The invention discloses a construction method for retaining side side soil in a highway large section tunnel, which is suitable for the large section tunnel above 12m and has a tunnel in the surrounding rock section of grade III and IV with certain self stability conditions. After the survey, three steps are divided into the steps of the steps, the middle steps and the lower steps in the course of the tunnel excavation. There are many different positions before and after the excavation, in which the upper steps are excavated at the same time with the middle rock and the middle step, the middle step is reserved for the side side, and the branches are supported in time, and the supporting whole is formed to shorten the working cycle time. The construction methods for excavation and support of all parts are stagger and parallel along the longitudinal direction of the tunnel. The construction method of the side side soil in the large section tunnel of the highway is innovated and improved on the existing methods, and the corresponding measures of equipment improvement can give full play to the rapid construction potential, and achieve the purpose of safety, reliability and rapid construction.
【技术实现步骤摘要】
公路大断面隧道中导超前预留侧边土的施工工法
本专利技术涉及隧道施工方法
,具体涉及一种公路大断面隧道中导超前预留侧边土的施工工法。
技术介绍
公路大断面隧道施工中,常用的施工方法有双侧壁导坑法、CD法、CRD法、三台阶七步流水法等,这些施工方法都是针对不同地质、不同断面大小的隧道进行先择不同的施工方法,存在一定的局限性。目前大断面隧道建设越来越多,地质越来越复杂,隧道建设的长度也在增加,施工中,更加体现出工期的紧迫性。因此,在保证安全的情况,根据地质情况设计一种能加快施工进度的方法非常必要。
技术实现思路
有鉴于此,本专利技术的目的在于提供一种公路大断面隧道中导超前预留侧边土的施工工法。为达到上述目的,本专利技术提供如下技术方案:一种公路大断面隧道中导超前预留侧边土的施工工法,按照以下步骤进行,步骤一:作业台车就位,利用台车提供的工作面在拱部进行超前支护;超前支护完毕后再次利用台车提供的工作面按爆破设计在上台阶、中台阶打设钻孔,钻孔后进行装药、起爆;开挖循环进尺小于或者等于1.5m,爆破后上台阶和中台阶同时出渣;出渣完毕进行喷、锚、网系统支护,钢架架设在钢架拱脚以上30cm高度处,紧贴钢架两侧边沿按下倾角30°打设锁脚锚杆,锁脚锚杆与钢架牢固焊接,复喷混凝土至设计厚度。步骤二、步骤三:中导坑的左侧预留侧边土和右侧预留侧边土开挖,开挖进尺根据初期支护钢架间距确定,最大不超过1.5m,开挖高度为2~2.5m;左侧预留侧边土和右侧预留侧边土错开2~3m,开挖后立即初喷3~5cm混凝土,及时进行喷、锚、网系统支护,接长钢架,在钢架墙脚以上30cm高度处,紧贴钢架 ...
【技术保护点】
1.一种公路大断面隧道中导超前预留侧边土的施工工法,其特征在于,按照以下步骤进行:步骤一:作业台车就位,利用台车提供的工作面在拱部进行超前支护;超前支护完毕后再次利用台车提供的工作面按爆破设计在上台阶、中台阶打设钻孔,钻孔后进行装药、起爆;开挖循环进尺小于或者等于1.5m,爆破后上台阶和中台阶同时出渣;出渣完毕进行喷、锚、网系统支护,钢架架设在钢架拱脚以上30cm高度处,紧贴钢架两侧边沿按下倾角30°打设锁脚锚杆,锁脚锚杆与钢架牢固焊接,复喷混凝土至设计厚度;步骤二、步骤三:中导坑的左侧预留侧边土和右侧预留侧边土开挖,开挖进尺最大不超过1.5m,开挖高度为2~2.5m;左侧预留侧边土和右侧预留侧边土错开2~3m,开挖后立即初喷3~5cm混凝土,及时进行喷、锚、网系统支护,接长钢架,在钢架墙脚以上30cm高度处,紧贴钢架两侧边沿按下倾角30°打设锁脚锚杆,锁脚锚杆与钢架牢固焊接,复喷混凝土至设计厚度;步骤四、步骤五:下台阶的左侧台阶和右侧台阶开挖,下台阶和中导坑之间的距离控制在20m;开挖进尺最大间距不超过1.5m;下台阶左侧和下台阶右侧错开2~3m,开挖后立即初喷3~5cm混凝土,及时 ...
【技术特征摘要】
1.一种公路大断面隧道中导超前预留侧边土的施工工法,其特征在于,按照以下步骤进行:步骤一:作业台车就位,利用台车提供的工作面在拱部进行超前支护;超前支护完毕后再次利用台车提供的工作面按爆破设计在上台阶、中台阶打设钻孔,钻孔后进行装药、起爆;开挖循环进尺小于或者等于1.5m,爆破后上台阶和中台阶同时出渣;出渣完毕进行喷、锚、网系统支护,钢架架设在钢架拱脚以上30cm高度处,紧贴钢架两侧边沿按下倾角30°打设锁脚锚杆,锁脚锚杆与钢架牢固焊接,复喷混凝土至设计厚度;步骤二、步骤三:中导坑的左侧预留侧边土和右侧预留侧边土开挖,开挖进尺最大不超过1.5m,开挖高度为2~2.5m;左侧预留侧边土和右侧预留侧边土错开2~3m,开挖后立即初喷3~5cm混凝土,及时进行喷、锚、网系统支护,接长钢架,在钢架墙脚以上30cm高度处,紧贴钢架两侧边沿按下倾角30°打设锁脚锚杆,锁脚锚杆与钢架牢固焊接,复喷混凝土至设计厚度;步骤四、步骤五:...
【专利技术属性】
技术研发人员:刘灿,海大鹏,张吉港,黄毅翔,郑邦友,邱琼,刘莉,
申请(专利权)人:中建隧道建设有限公司,
类型:发明
国别省市:重庆,50