The invention relates to the technical field of wind power transmission, which is a post-evaluation method of transmission engineering project based on the life cycle theory. The characteristics of the post-evaluation method are that the total cost and the total benefit obtained during the whole life cycle of the energy storage system are analyzed by considering the cost and benefit of the project with the life cycle theory. And income are analyzed separately to find out the main cost types and income types, and calculate them separately; finally, the project income minus the project cost, get the total benefit of the whole life cycle of the project, and analyze the benefits brought by different energy storage systems. Based on the life cycle assessment theory, the invention verifies that the transmission project has obvious effect on reducing the blocking discarded air volume and improving the income. The method is scientific, reasonable, applicable, accurate and effective.
【技术实现步骤摘要】
基于全寿命周期理论的输电工程项目后评价方法
本专利技术涉及风电输送
,特别涉及一种基于全寿命周期理论的输电工程项目后评价方法。
技术介绍
如今,我国的经济水平正处于一个飞速发展的时期,越来越多项目建设的展开,许多企业的兴办以及人们生活水平的提高,随之而来的是各种电器设备的使用增加,这些改变都导致用电量得到了的大幅增加。各行业的生产用电和居民生活的用电负荷正在快速持续性增长,使得现有的输电线路结构薄弱环节逐渐显现出来,改造或新建输电通道刻不容缓。为了保证项目投资效益的提升,以及全面了解项目实际情况与预期情况的差异,输电工程项目急需进行科学而又有效的后评价方法。输电工程项目后评价是项目可行性研究的有机组成部分和重要内容,具有项目投资大、建设规模大、周期长、参与单位多、工程管理难度大、社会协调因素多等特点。传统的输电工程后评价方案评价的重心一般在电网项目的前期投入成本,忽视项目实施后的运行、维护及报废等诸多后续环节,暴露出电网规划环节与工程施工、运行与维护及设备报废处理等多个环节之间联系薄弱的弊端。如今的输电工程项目往往采用主观评价法或者是客观评价法去评价,但不论是主观评价法还是客观评价法,其评价结果的准确率都较低。
技术实现思路
本专利技术的目的是克服现有技术的不足,提供一种科学合理,适用性强,准确率高,效果佳基于全寿命周期理论的输电工程项目后评价方法。实现本专利技术的目的采用的技术方案是,一种基于全寿命周期理论的输电工程项目后评价方法,其特征在于,它包含以下步骤:1)计算全寿命周期成本:全寿命周期成本包括投资费用和维持运行费用,所述投资费用指的是购买设备的 ...
【技术保护点】
1.一种基于全寿命周期理论的输电工程项目后评价方法,其特征在于,它包含以下步骤:1)计算全寿命周期成本:全寿命周期成本包括投资费用和维持运行费用,所述投资费用指的是购买设备的投资成本;维持运行费用指的是运行成本、检修维护成本、故障成本和退役处置成本,全寿命周期成本的计算公式为:LCC=IC+OC+MC+FC+DC (1)式中,LCC为全寿命周期成本,IC为投资成本,OC为运行成本,MC为检修维护成本,FC为故障成本,DC为退役处置成本;采用净年值(NAV)对储能系统全寿命周期成本进行计算,输电线路成本的计算按照静态回收考虑,净年值是通过资金等值换算来实现的,将项目净年值分摊到寿命期内的每一年,从第1年到第n年的等额年值,其计算公式为:NAV=LCC×i(1+i)n÷[(1+i)n‑1] (2)式中,NAV为净年值,i为净年值的年份,n为储能系统寿命,购买设备的投资成本发生在买进设备的那一年,即计算周期的起始年份为基准年份,主要由购买设备费用和安装调试费用构成,由于安装调试费用与购买设备费用相比费用较少,可以忽略不计,故其计算公式为:IC=ICp (3)ICp=cpBe+cc ...
【技术特征摘要】
1.一种基于全寿命周期理论的输电工程项目后评价方法,其特征在于,它包含以下步骤:1)计算全寿命周期成本:全寿命周期成本包括投资费用和维持运行费用,所述投资费用指的是购买设备的投资成本;维持运行费用指的是运行成本、检修维护成本、故障成本和退役处置成本,全寿命周期成本的计算公式为:LCC=IC+OC+MC+FC+DC(1)式中,LCC为全寿命周期成本,IC为投资成本,OC为运行成本,MC为检修维护成本,FC为故障成本,DC为退役处置成本;采用净年值(NAV)对储能系统全寿命周期成本进行计算,输电线路成本的计算按照静态回收考虑,净年值是通过资金等值换算来实现的,将项目净年值分摊到寿命期内的每一年,从第1年到第n年的等额年值,其计算公式为:NAV=LCC×i(1+i)n÷[(1+i)n-1](2)式中,NAV为净年值,i为净年值的年份,n为储能系统寿命,购买设备的投资成本发生在买进设备的那一年,即计算周期的起始年份为基准年份,主要由购买设备费用和安装调试费用构成,由于安装调试费用与购买设备费用相比费用较少,可以忽略不计,故其计算公式为:IC=ICp(3)ICp=cpBe+ccCe(4)式中:ICp为购买设备费用;ICi为安装调试费用;cp为储能功率价格,元/MW;Be为储能系统功率,MW;cc为储能系统容量价格,元/MWh;Ce为储能系统功率,MWh,储能系统的运行成本主要由设备能耗费用构成,其计算公式为:OC=(Pc-Pd)×8760×α(5)式中:Pd为储能放电效率;Pc为储能充电效率;α为风电成本电价,储能系统的检修成本主要由解体检修和检修维护两部分构成,其成本检修周期和单次的检修费用决定,第n年的检修费用计算公式如下:式中:MCn0为单次解体检修费用,MCnr为单次检修维护费用,其中,n0和nr分别表示第n年是否对储能系统进行检修,其取值由各自的检修维护周期T0和Tr决定,为0或1,具体为:n能整除T0时,n0取1,否则取0;nr的取值与n0类似,储能系统的故障成本主要包括故障检修费用和故障损失费用,为计算方便,以故障损失费用近似代替故障成本,故障损失费主要由停电损失费用决定,故第n年的故障成本可用下面公式计算FCn=λPFtFα(7)式中:λ为储能系统故障率,PF为故障时储能系统损失功率,tF为故障时储能系统平均停止工作时间,α为风电成本电价,储能系统的退役处置...
【专利技术属性】