The utility model discloses a sluice gate structure of a spillway. In the (1) (2) on both sides of the pier, the pier of spillway on both sides are respectively provided with a gate (3), two gates are symmetrically arranged on side of the gate; gate hinge (4) hinged with the pier, central gate and hydraulic lever (5) hinged, hydraulic rod of the other in the end with the pier on hydraulic rod hinged hinged joint (6); two gates with gate between the water stop (7), before the water stop gate is arranged between the two gate and side wall of spillway pier; (8) is arranged on the gate slot corresponding to the shape of the gate, the gate (9) open state is located in the gate slot. The utility model is used for door shaped pier of spillway gate length is much shorter, can greatly reduce the cost, can shorten the construction period, the length of the layout is also easier to reduce. Especially for the arch dam in spillway structure layout table hole is more favorable.
【技术实现步骤摘要】
一种溢洪道的闸门结构
本技术涉及一种溢洪道的闸门结构,属于水工结构
技术介绍
表孔溢洪道闸墩受弧形闸门尺寸限制,结构尺寸、配筋等工程量均较大,造价较高,工期较长,且布置难度较大。
技术实现思路
本技术的目的在于,提供一种溢洪道的闸门结构。以克服现有表孔溢洪道弧形闸门尺寸较长而导致溢洪道闸墩在上、下游方向尺寸过长、配筋等工程量较大,造价较高,工期较长,布置难度较大的问题。本技术的技术方案:一种溢洪道的闸门结构,包括位于溢洪道两侧的闸墩,溢洪道两侧的闸墩上分别设有一扇闸门,两扇闸门对称设置;闸门一侧经闸门支铰与闸墩铰接,闸门中部与液压杆一端铰接,液压杆另一端与设在闸墩上的液压杆支铰铰接;两扇闸门的对接处设有闸门间止水带,两扇闸门与溢洪道侧壁之间设有闸门前止水带;闸墩上设有与闸门形状对应的门槽,闸门打开状态时位于门槽内。与现有技术相比,本技术用于溢洪道的门字形闸门闸墩长度大大减短,可以大大降低造价,可缩短工期,由于长度降低布置也更容易。尤其对于拱坝在布置表孔溢洪道结构时更为有利。附图说明图1是本技术的结构示意图。附图中标记为:1-溢洪道,2-闸墩,3-闸门,4-闸门支 ...
【技术保护点】
一种溢洪道的闸门结构,其特征在于:包括位于溢洪道(1)两侧的闸墩(2),溢洪道两侧的闸墩上分别设有一扇闸门(3),两扇闸门对称设置;闸门一侧经闸门支铰(4)与闸墩铰接,闸门中部与液压杆(5)一端铰接,液压杆另一端与设在闸墩上的液压杆支铰(6)铰接;两扇闸门的对接处设有闸门间止水带(7),两扇闸门与溢洪道侧壁之间设有闸门前止水带(8);闸墩上设有与闸门形状对应的门槽(9),闸门打开状态时位于门槽内。
【技术特征摘要】
1.一种溢洪道的闸门结构,其特征在于:包括位于溢洪道(1)两侧的闸墩(2),溢洪道两侧的闸墩上分别设有一扇闸门(3),两扇闸门对称设置;闸门一侧经闸门支铰(4)与闸墩铰接,闸门中部与液压杆(5)一端铰接...
【专利技术属性】
技术研发人员:李晓梅,刘其文,代彬,陈章淼,
申请(专利权)人:贵州省水利水电勘测设计研究院,
类型:新型
国别省市:贵州,52