The invention discloses an assembled composite building and its construction method. The assembled composite building is mainly composed of a plurality of prefabricated building units (1), which are integrally prefabricated with a roof (11), a floor (12), a wall (13) and a load-bearing structure, with a reserved exposed steel bar at the top and a load-bearing structure at the bottom. The grouting coupling rod (2) is embedded in the upper part of the load-bearing structure, and the steel bar reserved at the top of the precast building unit (1) is inserted into the grouting cavity (21) of the grouting coupling rod (2) and the adjacent precast building units (1) are connected by grouting concrete, and the roof (11) of the precast building unit (1) is set up. The cast-in-place concrete interlayer (3) is connected to the adjacent prefabricated housing units (1) of the same layer. The assembled composite building of the invention can greatly reduce the amount of on-site construction work, greatly shorten the construction time, and the construction is more convenient and fast.
【技术实现步骤摘要】
组装合成建筑及其施工方法
本专利技术涉及一种建筑物及其施工方法,尤其涉及一种采用预制房单元建造的建筑及其施工方法,可应用于多层或高层的住宅或办公楼。
技术介绍
传统的住宅或办公楼、尤其是高层建筑通常都是在施工现场现浇混凝土来建造的,但这种传统现浇结构的建筑不仅施工工序烦杂,施工周期长,耗费人工,质量难以统一,而且会产生较多的建筑垃圾和极大的噪声和沙尘污染,给周边居民的正常生活造成极大的干扰。为此,现在的建筑物也开始逐渐采用预制梁、半预制楼板、甚至预制阳台、预制卫生间和预制厨房等预制单元来加快和简化施工过程,这种建筑方式确实减少了一部分现场施工作业量,可以缩短施工时间和减少人工,但是这种建筑的剪力墙、结构墙、外墙、梁、柱等构件仍需采用现浇混凝土的结构,并且预制卫生间和预制厨房等预制单元的墙体采用半预制墙,与相邻单元采用现浇结构结合在一起,因此现场施工作业量仍然很大,无法更进一步缩短工期。
技术实现思路
本专利技术针对现有木方的不足,提供一种采用多个预制房单元来建造、能极大地减少现场施工作业量的组装合成建筑及其施工方法。本专利技术采用如下技术方案:一种组装合成建筑,包括组装在一起的多个预制房单元,所述预制房单元一体化预制有顶板、底板、墙体以及承重结构;该预制房单元顶部设有预留外露钢筋,预制房单元的承重结构底部预埋有多个灌浆耦合杆。所述灌浆耦合杆设有连通至预制房单元底面的内部灌浆空腔以及连通该内部灌浆空腔至承重结构外部的灌浆通道和排浆通道,该承重结构内的钢筋插入所述内部灌浆空腔上部,下一层预制房单元顶部的预留外露钢筋插入该内部灌浆空腔下部,通过在所述内部灌浆空腔内灌 ...
【技术保护点】
1.一种组装合成建筑,其特征在于:包括组装在一起的多个预制房单元(1),所述预制房单元(1)一体化预制有顶板(11)、底板(12)、墙体(13)以及承重结构;该预制房单元(1)顶部设有预留外露钢筋,预制房单元(1)的承重结构底部预埋有多个灌浆耦合杆(2);所述灌浆耦合杆(2)设有连通至预制房单元(1)底面的内部灌浆空腔(21)以及连通该内部灌浆空腔(21)至承重结构外部的灌浆通道(22)和排浆通道(23),该承重结构内的钢筋插入所述内部灌浆空腔(21)上部,下一层预制房单元(1)顶部的预留外露钢筋插入该内部灌浆空腔(21)下部,通过在所述内部灌浆空腔(21)内灌注混凝土将相邻的上、下层预制房单元(1)连接在一起;某一层预制房单元(1)的底板(12)与下一层预制房单元(1)的顶板(11)之间设有现浇混凝土夹层(3)将同一层相邻的预制房单元(1)连接在一起,该现浇混凝土夹层(3)内的钢筋与所述下一层预制房单元(1)顶部的预留外露钢筋连接在一起。
【技术特征摘要】
1.一种组装合成建筑,其特征在于:包括组装在一起的多个预制房单元(1),所述预制房单元(1)一体化预制有顶板(11)、底板(12)、墙体(13)以及承重结构;该预制房单元(1)顶部设有预留外露钢筋,预制房单元(1)的承重结构底部预埋有多个灌浆耦合杆(2);所述灌浆耦合杆(2)设有连通至预制房单元(1)底面的内部灌浆空腔(21)以及连通该内部灌浆空腔(21)至承重结构外部的灌浆通道(22)和排浆通道(23),该承重结构内的钢筋插入所述内部灌浆空腔(21)上部,下一层预制房单元(1)顶部的预留外露钢筋插入该内部灌浆空腔(21)下部,通过在所述内部灌浆空腔(21)内灌注混凝土将相邻的上、下层预制房单元(1)连接在一起;某一层预制房单元(1)的底板(12)与下一层预制房单元(1)的顶板(11)之间设有现浇混凝土夹层(3)将同一层相邻的预制房单元(1)连接在一起,该现浇混凝土夹层(3)内的钢筋与所述下一层预制房单元(1)顶部的预留外露钢筋连接在一起。2.根据权利要求1所述的组装合成建筑,其特征在于:所述承重结构为结构墙(14)、梁(15)或立柱。3.根据权利要求1所述的组装合成建筑,其特征在于:所述预制房单元(1)的混凝土体积占整个建筑的混凝土体积的80%以上。4.根据权利要求3所述的组装合成建筑,其特征在于:所述预制房单元(1)内预埋有水电线管,表面预设有装饰面层。5.根据权利要求1至4任一项所述的组装合成建筑,其特征在于:所述预制房单元(1)的顶部边缘设有向上延伸的凸边(16)。6.根据权利要求1至4任一项所述的组装合成建筑,其特征在于:同一层相邻的预制房单元(1)之间安装有竖向密封条(41),上下相邻的预制房单元(1)之间安装有水平...
【专利技术属性】
技术研发人员:黄天祥,黄慧敏,
申请(专利权)人:有利华建筑预制件深圳有限公司,
类型:发明
国别省市:广东,44