梁吊装时吊点、临时支撑、临时固定、线性调整困难的问题,能适应不同规格的轨道梁、复杂地形轨道梁的架设和安装,施工的安全风险较小。本专利技术通过下述技术方案实现。跨座式单轨轨道梁安装的施工方法,其特征在于包括如下步骤:1)轨道梁吊装:承台施工→墩柱施工→帽梁施工→支架搭设→轨道梁运输就位→安装稳定箍、 ...
【技术保护点】
1.跨座式单轨轨道梁安装的施工方法,其特征在于包括如下步骤:1)轨道梁吊装:承台施工→墩柱施工→帽梁施工→支架搭设→轨道梁运输就位→安装稳定箍、吊装箍→安装临时支座及永久支座→吊装→安装临时固定装置→松开吊绳;所述承台施工步骤中,承台(1)外围采用混凝土回填和混凝土硬化,且承台(1)及承台(1)外围的顶部预埋支架铁板(42)作为支架基础;所述支架搭设步骤中,采用钢管立柱支撑,先将钢管(41)底端焊接于所述预埋支架铁板(42)上,然后在钢管(41)之间安装剪刀撑(43)进行加固,并于钢管(41)顶端安装双拼工字钢(45)用于支撑轨道梁,双拼工字钢(45)的顶、底部用钢板(44)焊接固定;所述安装稳定箍、吊装箍步骤中,在轨道梁(5)的梁端处安装稳定箍(8)、吊装箍(7),稳定箍(8)、吊装箍(7)与轨道梁的梁面之间夹橡胶垫块;所述稳定箍(8)、吊装箍(7)均为螺栓连接可拆卸的槽钢环箍,所述稳定箍(8)的底部焊接铁片(81)作为支撑点,所述吊装箍(7)的顶部设置吊点;所述安装临时支座及永久支座步骤中,采用三向千斤顶(9)通过钢板焊接在双拼工字钢(45)上作为支撑和固定轨道梁(5)的临时支座; ...
【技术特征摘要】
1.跨座式单轨轨道梁安装的施工方法,其特征在于包括如下步骤:1)轨道梁吊装:承台施工→墩柱施工→帽梁施工→支架搭设→轨道梁运输就位→安装稳定箍、吊装箍→安装临时支座及永久支座→吊装→安装临时固定装置→松开吊绳;所述承台施工步骤中,承台(1)外围采用混凝土回填和混凝土硬化,且承台(1)及承台(1)外围的顶部预埋支架铁板(42)作为支架基础;所述支架搭设步骤中,采用钢管立柱支撑,先将钢管(41)底端焊接于所述预埋支架铁板(42)上,然后在钢管(41)之间安装剪刀撑(43)进行加固,并于钢管(41)顶端安装双拼工字钢(45)用于支撑轨道梁,双拼工字钢(45)的顶、底部用钢板(44)焊接固定;所述安装稳定箍、吊装箍步骤中,在轨道梁(5)的梁端处安装稳定箍(8)、吊装箍(7),稳定箍(8)、吊装箍(7)与轨道梁的梁面之间夹橡胶垫块;所述稳定箍(8)、吊装箍(7)均为螺栓连接可拆卸的槽钢环箍,所述稳定箍(8)的底部焊接铁片(81)作为支撑点,所述吊装箍(7)的顶部设置吊点;所述安装临时支座及永久支座步骤中,采用三向千斤顶(9)通过钢板焊接在双拼工字钢(45)上作为支撑和固定轨道梁(5)的临时支座;所述三向千斤顶(9)包括两个Z轴顶(91)、一个X轴顶(92)、一个Y轴顶(93);所述吊装步骤中,将吊装钢丝绳与轨道梁两端的吊装箍(7)通过吊点连接固定,轨道梁(5)被吊起后采用稳定箍(8)底部焊接的铁片(81)与三向千斤顶(9)的两个Z轴顶(91)对接稳固;所述三向千斤顶(9)采用数控调节,且轨道梁两端的三向千斤顶(9)的各轴顶可同步移动;所述安装临时固定装置步骤中,于轨道梁(5)两侧的双拼工字钢(45)上安装横向千斤顶(10),于横向千斤顶(10)与稳定箍(8)之间安装槽钢支撑架(11),作为轨道梁的临时固定装置;2)轨道梁安装:轨道梁线型调整→后浇段...
【专利技术属性】
技术研发人员:曾昭武,王竺,罗桂军,廖纪明,白小兵,
申请(专利权)人:中建五局土木工程有限公司,
类型:发明
国别省市:湖南,43
还没有人留言评论。发表了对其他浏览者有用的留言会获得科技券。