The invention relates to a shovel conveyor chute under the wall, which belongs to the technical field of mine safety, including the chute (1), which is characterized in that the chute (1) of the head (4) is arranged in the blocking wall (2), (2) the blocking wall ends are respectively fixed on the chute (1). The wellhead (4) on both sides of the car wall (2) from the chute (1) the distance is 1000mm, under the wall thickness of 500mm (2), (2) under the wall height is 600mm, under the wall (2) is arranged in the front collision cushion (3). The invention has simple structure and reasonable design, can greatly improve the operation level of the safety production, improve the safety of the ore drawing, and ensure the safety of the human vehicle, and has strong practicability.
【技术实现步骤摘要】
电铲运机溜矿井挡车墙
本专利技术涉及一种电铲运机溜矿井挡车墙,属于矿山安全
技术介绍
我国矿山系统中,电铲运机是矿山工作中所必不可少的设备,使用完毕后,均需要出矿,但是井下电铲运机在溜矿井处出矿时,很容易开进溜矿井里面,尤其是在电铲运机司机在操作失误或者疲劳麻木状态下进行作业时,存在很大的安全隐患,轻则设备损坏,严重时会造成人员伤亡。
技术实现思路
根据以上现有技术中的不足,本专利技术要解决的问题是:提供一种可以克服上述缺陷,结构简单,设计合理,能够大大提高安全生产的运作程度,提高出矿安全性,保证人车安全的电铲运机溜矿井挡车墙。本专利技术解决其技术问题所采用的技术方案是:所述的电铲运机溜矿井挡车墙,包括溜矿井,溜矿井的井口内设置挡车墙,挡车墙的两端分别固定在溜矿井的井口两侧,所述的挡车墙距离溜矿井的距离为1000mm,挡车墙的厚度为500mm,挡车墙高度为600mm,挡车墙的前端设置碰撞缓冲垫。电铲运机溜矿井挡车墙在井口设置挡车墙,能够简单有效的防止电铲运机进入溜矿井而存在的安全隐患,同时在挡车墙前端设置碰撞缓冲垫,既能够提高挡车墙的使用寿命,又可以减轻电铲运车与挡车墙碰撞所产生的损坏,结构简单,设计合理。进一步的优选,碰撞缓冲垫采用棉垫或弹簧垫。能够在电铲运车与挡车墙接触时进行缓冲,避免两者都受到损伤。进一步的优选,碰撞缓冲垫的厚度为挡车墙厚度的三分之一至二分之一。再保证不占用体积的前提下起到较好的缓冲效果。进一步的优选,溜矿井的井口上方设置防坠垫,防坠垫上层为棉层,防坠垫下层为弹簧层。提高安全性,防坠垫铰接在溜矿井的井口上方,通过支撑架支撑,在不 ...
【技术保护点】
一种电铲运机溜矿井挡车墙,包括溜矿井(1),其特征在于:溜矿井(1)的井口(4)内设置挡车墙(2),挡车墙(2)的两端分别固定在溜矿井(1)的井口(4)两侧,所述的挡车墙(2)距离溜矿井(1)的距离为1000mm,挡车墙(2)的厚度为500mm,挡车墙(2)高度为600mm,挡车墙(2)的前端设置碰撞缓冲垫(3)。
【技术特征摘要】
1.一种电铲运机溜矿井挡车墙,包括溜矿井(1),其特征在于:溜矿井(1)的井口(4)内设置挡车墙(2),挡车墙(2)的两端分别固定在溜矿井(1)的井口(4)两侧,所述的挡车墙(2)距离溜矿井(1)的距离为1000mm,挡车墙(2)的厚度为500mm,挡车墙(2)高度为600mm,挡车墙(2)的前端设置碰撞缓冲垫(3)。2.根据权利要求1所述的电铲运机溜...