一种预埋注浆管注浆加固围岩松动区方法技术

技术编号:16171905 阅读:43 留言:0更新日期:2017-09-09 00:24
一种预埋注浆管注浆加固围岩松动区方法,包括钢拱架(3)、注浆管(2)、L型连接筋(1),其特征在于:钢拱架(3)翼缘边设置注浆管(2),注浆管(2)斜插到钢拱架(3)背后的裸露围岩面节理裂隙处,通过L型连接钢筋(1)将钢拱架(3)和注浆管(2)焊接牢固,注浆管(2)外露于喷射混凝土表面少许,以便待喷射混凝土强度满足要求后进行注浆作业。

Method for reinforcing surrounding rock loosing zone by grouting with pre embedded grouting pipe

A kind of embedded grouting pipe grouting reinforcement method of surrounding rock loose zone, including steel arch (3), (2), the grouting pipe of L type connecting rib (1), which is characterized in that: the steel arch (3) flange arranged on the edge of the grouting pipe grouting pipe (2), (2) inclined to steel arch (3) the bare rock surface jointed place behind the connection bar by L (1) (3) of the steel arch and grouting pipe (2) solid welding, grouting pipe (2) exposed on the surface of concrete to be a jet grouting work of concrete strength meet the requirements.

【技术实现步骤摘要】
一种预埋注浆管注浆加固围岩松动区方法
本专利技术涉及一种预埋注浆管注浆加固围岩松动区装置,适用于隧道初期支护施作完成后对松动圈围岩进行注浆加固。
技术介绍
随着我国交通建设的飞速发展,出现了大量的铁路、公路隧道,同时出现了越来越多的破碎软岩大变形隧道。由于开挖过程中坍塌掉块,致使无法很好的保持开挖尺寸轮廓线,超挖现象严重,围岩松动圈扩大,导致初期支护受力增大、开裂、掉块等,此时就需要对围岩松动区进行注浆补强。喷射混凝土虽有良好的可塑性,但由于喷射盲区的影响,喷射混凝土无法完全填充钢拱架背后空间,有时喷射混凝土与隧道围岩洞壁的接触状态进一步恶化,初期支护背后出现较大的空洞,不利于使初期支护与围岩共同变形,容易使初期支护产生应力集中,发生裂缝、掉块等现象,对后续施工产生不利的影响。隧道的建设往往在地下水位以下,初期支护是隧道防水的第一道防线,但由于围岩与初期支护之间接触不良,会使地下水储存于初期支护与围岩之间的缝隙和空洞之中,随着水压的增长,最终导致初期支护发生渗漏水甚至掉块。以往的施工案例中,若要对初期支护背后空洞、松动区进行注浆处理,需要在初期支护施工完成后,在初期支护上钻孔安装注浆本文档来自技高网...
一种预埋注浆管注浆加固围岩松动区方法

【技术保护点】
一种预埋注浆管注浆加固围岩松动区方法,包括钢拱架(3)、注浆管(2)、L型连接筋(1),其特征在于:钢拱架(3)翼缘边设置注浆管(2),注浆管(2)斜插到钢拱架(3)背后的裸露围岩面节理裂隙处,通过L型连接钢筋(1)将钢拱架(3)和注浆管(2)焊接牢固,注浆管(2)外露于喷射混凝土表面少许,以便待喷射混凝土强度满足要求后进行注浆作业。

【技术特征摘要】
1.一种预埋注浆管注浆加固围岩松动区方法,包括钢拱架(3)、注浆管(2)、L型连接筋(1),其特征在于:钢拱架(3)翼缘边设置注浆管(2),注浆管(2)斜插到钢拱架(3)...

【专利技术属性】
技术研发人员:刘雪冬范春宇邵志远徐松李德武马学宁孙铭泽
申请(专利权)人:中铁二十二局哈尔滨铁路建设集团有限责任公司中铁二十二局集团有限公司兰州交通大学
类型:发明
国别省市:黑龙江,23