An assembly to compensate for deformation tunnel supporting method, which belongs to the technical field of civil engineering construction, mainly used for tunnel supporting engineering settlement deformation of the high risk source strict subway tunnel crossing or weak stratum. In the excavation process of underground tunnel excavation, the strength of the initial support system can be increased by using this method to support. By changing the supporting structure of the rotary screw, the displacement of the initial support of the tunnel to the external direction of the tunnel is changed, and the function of compensating deformation is achieved. So as to decrease the shrinkage deformation of tunnel surrounding rock, reduce the surface subsidence, and finally reduce the influence of tunnel excavation on the surrounding environment safety. In addition, this method can also realize the strengthening of the local two lining strength. On the other hand, through the removable function of the support device, the material reuse can be realized, the construction cost is reduced, and the economic benefit of the construction process is improved.
【技术实现步骤摘要】
一种装配式补偿变形的暗挖隧道支护方法
本专利技术属于土木工程施工
,主要用于软弱地层或隧道穿越对沉降变形要求严格的高风险源的地铁暗挖隧道支护工程。
技术介绍
在城市地铁暗挖隧道开挖过程中,常采用的施工工法主要包括盾构法、浅埋暗挖法、矿山法、新奥法等。由于开挖过程对土体造成了扰动,隧道周围土体向临空面产生蠕动变形,为了保证在开挖过程中隧道内部的稳定同时减小地表变形,必须采用适当的支护方法。除盾构法外,实践中一般经常采用的支护方法是初期支护加二次衬砌的复合式衬砌支护方法。在软弱地层中,隧道在施做完初期支护后,隧道内部往往会产生较大变形。必要时就需要用钢管和工字钢等型钢支撑构件来撑住变形较大部位。以上支护方法存在着自身的不足。(1)支护方式属于被动支撑,支撑效果不理想,对减小地层变形方面效果较差。尤其是在隧道穿越对地表沉降变形要求严格的高风险源的地铁隧道支护过程中,这一缺点就变得更加明显。(2)采用型钢构件等被动支撑无法达到补偿变形作用,在隧道变形较大位置只能防止变形继续发生,而不能达到补偿变形作用。(3)在隧道施工完成之后拆除隧道内支撑结构时会造成材料浪费,回收率较低。
技术实现思路
暗挖隧道台阶法开挖隧道的过程中,先进行小导管超前注浆(1),再开挖上部台阶土体(2),施做初期支护(3),打设锁脚锚杆(4),开挖下台阶土体(5),最后施做下部初期支护(3)。台阶留设长度为3~5m。台阶法开挖隧道横剖面图如图1所示,台阶法开挖隧道支护纵向剖面图如图2所示,其中第一榀钢支撑(6)设置在开挖掌子面附近。本专利技术的技术方案与关键技术是:待下部初期支护施做完成后,在 ...
【技术保护点】
一种装配式补偿变形的暗挖隧道支护方法,暗挖隧道台阶法开挖隧道的过程中,先进行小导管超前注浆(1),再开挖上部台阶土体(2),施做初期支护(3),打设锁脚锚杆(4),开挖下台阶土体(5),最后施做下部初期支护(3);台阶留设长度为3~5m,其中第一榀钢支撑(6)设置在开挖掌子面附近;其特征在于:待下部初期支护施做完成后,在距离下台阶1m的位置架设环向钢支撑,其中环向钢支撑为带有防缩进错动卡槽的U型钢,每榀环向钢支撑之间纵向间距为1m;环向钢支撑包括上部U型钢支撑(7)、下部U型钢支撑(8)、左侧U型钢支撑(9)和右侧U型钢支撑(10);在隧道开挖并且施做初期支护后安装环向钢支撑,环向钢支撑全部架设在隧道初期支护(3)上,依次安装环向钢支撑中的上部U型钢支撑(7)、下部U型钢支撑(8)、左侧U型钢支撑(9)和右侧U型钢支撑(10),并在钢支撑背后喷射混凝土使钢支撑与隧道密贴;左侧横向丝杠(12)和右侧横向丝杠(13)通过套在竖向丝杠(11)中部的丝杠连接器(14)连接;竖向丝杠(11)和左侧横向丝杠(12)、右侧横向丝杠(13)采用顶部带有螺纹的Φ200的钢管,竖向丝杠设计长度为D,左侧横 ...
【技术特征摘要】
1.一种装配式补偿变形的暗挖隧道支护方法,暗挖隧道台阶法开挖隧道的过程中,先进行小导管超前注浆(1),再开挖上部台阶土体(2),施做初期支护(3),打设锁脚锚杆(4),开挖下台阶土体(5),最后施做下部初期支护(3);台阶留设长度为3~5m,其中第一榀钢支撑(6)设置在开挖掌子面附近;其特征在于:待下部初期支护施做完成后,在距离下台阶1m的位置架设环向钢支撑,其中环向钢支撑为带有防缩进错动卡槽的U型钢,每榀环向钢支撑之间纵向间距为1m;环向钢支撑包括上部U型钢支撑(7)、下部U型钢支撑(8)、左侧U型钢支撑(9)和右侧U型钢支撑(10);在隧道开挖并且施做初期支护后安装环向钢支撑,环向钢支撑全部架设在隧道初期支护(3)上,依次安装环向钢支撑中的上部U型钢支撑(7)、下部U型钢支撑(8)、左侧U型钢支撑(9)和右侧U型钢支撑(10),并在钢支撑背后喷射混凝土使钢支撑与隧道密贴;左侧横向丝杠(12)和右侧横向丝杠(13)通过套在竖向丝杠(11)中部的丝杠连接器(14)连接;竖向丝杠(11)和左侧横向丝杠(12)、右侧横向丝杠(13)采用顶部带有螺纹的Φ200的钢管,竖向丝杠设计长度为D,左侧横向丝杠(12)和右侧横向丝杠(13)设计长度为D/2,其中,D为隧道开挖直径;竖向丝杠(11)、左侧横向丝杠(12)、右侧横向丝杠(13)和环向钢支撑之间的连接部分采用补偿变形预制节点构件。2.根据权利要求1所述的一种装配式补偿变形的暗挖隧道支护方法,其特征在于:补偿变形预制节点构件分为顶部补偿变形预制节点构件、底部补偿变形预制节点构件、左侧补偿变形预制节点构件和右侧补偿变形预制节点构件;顶部补偿变形预制节点构件包括螺纹顶升套管(15)、U型钢固定槽(16)、螺纹水平套管(17);两榀钢支撑之间用四根相互平行的拉杆(18)与补偿变形预制节点构件连接形成整体;底部补偿变形预制节点构件包括无螺纹固定套管(19)、U型钢固定槽(16)、螺纹水平套管(17);左侧补偿变形预制节点构件和右侧补偿变形预制节点构件的结构与上部结构相同;上部U型钢支撑(7)通过U型钢固定槽(16)、螺纹顶升套管(15)与竖向丝杠(11)的一端连接,下部U型钢支撑(8)通过U型钢固定...
【专利技术属性】
技术研发人员:姚爱军,卢健,高秀清,荆海丰,张剑涛,周一君,
申请(专利权)人:北京工业大学,
类型:发明
国别省市:北京,11