The construction method of lifting truss girder of tower crane includes the following steps: (1) processing two sets of crane girder assemblies and two sets of lifting tray assemblies; (2) setting tower crane foundation, guide pulley ground anchor pulling ring and hoist ground anchor; (3) installing foundation section and top in sequence according to the normal installation procedure of tower crane Lifting sleeve, rotating support assembly, slewing tower body section, imported beam and lifting tray assembly; (4) Installing the crown wheel beam assembly on the rotating support assembly; (5) Two car cranes, lifting the zigzag truss beam to the top of the lifting tray assembly; (6) lifting operation; (7) lifting in place and then falling in turn. The invention utilizes the partial structure of the tower crane and the special jacking and adding high performance of the tower crane to achieve the purpose of jacking the traveling beam frame. The practical application test shows that the method is faster, safer, more energy-saving and environmental protection than the steel strand jacking method.
【技术实现步骤摘要】
利用塔式起重机顶升桁架梁的施工方法
本专利技术属于建筑施工机械设备
,具体涉及利用塔式起重机顶升桁架梁的施工方法。
技术介绍
在施工建设中有很多的钢制桁架梁(行车梁架)、网球架要在地面上制作完成后,再将桁架梁吊运至设计高度,现有施工方法是采用穿芯式千斤顶,预设多处千斤顶支点,通过钢绞线一点点的顶升,这种施工方法工期长、安全可靠性不能保障,需要在建筑结构未完成前期,预埋设置多处千斤顶支点,还需要购买一整套液压设备,这些液压设备用完后再无它用,造成了浪费。
技术实现思路
本专利技术为了解决现有技术中的不足之处,提供一种安全可靠性强、施工时间短、成本低、效率高的利用塔式起重机顶升桁架梁的施工方法。为解决上述技术问题,本专利技术采用如下技术方案:利用塔式起重机顶升桁架梁的施工方法,包括以下步骤:(1)加工两套天轮梁组件和两套顶升托盘组件;(2)在施工地点桁架梁的安装位置的两端下方分别作为塔式起重机的设置点,在两个设置点均按塔式起重机顶升300m高度设置塔式起重机基础,预设导向滑轮地锚拉环和卷扬机地锚;(3)按照塔式起重机正常的安装程序依次安装基础节、顶升套架、回转支撑总成、回转塔身节、引进梁和顶升托盘组件,顶升套架、回转支撑总成、回转塔身节、引进梁和顶升托盘组件构成一个同步升降的顶升平台;(4)在回转支撑总成上安装天轮梁组件,在基础节下部安装与导向滑轮地锚拉环连接的导向滑轮,在地面上固定与卷扬机地锚连接的卷扬机,穿绕起重绳,起重绳由卷扬机引出至导向滑轮,再由导向滑轮至天轮梁组件,起重绳端头固定在天轮梁组件上,起重绳上设置有动滑轮,动滑轮上连接有吊钩,由卷扬机、导 ...
【技术保护点】
1.利用塔式起重机顶升桁架梁的施工方法,其特征在于:包括以下步骤:(1)加工两套天轮梁组件和两套顶升托盘组件;(2)在施工地点桁架梁的安装位置的两端下方分别作为塔式起重机的设置点,在两个设置点均按塔式起重机顶升300m高度设置塔式起重机基础,预设导向滑轮地锚拉环和卷扬机地锚;(3)按照塔式起重机正常的安装程序依次安装基础节、顶升套架、回转支撑总成、回转塔身节、引进梁和顶升托盘组件,顶升套架、回转支撑总成、回转塔身节、引进梁和顶升托盘组件构成一个同步升降的顶升平台;(4)在回转支撑总成上安装天轮梁组件,在基础节下部安装与导向滑轮地锚拉环连接的导向滑轮,在地面上固定与卷扬机地锚连接的卷扬机,穿绕起重绳,起重绳由卷扬机引出至导向滑轮,再由导向滑轮至天轮梁组件,起重绳端头固定在天轮梁组件上,起重绳上设置有动滑轮,动滑轮上连接有吊钩,由卷扬机、导向滑轮、天轮梁、起重绳、动滑轮和吊钩组成起重机构,起重机构安装完成后进行试吊,试吊后完成准备工作;(5)选用二台500t汽车吊,分别在距离桁架梁两端部2m‑4m处设吊点,将一字形桁架梁抬吊放至顶升托盘组件上面,用4个固定螺栓将桁架梁固定在顶升托盘组件上, ...
【技术特征摘要】
1.利用塔式起重机顶升桁架梁的施工方法,其特征在于:包括以下步骤:(1)加工两套天轮梁组件和两套顶升托盘组件;(2)在施工地点桁架梁的安装位置的两端下方分别作为塔式起重机的设置点,在两个设置点均按塔式起重机顶升300m高度设置塔式起重机基础,预设导向滑轮地锚拉环和卷扬机地锚;(3)按照塔式起重机正常的安装程序依次安装基础节、顶升套架、回转支撑总成、回转塔身节、引进梁和顶升托盘组件,顶升套架、回转支撑总成、回转塔身节、引进梁和顶升托盘组件构成一个同步升降的顶升平台;(4)在回转支撑总成上安装天轮梁组件,在基础节下部安装与导向滑轮地锚拉环连接的导向滑轮,在地面上固定与卷扬机地锚连接的卷扬机,穿绕起重绳,起重绳由卷扬机引出至导向滑轮,再由导向滑轮至天轮梁组件,起重绳端头固定在天轮梁组件上,起重绳上设置有动滑轮,动滑轮上连接有吊钩,由卷扬机、导向滑轮、天轮梁、起重绳、动滑轮和吊钩组成起重机构,起重机构安装完成后进行试吊,试吊后完成准备工作;(5)选用二台500t汽车吊,分别在距离桁架梁两端部2m-4m处设吊点,将一字形桁架梁抬吊放至顶升托盘组件上面,用4个固定螺栓将桁架梁固定在顶升托盘组件上,两台塔式起重机通过对讲机作同步试顶升,桁架梁上放置水平尺,实时观察水平尺,要求二顶升托盘组件高度差在100mm以内;(6)先操作起重机构,吊钩吊挂一个标准节向上提升放置在引进梁上,然后按照塔式起重机正常顶升加节程序进行顶升,取出基础节与回转支撑总成之间连接的8个连接销,二台塔式起重机的通过对讲机作同步顶升,塔式起重机上的液压缸向上伸长,顶升平台上升二个行程后,将吊挂在引进梁上的标准节推向基础节上方并与基础节固定,然后液压缸收缩,顶升平台下降完成对准、就位,安装8个连接销将回转支撑总成和标准节连接后完一个顶升循环,按照上述顶升过程通过不断的顶升循环、加装附着直至将桁架梁顶升到预定高度,将桁架梁抬顶升到预定高度后,再继续顶升1...
【专利技术属性】
技术研发人员:崔文才,闫许锋,范吉英,高东宇,
申请(专利权)人:中建二局第二建筑工程有限公司,
类型:发明
国别省市:河南,41