The invention discloses a construction method of electric well and traction pipeline, which comprises the following steps: S1. Excavation of foundation pit earthwork of electric well, excavation of foundation pit earthwork by excavator, measurement of elevation of trench bottom by the surveyor, and slope repair by manual cooperation. When the excavator excavates earthwork, at least 10cm thick earthwork shall be left at the foundation pit base, and the foundation pit shall be manually repaired by shovel, and the foundation pit acceptance is qualified After pouring the concrete cushion, the construction method provided by the invention effectively speeds up the problems that there are a large number of construction wells and traction pipes are not connected and the construction period is delayed long in the process of passing the road traction pipeline construction, which is not only simple and easy to operate, but also can speed up the project progress and shorten the project period, improve the construction quality and reduce the construction cost.
【技术实现步骤摘要】
一种电力工井及牵引管道的施工方法
本专利技术专利为一种埋地电力工井及涉及地下牵引管道的施工方法,采用电力工井先施工、牵引管后牵引施工的施工方法。
技术介绍
建设城市管线下地,是新型城镇化发展的必然要求,是补齐城市地下基础设施建设“短板”、打造经济发展新动力的一项重大民生工程,也是解决“马路拉链”问题的有效途径。电力等管线纳入地下预埋是城市管线建设发展方式的重大转变,有利于提高电力等管线运行的可靠性、安全性和使用寿命;对节约利用城市地面土地和地下空间,提高城市综合承载能力起到关键性作用,对促进城市建设可持续发展具有重要意义。
技术实现思路
本专利技术提出的解决方法是采用电力工井先施工再通过预留牵引管施工洞口,在电力工井施工结束后进行牵引管施工后进行封堵的施工方法,可以提高具有过路牵引管的电力工井的施工速度,达到减少施工总工期时间的目的。为实现上述目的,本专利技术提供如下技术方案:一种电力工井及牵引管道的施工方法,包括如下步骤:S1、电力工井基坑土方开挖采用挖掘机开挖基坑土方,测量人员测量槽底高程,人工配合进行铲底修坡,挖掘机挖除土方时在基坑的基底留至少10cm厚度的土方,人工对基底进行铲修,基坑验收合格后,浇筑混凝土垫层;S2、电力工井筏板基础施工1)钢筋加工及安装根据图纸尺寸计算钢筋下料长度,对钢筋进行矫直处理,对钢筋进行表面处理去除表面的油渍、漆皮、鳞绣;绑扎钢筋时,检查钢筋的直径、相邻之间的间距、位置和搭接长度,各受力钢筋之间绑扎接头位置相互错开 ...
【技术保护点】
1.一种电力工井及牵引管道的施工方法,其特征在于:包括如下步骤:/nS1、电力工井基坑土方开挖/n采用挖掘机开挖基坑土方,测量人员测量槽底高程,人工配合进行铲底修坡,挖掘机挖除土方时在基坑的基底留至少10cm厚度的土方,人工对基底进行铲修,基坑验收合格后,浇筑混凝土垫层;/nS2、电力工井筏板基础施工/n1)钢筋加工及安装/n根据图纸尺寸计算钢筋下料长度,对钢筋进行矫直处理,对钢筋进行表面处理去除表面的油渍、漆皮、鳞绣;绑扎钢筋时,检查钢筋的直径、相邻之间的间距、位置和搭接长度,各受力钢筋之间绑扎接头位置相互错开,采用铅丝进行钢筋绑扎,绑扎头和外露头均向下弯曲;/n2)模板/n模板支撑顺直、牢固、拼缝严密,在底板侧模安装前,对素砼垫层面进行清洗,根据井边线样桩划出模板内侧位置的墨线,根据浇筑高度立模进行支撑固定,模板的表面平整、接缝严密,待砼达到设计强度后对模板进行拆除;/n3)混凝土浇注/n在浇注混凝土时使用插入式振捣器进行振捣,底板混凝土采用连续浇筑的方式,混凝土的表面平整且石子不露出混凝土的上表面;/nS3、电力工井牵引预留孔的留设/n在工井前后在图纸尺寸的基础上各边外扩100m ...
【技术特征摘要】
1.一种电力工井及牵引管道的施工方法,其特征在于:包括如下步骤:
S1、电力工井基坑土方开挖
采用挖掘机开挖基坑土方,测量人员测量槽底高程,人工配合进行铲底修坡,挖掘机挖除土方时在基坑的基底留至少10cm厚度的土方,人工对基底进行铲修,基坑验收合格后,浇筑混凝土垫层;
S2、电力工井筏板基础施工
1)钢筋加工及安装
根据图纸尺寸计算钢筋下料长度,对钢筋进行矫直处理,对钢筋进行表面处理去除表面的油渍、漆皮、鳞绣;绑扎钢筋时,检查钢筋的直径、相邻之间的间距、位置和搭接长度,各受力钢筋之间绑扎接头位置相互错开,采用铅丝进行钢筋绑扎,绑扎头和外露头均向下弯曲;
2)模板
模板支撑顺直、牢固、拼缝严密,在底板侧模安装前,对素砼垫层面进行清洗,根据井边线样桩划出模板内侧位置的墨线,根据浇筑高度立模进行支撑固定,模板的表面平整、接缝严密,待砼达到设计强度后对模板进行拆除;
3)混凝土浇注
在浇注混凝土时使用插入式振捣器进行振捣,底板混凝土采用连续浇筑的方式,混凝土的表面平整且石子不露出混凝土的上表面;
S3、电力工井牵引预留孔的留设
在工井前后在图纸尺寸的基础上各边外扩100mm进行预留孔的制作,预留孔之间前后对应在一条直线上,预留时在墙板中间采用方木卡槽,并在预留孔四周预留钢...
【专利技术属性】
技术研发人员:汪为巍,
申请(专利权)人:中国十七冶集团有限公司,
类型:发明
国别省市:安徽;34