The utility model is a tributary of the the Yellow River River hydropower station, the sediment cascade structure includes a plurality of closure generating device, the power cut-off device according to the sequential difference set in the tributaries of the the Yellow River River, the closure of each power generating device comprises a reservoir of hydropower station and water retaining plate and water retaining dam station tilting dam set in the outlet of the reservoir and the downstream hydropower, the hydropower station tail water through the river to the next level of the reservoir, the reservoir is larger than the width of the channel width, the reservoir depth is greater than the depth of the river. The utility model adopts the cascade development theory, the the Yellow River sediment closure in the tributaries, reduce sediment into the tributaries of the the Yellow River the Yellow River main road, a tributary of the the Yellow River river sediment Hydropower Station cascade structure as far as possible.
【技术实现步骤摘要】
本技术涉及一种截流泥沙、开发水电站的结构,尤指一种黄河支流截流泥沙、开发水电站的梯级结构。
技术介绍
黄河泥沙含量太大,造成了许多危害。黄河的泥沙主要来自各大支流,尤其黄河的中游,泥沙含量特大。黄河每年流走泥沙16亿方,造成黄河地上悬河,造成了国家重点投资项目大型水库电站面临泥沙淤积。因此治理黄河的首要任务,就是解决黄河泥沙的淤积。
技术实现思路
为解决上述技术问题,本技术提供一种采用梯级开发理论,使黄河泥沙截流在支流上,尽量减少黄河支流的泥沙流入黄河主干道的黄河支流截流泥沙、开发水电站的梯级结构。本技术是一种黄河支流截流泥沙、开发水电站的梯级结构,包括若干组截流发电装置,所述截流发电装置根据高差连续逐级设置在黄河支流的河道上,所述每组截流发电装置包括水库,水电站和拦水翻板坝,所述水电站和拦水翻板坝设置在水库下流的排水口位置,所述水电站的发电尾水通过河道或渠道通向下一级水库,所述水库的宽度大于河道的宽度,所述水库的深度大于河道的深度。本技术黄河支流截流泥沙、开发水电站的梯级结构,所述水电站为河床式水电站或坝后式水电站。本技术黄河支流截流泥沙、开发水电站的梯级结构,所述水库的周边设置清理淤泥的下车道。本技术黄河支流截流泥沙、开发水电站的梯级结构,设置吸沙船,所述吸沙船上设置输砂软管,所述输砂软管一端设置在吸沙船上,另一端连接水库的岸边。本技术的有益技术效果在于:1、本技术梯级开发水库、水电站,梯级截流泥沙,不仅黄河的泥沙会截流在支流上,减少黄河的泥沙含量,而且会使黄河的水质变清。2、本技术梯级开发水库,若干个水库对农田灌溉,环境的改善起了很大作用。3、本技术梯级开 ...
【技术保护点】
一种黄河支流截流泥沙、开发水电站的梯级结构,其特征在于,包括若干组截流发电装置,所述截流发电装置根据高差连续逐级设置在黄河支流的河道上,所述每组截流发电装置包括水库,水电站和拦水翻板坝,所述水电站和拦水翻板坝设置在水库下流的排水口位置,所述水电站的发电尾水通过河道或渠道通向下一级水库,所述水库的宽度大于河道的宽度,所述水库的深度大于河道的深度。
【技术特征摘要】
1.一种黄河支流截流泥沙、开发水电站的梯级结构,其特征在于,包括若干组截流发电装置,所述截流发电装置根据高差连续逐级设置在黄河支流的河道上,所述每组截流发电装置包括水库,水电站和拦水翻板坝,所述水电站和拦水翻板坝设置在水库下流的排水口位置,所述水电站的发电尾水通过河道或渠道通向下一级水库,所述水库的宽度大于河道的宽度,所述水库的深度大于河道的深度。2.根据权利要求1所述的一种黄...