The present invention discloses a new use of foreign steam start debugging method and system of supercritical unit, in the high and cold side production unit is added between the first isolation gate, in the high and cold production unit beside the isolation section with the connection pipeline, setting the contact contact door in the pipeline, in the new supercritical unit high side and the cold is added between the second isolation door; closing the first isolation door, open the door to contact, through the production unit adjacent to the new high supercritical unit provided by external steam temperature and pressure reduction after the use of steam pressure; external purging superheater and connecting pipes, the use of external steam purge, steady buck reheater and connecting pipes; new ultra supercritical steam turbine set to start debugging. The invention is not in the new ignition boiler under the condition of external steam provided by production units, complete sets of steam blowing and set to start the air load trial operation stage of the debugging work, reduce the number of boiler ignition of supercritical units and runs in the \non economic zone time.
【技术实现步骤摘要】
利用外来蒸汽启动调试新建超临界机组的方法与系统
本专利技术涉及火力燃煤发电机组领域,特别涉及一种利用外来蒸汽启动调试新建超临界机组的方法与系统。
技术介绍
新建超临界机组在吹管和空负荷试运阶段,大量设备需反复启停,汽水系统需反复冲洗,锅炉长时间处于油煤混烧或等离子助燃的低负荷、低效率工况,给电厂在基建成本和环保方面造成很大压力。现有的新建机组启动调试方法有:一、大多数超临界机组的启动调试都是按照单元机组的思路,通过锅炉点火自产汽,顺序地完成热态冲洗、蒸汽吹管、汽轮机冲转、电气试验、发电机并网带负荷等启动调试项目,外来蒸汽只是用做辅助汽源;二、少部分电厂增加了抽取邻机冷再蒸汽加热给水的系统,实现了锅炉不点火即完成超临界机组的热态冲洗工作,有不错的节能和环保效益,但因冷再抽汽量受限,蒸汽参数不能灵活调整,无法满足更多试运工况的需要。因此,在新建机组锅炉不点火的情况下,如何利用已投产机组提供的外来蒸汽,完成超临界机组蒸汽吹管和整套启动空负荷试运阶段的调试工作,仍是待解决的技术问题。
技术实现思路
为了克服上述现有技术的不足,本专利技术提供了一种利用外来蒸汽启动调试新建超临界机组的方法与系统,在新建机组锅炉不点火的情况下,利用已投产机组提供的外来蒸汽,完成机组蒸汽吹管和整套启动空负荷试运阶段的调试工作,减少了超临界机组中锅炉点火的次数和在“非经济区”运行的时间,有很大的经济和环保效益。本专利技术所采用的技术方案是:一种利用外来蒸汽启动调试新建超临界机组的方法,包括以下步骤:步骤一:在投产机组高压旁路阀与冷再间管道上加装第一隔离门,在投产机组高压旁路阀与冷再间隔离段加装 ...
