The invention relates to a construction method of a tool-type advanced hanging formwork system with post-pouring belt, which mainly includes: floor bottom formwork installation, concrete cushion block installation, advanced hanging formwork support installation, dressing concrete non-removal formwork installation, steel bar binding, comb wood formwork and cover plate installation, floor concrete pouring and maintenance, comb wood formwork removal, post-pouring belt concrete pouring and maintenance, demolition. Advance lifting formwork support and other steps. The front suspension formwork bracket fixed on the concrete pad is used to carry out the front suspension formwork for the rear pouring belt before the floor is poured. When the demolition of the formwork is completed, the rear pouring belt does not need to demolish the formwork and re-suspension formwork, thus effectively solving the problems of the formwork support device for the floor and the post pouring belt, erecting, removing and re-suspending formwork for the latter pouring belt, and having better economic and social benefits.
【技术实现步骤摘要】
后浇带工具式超前吊模系统的施工方法
本专利技术涉及一种后浇带工具式超前吊模系统的施工方法,属于主体结构后浇带施工
,适用于建筑物后浇带混凝土施工,尤其适用于后浇带位置钢筋密集,楼板施工中对后浇带影响大,后浇带内建筑垃圾处理复杂的工程。
技术介绍
后浇带是在建筑物中设置的临时施工缝,该缝保留一段时间后再浇筑。也就是将原来“超长”的平面“化整为零”,使其能在较短的时间内完成混凝土的收缩,竖向荷重差异过大而产生的变形等约束应力的释放。而待后浇带施工完成后,结构又“化零为整”,大量减少了上述应力对结构的影响,减少了过多设置永久性变形缝。这种“缝”在整个结构施工中既解决了建筑物间的差异沉降、由解决了混凝土的收缩变形、温度应力变形,同时又达到了不设永久变形缝的目的。由于常规施工后浇带的模板支撑架支设缺陷,造成了很多的质量问题,例如后浇带板底错台、钢筋移位、保护层控制不当、拆模后混凝土表面观感质量较差,是后浇带施工中的质量通病。传统的后浇带部位的模板支撑架做法是与其它部位形成整体满堂红模板支撑装置,同时搭设,同时拆除。由于后浇带处的混凝土封闭施工是有一定的时间间隔,后浇带是施工的薄弱部位,必须进行加固处理,故拆除模板支撑装置后,一般采用反顶的方法进行加固处理。另外反顶施工方法破坏了模板支撑装置原有的受力平衡状态,杆件受力不均匀,与周边混凝土构件衔接达不到理想效果。后浇带混凝土浇筑时还必须重新支设模板支撑装置,保护板盖、后浇模板分别加工,分别使用,消耗量较大,周转率低,支护成本也比较高。针对上述传统后浇带施工的问题,研发了一种后浇带工具式超前吊模系统,该系统在楼板浇 ...
【技术保护点】
1.后浇带工具式超前吊模系统的施工方法,其特征在于,包括下列步骤:步骤一、楼层板底模安装:根据设计要求搭设支撑脚手架(10),在支撑脚手架(10)上安装楼板底模(1),在楼板底模(1)上测放出混凝土垫块(3)和梳状混凝土免拆模板(4)安装位置线,并用记号笔标出定位钢筋(301)和模板固定筋(401)位置;步骤二、混凝土垫块安装:根据测量放线结果,用电钻在楼板底模(1)上记号笔标记处钻孔,将混凝土垫块(3)底部的定位钢筋(301)插入到楼板底模(1)钻孔中,并用螺母(302)固定;步骤三、超前吊模支架安装:将超前吊模支架(7)的两个支腿(708)支撑在已经安装好的混凝土垫块(3)顶部的套筒(304)内,调节吊杆(703)至指定位置后并套上保护外套管(8),通过吊杆(703)和螺母A(704)将后浇带底模(2)固定在后浇带(13)底部;步骤四、梳妆混凝土免拆模板安装:根据测量放线结果,用电钻在楼板底模(1)上记号笔标记处钻孔,将梳妆混凝土免拆模板(4)通过底部的模板固定筋(401)插入到钻孔内并用螺母B(404)将其固定楼板底模(1)上;步骤五、钢筋绑扎:按照设计要求绑扎楼层板钢筋,钢筋绑 ...
【技术特征摘要】
1.后浇带工具式超前吊模系统的施工方法,其特征在于,包括下列步骤:步骤一、楼层板底模安装:根据设计要求搭设支撑脚手架(10),在支撑脚手架(10)上安装楼板底模(1),在楼板底模(1)上测放出混凝土垫块(3)和梳状混凝土免拆模板(4)安装位置线,并用记号笔标出定位钢筋(301)和模板固定筋(401)位置;步骤二、混凝土垫块安装:根据测量放线结果,用电钻在楼板底模(1)上记号笔标记处钻孔,将混凝土垫块(3)底部的定位钢筋(301)插入到楼板底模(1)钻孔中,并用螺母(302)固定;步骤三、超前吊模支架安装:将超前吊模支架(7)的两个支腿(708)支撑在已经安装好的混凝土垫块(3)顶部的套筒(304)内,调节吊杆(703)至指定位置后并套上保护外套管(8),通过吊杆(703)和螺母A(704)将后浇带底模(2)固定在后浇带(13)底部;步骤四、梳妆混凝土免拆模板安装:根据测量放线结果,用电钻在楼板底模(1)上记号笔标记处钻孔,将梳妆混凝土免拆模板(4)通过底部的模板固定筋(401)插入到钻孔内并用螺母B(404)将其固定楼板底模(1)上;步骤五、钢筋绑扎:按照设计要求绑扎楼层板钢筋,钢筋绑扎时要避免碰撞混凝土垫块(3)、梳状混凝土免拆模板(4)以及超前吊模支架(7),如发现变形和损坏应立即调整和更换,下层钢筋网的楼板下横筋(901)卡放在钢筋凹槽一(402)内;步骤六、梳状木模板及盖板安装:钢筋绑扎完毕后,将梳状木模板(5)的钢筋凹槽二(501)对准楼板上横筋(901)插入到限位槽(403)内,控制调节螺母(705)使侧模固...
【专利技术属性】
技术研发人员:陈小林,朱凯,张迎珍,
申请(专利权)人:杭州昂创科技有限公司,
类型:发明
国别省市:浙江,33