A substation of assembled steel structure housing, which comprises a wall body and a roof, and is characterized in that a H type steel roof beam and H type steel beam wall, roof beam and wall beam through a connecting piece connected into a building frame roof beam and wall beam are respectively connected with the C type steel purlin, wall and roof are in outside, color steel plate and sandwich EPS polystyrene insulation layer is arranged on the inner surface and the outer surface of the wall connection between the wall of C type steel purlin roof, roof connection in C steel purlin. The utility model has the advantages of fast construction speed, short construction period, reduce wet work, protect the environment, reduce pollution, building space layout flexibility, high strength, light weight, good seismic performance, can meet the different requirements of multi-functional substation.
【技术实现步骤摘要】
本技术属于一种变电站房屋结构,特别是一种变电站装配式钢结构房屋。
技术介绍
传统上的房屋砖混结构对模数和层高的要求较为严格,一般变电站房屋采用钢筋 混凝土结构虽然比较普遍,但是由于体积庞大,施工周期长,湿作业及其养护对环境、温度 的要求高,重量大,在冬季寒冷干燥的北方基本无法施工作业,进而影响了冬季电力设施建 设。
技术实现思路
本技术的目的是提供一种变电站装配式钢结构房屋,施工速度快,建设工期 短,强度高,自重轻,抗震性能高,减少湿作业,保护环境,减少污染,建筑空间布置灵活,能 满足不同的变电站多功能要求。本技术的目的是通过如下技术方案实现的它包括墙体和屋顶,其特征是 设置H型钢屋顶梁和H型钢墙面梁,屋顶梁和墙面梁通过连接件连接成房屋框架,屋顶梁和 墙面梁上分别连接C型钢檩条,墙体和屋顶均为内、外面彩钢板,在内外面之间设置EPS夹 心苯板保温层,墙体连接在墙面C型钢檩条上,屋顶连接在屋顶C型钢檩条上。在屋顶的内侧组装石棉板的绝缘吊顶,在墙体的内侧组装石膏板绝缘墙面。本技术优点是施工速度快,建设工期短,减少湿作业,保护环境,减少污染, 建筑空间布置灵活,强度高,自重轻,抗震性能好,能满足不同的变电站多功能要求。附图说明图1是本技术结构示意图一(屋顶剖视)。图2是本技术结构示意图二 (墙体剖视)。具体实施方式见图1、2,具体结构如下设置H型钢屋顶梁5. 1和H型钢墙面梁5. 2,屋顶梁5. 1 和墙面梁5. 2通过连接件连接成房屋框架,屋顶梁5. 1和墙面梁5. 2上分别连接C型钢檩 条4,墙体和屋顶均为内、外面彩钢板1、3,在内外面之间设置EPS夹心苯板保 ...
【技术保护点】
1.一种变电站装配式钢结构房屋,它包括墙体和屋顶,其特征是:设置H型钢屋顶梁和H型钢墙面梁,屋顶梁和墙面梁通过连接件连接成房屋框架,屋顶梁和墙面梁上分别连接C型钢檩条,墙体和屋顶均为内、外面彩钢板,在内外面之间设置EPS夹心苯板保温层, 墙体连接在墙面C型钢檩条上,屋顶连接在屋顶C型钢檩条上。
【技术特征摘要】
还没有人留言评论。发表了对其他浏览者有用的留言会获得科技券。