【技术保护点】
一种利用外来蒸汽启动调试新建超临界机组的方法,其特征是,包括以下步骤:步骤一:在投产机组高压旁路阀与冷再间管道上加装第一隔离门,在投产机组高压旁路阀与冷再间隔离段加装联络管道,在所述联络管道上设置联络门,所述联络管道的末端连接新建超临界机组的冷再管道,在新建超临界机组高压旁路阀与冷再间管道上加装第二隔离门;步骤二:关闭第一隔离门,开启联络门,通过投产机组向新建超临界机组提供经投产机组高压旁路阀减温减压后的主蒸汽,将该主蒸汽作为新建超临界机组的外来蒸汽;步骤三:利用外来蒸汽降压吹扫过热器及连接管道,直至打靶合格;过热器吹扫合格后,利用外来蒸汽稳、降压吹扫再热器及连接管道,直至打靶合格;步骤四:进行新建超临界机组汽轮机整套启动调试。
【技术特征摘要】
1.一种利用外来蒸汽启动调试新建超临界机组的方法,其特征是,包括以下步骤:步骤一:在投产机组高压旁路阀与冷再间管道上加装第一隔离门,在投产机组高压旁路阀与冷再间隔离段加装联络管道,在所述联络管道上设置联络门,所述联络管道的末端连接新建超临界机组的冷再管道,在新建超临界机组高压旁路阀与冷再间管道上加装第二隔离门;步骤二:关闭第一隔离门,开启联络门,通过投产机组向新建超临界机组提供经投产机组高压旁路阀减温减压后的主蒸汽,将该主蒸汽作为新建超临界机组的外来蒸汽;步骤三:利用外来蒸汽降压吹扫过热器及连接管道,直至打靶合格;过热器吹扫合格后,利用外来蒸汽稳、降压吹扫再热器及连接管道,直至打靶合格;步骤四:进行新建超临界机组汽轮机整套启动调试。2.根据权利要求1所述的一种利用外来蒸汽启动调试新建超临界机组的方法,其特征是,所述步骤三中,利用外来蒸汽降压吹扫过热器及连接管道具体过程为:抽取新建超临界机组高压旁路阀的阀芯,使新建超临界机组高压旁路阀处于联通状态,关闭第二隔离门、给水门和临冲门,外来蒸汽通过新建超临界机组高压旁路阀经过热器、分离器、水冷壁、省煤器反充汽到给水门前,当外来蒸汽参数满足预设的吹管条件后,关闭联络门,开启临冲门,对过热器及连接管道降压吹扫,直至打靶合格。3.根据权利要求1所述的一种利用外来蒸汽启动调试新建超临界机组的方法,其特征是,所述步骤三中,利用外来蒸汽降压吹扫再热器及连接管道的具体过程为:过热器吹扫合格后,外来蒸汽通过新建超临界机组高压旁路阀经过热器、分离器、水冷壁、省煤器反充汽到给水门前,当外来蒸汽参数满足预设的吹管条件后,关闭联络门,开启第二隔离门,对再热器及连接管道降压吹扫,直至打靶合格。4.根据权利要求1所述的一种利用外来蒸汽启动调试新建超临界机组的方法,其特征是,所述步骤三中,利用外来蒸汽稳压吹扫再热器及连接管道的具体过程为:过热器吹扫合格后,恢复新建超临界机组高压旁路阀的阀芯,并关闭新建超临界机组高压旁路阀,开启第二隔离门和联络门,通过新建超临界机组高压旁路阀控制外来蒸汽参数,对再热器及连接管道稳压吹扫,直至打靶合格。5.根据权利要求1所述的一种利用外来蒸汽启动调试新建超临界机组的方法,其特征是,所述步骤四中,新建超临界机组汽轮机整套启动调试的具体过程为:步骤4.1:锅炉热态冲洗和空冷岛冲洗;步骤4.2:汽轮机冲转;步骤4.3:进行机组并网前电气试验和厂用电切换试验;步骤4.4:对低压加热器、2号高压加热器、3号高压加热器进行试投和冲洗;步骤4.5:进行汽轮机的超速试验和再热器安全门校验。6.根据权利要求5所述的一种利用外来蒸汽启动调试新建超临界机组的方法,其特征是,所述步骤4.1中,锅炉热态冲洗的具体过程为:(1)开启第一隔离门和联络门,通过投产机组向新建超临界机组提供冷再蒸汽;(2)开启新建超临界机组中第二隔离门,向再热器及冷再用户提供蒸汽;(3)开启冷再向辅汽联箱提供蒸汽,再通过辅汽联箱向除氧器提供蒸汽,将给水加热到100℃以上;(4)通过辅汽联箱向轴封提供蒸汽,建立机组真空;(5)开启冷再向2号高压加热器提供蒸汽,将给水加热到190℃以上,对锅炉进行热态冲洗,直至水质满足预设的热态冲洗合格条件;空冷岛冲洗的具体过程为:(1)关闭第一隔离门,开启联络门,投产机组向新建超临界机组提供经投产机组的高压旁路阀减温减压后的外来蒸汽;(2)开启新建机组第二隔...
【专利技术属性】
技术研发人员:部俊锋,张杰,李华东,
申请(专利权)人:山东中实易通集团有限公司,
类型:发明
国别省市:山东,37