The utility model relates to a special bracket for temporary shelter connection in a substation, which belongs to the technical field of electric power safety equipment. The technical scheme is: (1), including obstruction rod block base (2), Wan Xiangzhou (3), a fastening ring (4) and clasp (5), the block base (2) is arranged in the lower end of the rod block (1), cardan shaft (4) through the fastening ring (3) fixed at the upper end of the rod block (1), spring ring (5) is arranged in the cardan shaft (4) at the end of. The utility model has the advantages that: the folding rotating metal clasp, operation and maintenance personnel in security measures, can directly block card in such special bracket, fixed to a good effect on the obscuration network not only shorten the operation and maintenance personnel arrangement, safety measures in time, can effectively prevent the obstruction dumping, prevent maintenance personnel into live space, improve work efficiency to ensure the safety of maintenance personnel.
【技术实现步骤摘要】
一种变电站临时遮挡连接专用支架
本技术涉及一种变电站临时遮挡连接专用支架,属于电力安全设备
技术介绍
目前在电力系统中,为了保证变电站设备安全稳定运行,检修人员需要定期对变电设备进行检修维护。检修人员进入工作现场前,变电站内的运维人员需要对停电设备周围设置遮拦支架,并在遮拦支架上装设临时遮拦网,这样可以为检修人员划定出安全工作区域,防止检修人员走错间隔,误入带电间隔,起到了警示作用,确保了人身安全。停电检修时需要设置的遮拦很多,遮拦网的长度一般为10米,110kV变电站停电检修现场需要遮拦20多个,220kV以上等级的变电站停电检修现场需要遮拦就更多了,需要用遮拦支架将这些遮拦连接支撑起来,当前运维人员只能用缠绕绑系的方法将遮拦网之间连接在遮拦支架上,此种方法既费时又费力,检修结束时,拆除遮拦网时,也很费时,影响送电时间。
技术实现思路
本技术目的是提供一种变电站临时遮挡连接专用支架,采用可以折叠旋转的金属卡环,运维人员在做安全措施时,可以直接将遮拦网卡在此种专用支架上,极大的缩短了整体工作时间,有效地解决了
技术介绍
中存在的上述问题。本技术的技术方案是:一种变电 ...
【技术保护点】
一种变电站临时遮挡连接专用支架,其特征在于:包含遮拦杆(1)、遮拦底座(2)、紧固圈(3)、万向轴(4)和弹簧卡环(5),所述遮拦底座(2)设置在遮拦杆(1)的下端,万向轴(4)通过紧固圈(3)固定在遮拦杆(1)的上端,弹簧卡环(5)设置在万向轴(4)的末端。
【技术特征摘要】
1.一种变电站临时遮挡连接专用支架,其特征在于:包含遮拦杆(1)、遮拦底座(2)、紧固圈(3)、万向轴(4)和弹簧卡环(5),所述遮拦底座(2)设置在遮拦杆(1)的下端,万向轴(4)通过紧固圈(3)固定在遮拦杆(...
【专利技术属性】
技术研发人员:冯良韬,李征,杨坤,宋世超,田新成,杜鹏,张兆鑫,于勇,杨联宇,刘学,杨广兴,于海风,谭会征,韩斐,秦浩然,卢杨,么远,李柄君,彭英杰,马亚运,杨东星,
申请(专利权)人:国网冀北电力有限公司唐山供电公司,国家电网公司,
类型:新型
国别省市:河北,13