The invention discloses an installation method of coal mill 1000MW unit speed roller, which comprises the following steps: (1) basic acceptance; (2) the reducer base plate is positioned alignment; (3) the installation of speed reducer; (4) the base is in place; (5) the base is provided with a sealing ring alignment and welding; (6) the drive plate mounting; (7) the scraper device is installed; (8) grinding ring and nozzle ring installation; (9) a mounting; (10) the grinding roller mounting; (11) pressing frame and a hinge shaft installation; (12) separator installed; (13) oil system installation; the lifting tool is the use of three M64 bolts, the hook welded on the bolt cap, in the process of slowly fall off the drive plate, the close attention of central drive plate sealing rabbet and connected with the frame of the clearance between the sealing ring and appropriate adjust the frame sealing connecting ring In the radial position, the lower end of the lower part enters the protruding stop of the output flange of the reducer until it is properly implemented. The invention can ensure the safety and stable operation of the coal pulverizer.
【技术实现步骤摘要】
1000MW机组中速辊式磨煤机安装工法
:本专利技术涉及一种磨煤机安装工法,特别是涉及一种1000MW机组中速辊式磨煤机安装工法。
技术介绍
:在大唐三门峡电厂三期扩建工程5#机组中,磨煤机作为辅机安装的一大项目,必须当做重点来抓,以往在安装磨煤机过程中,由于安装步法不确定,在安装时容易造成安装不精确,安装后期出现好多要返工的现象,浪费人力物力,延长工程周期,增加了工程的投入,由于磨煤机运行要求较高,对安装质量要求较为严格,所以对安装过程中的重要工序要严格控制,以确保磨煤机安全、稳定运行。
技术实现思路
:本专利技术所要解决的技术问题是:克服现有技术的不足,提供一种能够稳定运行,减少工程投入的1000MW机组中速辊式磨煤机安装工法。本专利技术为解决技术问题所采取的技术方案是:一种1000MW机组中速辊式磨煤机安装工法,包括以下步骤:(1)基础验收:螺栓孔的间距及深度,基础的定位、尺寸及标高等要进行测量校核,使其尺寸在允许偏差范围之内。(2)减速机台板就位找正:将减速机台板的上下表面、高点、螺栓孔边角、台板边角与减速机固定螺栓孔进行打磨处理清理干净,在减速机就位前对螺栓孔进行一次过丝,台板水平度找正时,调平地脚螺栓两侧及台板承力部位,减速机台板平面度允差应小于±0.1/1000。(3)减速机的安装:减速机就位前,用过轨吊将减速机放在槽钢制作的支墩上进行清理,清理要求与减速机台板清理要求一致,在减速机就位时,钢丝绳与减速机接触处要垫好方木或者破布,在减速机台板没有涂抹MOS2的情况下,将减速机吊至减速机台板上,不紧固螺栓,试塞一下减速机与台板之间的间隙是否符合0. ...
【技术保护点】
一种1000MW机组中速辊式磨煤机安装工法,其特征在于,包括以下步骤:(1)基础验收:螺栓孔的间距及深度、基础的定位、尺寸及标高等要进行测量校核,使其尺寸在允许偏差范围之内;(2)减速机台板就位找正:将减速机台板的上下表面、高点、螺栓孔边角、台板边角与减速机固定螺栓孔进行打磨处理清理干净,在减速机就位前对螺栓孔进行一次过丝,台板水平度找正时,调平地脚螺栓两侧及台板承力部位,减速机台板平面度允差应小于±0.1/1000;(3)减速机的安装:减速机就位前,用过轨吊将减速机放在槽钢制作的支墩上进行清理,清理要求与减速机台板清理要求一致,在减速机就位时 ,钢丝绳与减速机接触处要垫好方木或者破布,在减速机台板没有涂抹MOS2的情况下,将减速机吊至减速机台板上,不紧固螺栓,试塞一下减速机与台板之间的间隙是否符合0.10mm不入的要求,如果间隙过大,需吊起减速机重新处理,直至合格后再抹MOS2润滑脂并进行就位,紧固;(4)机座的就位找正:以减速机输出法兰上端面为基准找正机座的上部,机座顶板平面允许的水平误差小于6 mm,找正时,重新复核减速机输出法兰和机座顶部的高差和同轴度,机座找正后,将机座和调整 ...
