The invention discloses an anchor bolt construction technology to ensure safety and quality, which relates to the field of construction technology, mainly solves the problems of block dropping and continuous tower cavity after excavation of supporting face, including the following steps: S1, preparation before construction, including construction survey and grout disposition; S2, advance small conduit construction; S3, face closure; S4, rock drilling platform car positioning; S5, drilling hole closure; S6, hole closure; The opening position, S7, grouting reinforcement; S8, grouting parameter design; S9, grouting technology; S10, excavation operation; excavation operation after grouting, and check whether the effect of grouting diffusion achieves the purpose of strengthening surrounding rock; The invention can effectively overcome the problems of block dropping and continuous tower cavity after the excavation of supporting face, solve the hidden safety hazards in the construction site, and effectively ensure the construction. Quality, suitable for promotion.
【技术实现步骤摘要】
一种保证安全、质量的锚杆施工工艺
本专利技术涉及施工
,具体是一种保证安全、质量的锚杆施工工艺。
技术介绍
隧址区地表水多为雨季雨水沿山坡两侧汇集径流,多属季节性溪流,水量较小。地下水按储藏条件及水动力特性可分为松散层孔隙水和基岩裂隙水两个类型。隧址区位于中纬度亚欧大陆腹地,属温带大陆性干旱气候,主要特征是:干旱少雨,光照丰富,年、日温差大,降水分布不均;春季多风,冷暖多变,夏季酷热、蒸发强,秋季晴朗、降温迅速,冬季寒冷、低空气层稳定。隧址区总体属于高中山地貌区,局部分布丘陵地貌及山间沟谷地貌,是典型的高中山深谷类型。在隧址区施工过程中,开挖后掌子面会存在掉块、连续塌腔的问题,初期支护完成后拱顶可能存在空洞,施工现场存在安全、质量隐患。
技术实现思路
本专利技术的目的在于提供一种保证安全、质量的锚杆施工工艺,以解决上述
技术介绍
中提出的问题。为实现上述目的,本专利技术提供如下技术方案:一种保证安全、质量的锚杆施工工艺,包括以下步骤:S1、施工前期准备,包括施工测量、浆液配置;S2、超前小导管施工,超前小道管长度为4-6m,环向35-45cm,打设角度控制在6-10°,打设范围隧道中线115-125°,打设完成后进行开挖作业,开挖1.8-2.2m临空面,为三臂凿岩台车打设自进式锚杆提供空间;S3、掌子面封闭;掌子面封闭分为两步:第一步,在打设锚杆竖向45-53cm范围内喷射一层水泥浆,然后对整个掌子面进行C25喷射混凝素喷8-12cm,素喷后形成一个1:0.2坡度;S4、凿岩台车就位;掌子面素喷完成后三臂凿岩台车推进至掌子面,连接水电,检查机械运转情况后进行 ...
【技术保护点】
1.一种保证安全、质量的锚杆施工工艺,其特征在于,包括以下步骤:S1、施工前期准备,包括施工测量、浆液配置;S2、超前小导管施工,超前小道管长度为4‑6m,环向35‑45cm,打设角度控制在6‑10°,打设范围隧道中线115‑125°,打设完成后进行开挖作业,开挖1.8‑2.2m临空面,为三臂凿岩台车打设自进式锚杆提供空间;S3、掌子面封闭;S4、凿岩台车就位;掌子面素喷完成后三臂凿岩台车推进至掌子面,连接水电,检查机械运转情况后进行钻孔作业;S5、钻孔;钻机就位后,根据测量人员放出的孔位进行钻孔作业;S6、封堵孔口位置,距离孔口1.3‑1.7m范围内孔壁缠绕麻丝打入围岩,并采用泡沫胶注入围岩内;S7、注浆加固;浆液类型使用水泥+水玻璃的双液浆,注浆压力2.0Mpa;S8、注浆参数设计;S9、注浆工艺;在进行注浆施工之前,首先完成各种机械设备的检查、仪器仪表的检验或标定,完成浆液材料的性能试验,确定合格后方可进行注浆作业;S10、注浆结束后进行开挖作业。
【技术特征摘要】
1.一种保证安全、质量的锚杆施工工艺,其特征在于,包括以下步骤:S1、施工前期准备,包括施工测量、浆液配置;S2、超前小导管施工,超前小道管长度为4-6m,环向35-45cm,打设角度控制在6-10°,打设范围隧道中线115-125°,打设完成后进行开挖作业,开挖1.8-2.2m临空面,为三臂凿岩台车打设自进式锚杆提供空间;S3、掌子面封闭;S4、凿岩台车就位;掌子面素喷完成后三臂凿岩台车推进至掌子面,连接水电,检查机械运转情况后进行钻孔作业;S5、钻孔;钻机就位后,根据测量人员放出的孔位进行钻孔作业;S6、封堵孔口位置,距离孔口1.3-1.7m范围内孔壁缠绕麻丝打入围岩,并采用泡沫胶注入围岩内;S7、注浆加固;浆液类型使用水泥+水玻璃的双液浆,注浆压力2.0Mpa;S8、注浆参数设计;S9、注浆工艺;在进行注浆施工之前,首先完成各种机械设备的检查、仪器仪表的检验或标定,完成浆液材料的性能试验,确定合格后方可进行注浆作业;S10、注浆结束后进行开挖作业。2.根据权利要求1所述的保证安全、质量的锚杆施工工艺,其特征在于,步骤S1中,测量人员要准确定出钻孔孔位并记录;浆液配置分别为10min凝固、15min凝固、20min凝固双液浆配比。3.根据权利要求2所述的保证安全、质量的锚杆施工工艺,其特征在于,步骤S3中,掌子面封闭分为两步:第一步,在打设锚杆竖向45-53cm范围内喷射一层水泥浆,然后对整个掌子面进行C25喷射混凝素喷8-12cm,素喷后形成一个1:0.2坡度。4.根据权利要求3所述的保证安全、质量的锚杆施工工艺,其特征在于,步骤S5中,钻孔的具体方法为:根据隧道中心线120°范围内,间距0.3-0.5m,进行钻孔,单个钻孔分为2个阶段,钻进长度9-11m,外插脚控...
【专利技术属性】
技术研发人员:邢冠林,周思峰,余昌平,杨玉平,黄海伦,孙井建,