【技术特征摘要】
1.一种1000MW机组中速辊式磨煤机安装工法,其特征在于,包括以下步骤:(1)基础验收:螺栓孔的间距及深度、基础的定位、尺寸及标高等要进行测量校核,使其尺寸在允许偏差范围之内;(2)减速机台板就位找正:将减速机台板的上下表面、高点、螺栓孔边角、台板边角与减速机固定螺栓孔进行打磨处理清理干净,在减速机就位前对螺栓孔进行一次过丝,台板水平度找正时,调平地脚螺栓两侧及台板承力部位,减速机台板平面度允差应小于±0.1/1000;(3)减速机的安装:减速机就位前,用过轨吊将减速机放在槽钢制作的支墩上进行清理,清理要求与减速机台板清理要求一致,在减速机就位时,钢丝绳与减速机接触处要垫好方木或者破布,在减速机台板没有涂抹MOS2的情况下,将减速机吊至减速机台板上,不紧固螺栓,试塞一下减速机与台板之间的间隙是否符合0.10mm不入的要求,如果间隙过大,需吊起减速机重新处理,直至合格后再抹MOS2润滑脂并进行就位,紧固;(4)机座的就位找正:以减速机输出法兰上端面为基准找正机座的上部,机座顶板平面允许的水平误差小于6mm,找正时,重新复核减速机输出法兰和机座顶部的高差和同轴度,机座找正后,将机座和调整垫铁、槽钢一起焊接固定,然后进行地脚螺栓孔灌浆,灌浆前调好露扣量,一般为3扣左右,灌浆养护期后,将地脚螺栓拧紧到紧固力矩所需位置;(5)机座密封环安装找正及焊接:找正时需保证密封环和减速机的同轴度不超过0.30mm,水平度不超过1.00mm,在轴向和径向面上用百分表进行找正,找正后将密封环的连接环焊接在机座的上盖板上,焊接时使用φ2.5mm的焊条,小电流、对称焊的方法,焊接后,对密封环的同轴度及水平度进行复查,检查焊接变形程度,随后安装炭精环;(6)传动盘的安装:传动盘安装之前彻底清理减速机输出法兰面、螺栓孔和传动盘下表面,然后将三个导向用的传动盘安装定位销拧入减速机的输出传动法兰的M48螺孔中,定位销每间隔120°左右安置一个,拧紧程度以定位销不能晃动为准,利用起吊工具起吊传动盘,使传动盘的中心与机座密封环的中心对准,同时使圆周上的φ52通孔对准上述的三根导向定心销,缓慢落下传动盘,用0.05mm塞尺检查传动盘与减速机输出法兰接合面,带上传动盘内与减速机输出法兰相连接的螺栓,然后取下三根导向定心销,把螺栓全部带上,在对称方向上拧紧,紧定力矩5300Nm,待螺栓全部拧紧后将止动垫圈扳边;(7)刮板装置的安装:把刮板装置装到传动盘上,调整刮板下部和机座顶面的间隙,正常间隙为6~10mm,检查刮板外侧与一次风室内壁之间以及刮板内侧与机座密封装置下连接环外壁的间隙,间隙必须大于10mm,调整好后将刮板和紧固螺栓点焊牢固;(8)磨环、喷嘴环的安装:清理传动盘上平面和磨环下平面,涂抹一层MOS2油脂,安装三个传动销,将磨环锥盖板卸下,吊磨环及喷嘴环就位,用0.06mm塞尺检查传动盘和磨环接触面,检查喷嘴环与粗粉导流环间的间隙,允许误差为±1.5mm,最后把密封垫、法兰盖及锥形罩按图纸要求用螺栓固定在磨环上;(9)机壳的安装:机壳安装时首先要确认各接口位置,就位前要区分开,机壳就位后,核查壳体垂直度,若偏差过大,则进行调整;(10)磨辊的安装:在安装磨辊前,先将拉杆及拉杆密封装置、导向板安装就位,然后清理辊...
【专利技术属性】
技术研发人员:叶向阳,穆大鹏,张毅,古传亮,张亚举,
申请(专利权)人:中国电建集团河南工程公司,
类型:发明
国别省市:河南,41
还没有人留言评论。发表了对其他浏览者有用的留言会获得科技券。