The present invention relates to deep well point connection structure of new and old sewage pipelines, including foundation pit support structure, old and new sewage pipeline inspection well structure and sewage pipeline suspension device; the foundation pit support structure includes steel sheet pile, drainage ditch, support plate, support plate, cross bar, inclined brace and groove; the new and old sewage pipeline inspection well structure includes blocking pipe, solid base, fixed base and tension screw. The sewage pipeline suspension device comprises a slide rail, a sliding beam harvester, a top connecting bar, a suspension rope, a pulley, a prop, a suspension ring, an extension rail and a hook. The beneficial effect of the invention is that the continuous flow construction of new and old sewage pipes can be realized by the three connecting pipes arranged on the inspection wells of the invention together with the blocked pipes; the inspection wells of the invention are constructed by assembling method, which greatly shortens the construction time.
【技术实现步骤摘要】
新老污水管道深井点连接结构及施工方法
本专利技术涉及污水管领域,尤其是涉及一种新老污水管道深井点连接结构及施工方法。
技术介绍
地下污水管道是掩埋在地下的用于输送上部排出的污水的管道,在城市、道路、污水厂、地下工程等得到使用。在污水管的使用过程中,需要对其进行维修,而有些损坏严重的管道需要对其进行管道的更换,更有甚者需要将原有管道弃用,利用新污水管道代替旧污水管道。传统的新旧污水管道施工时,永久关闭旧污水管的排污功能,然后进行新污水管道的施工,最后在新旧污水管交汇处将两管道连接在一起。由于新旧污水管的施工工期较长,断流的污水无处排放,会对原有环境造成不利影响,如污水厂的污水无处排放,只能往污水厂周边环境渗流;道路上的水无处排放,严重的会造成道路积水过多导致车辆无法行车。因此,目前拟寻求一种不断流的新老污水管道深井点连接结构及施工方法就显得十分重要。
技术实现思路
本专利技术的目的是克服现有技术中的不足,提供一种新老污水管道深井点连接结构及施工方法。这种新老污水管道深井点连接结构,包括基坑支护结构、新老污水管道检查井结构和污水管道悬吊装置;所述基坑支护结构包括钢板桩、排 ...
【技术保护点】
1.一种新老污水管道深井点连接结构,其特征在于,包括基坑支护结构、新老污水管道检查井结构和污水管道悬吊装置;所述基坑支护结构包括钢板桩(10)、排水沟(11)、支托板(18)、支撑板(19)、橫杆(20)、斜撑(21)和凹槽(22);支托板(18)与斜撑(21)焊接在钢板桩(10)上,形成三角结构;支撑板(19)放置在支托板(18)上,支撑板(19)上开设有凹槽(22),凹槽(22)与橫杆(20)相契合,橫杆(20)架设在两钢板桩(10)之间,橫杆(20)横向支撑着钢板桩(10);钢板桩(10)外侧设有排水沟(11);所述新老污水管道检查井结构包括堵塞管(6)、实心底座(2 ...
【技术特征摘要】
1.一种新老污水管道深井点连接结构,其特征在于,包括基坑支护结构、新老污水管道检查井结构和污水管道悬吊装置;所述基坑支护结构包括钢板桩(10)、排水沟(11)、支托板(18)、支撑板(19)、橫杆(20)、斜撑(21)和凹槽(22);支托板(18)与斜撑(21)焊接在钢板桩(10)上,形成三角结构;支撑板(19)放置在支托板(18)上,支撑板(19)上开设有凹槽(22),凹槽(22)与橫杆(20)相契合,橫杆(20)架设在两钢板桩(10)之间,橫杆(20)横向支撑着钢板桩(10);钢板桩(10)外侧设有排水沟(11);所述新老污水管道检查井结构包括堵塞管(6)、实心底座(23)、固定底座(24)、对拉螺栓孔(25)、实心块(26)、旧管联通管(29)、新管联通管(30)、拼接圆环(31)、拼接圆槽(32)和井室(33);实心底座(23)、固定底座(24)和对拉螺栓孔(25)组合成检查井底座,三口联通管(5)底部的实心块(26)插入固定底座(24),实心块(26)与固定底座(24)上的对拉螺栓孔(25)对齐并通过螺杆(28)连接固定;井室(33)拼接在三口联通管(5)顶部,井室(33)底部的拼接圆槽(32)与三口联通管(5)顶部的拼接圆环(31)配合连接;三口联通管(5)设有两个旧管连接管(29)和一个新管联通管(30),新管联通管(30)或旧管联通管(29)通过堵塞管(6)堵塞;所述污水管道悬吊装置包括滑轨(34)、滑动收束机(35)、顶部连接横杆(36)、吊绳(37)、滑行轮(38)、支柱(39)、吊环(40)、外伸轨(41)和吊钩(44);悬吊装置外框架由支柱(39)及顶部和底部的连接横杆组成,顶部连接横杆(36)下方一段距离设置支撑挡板(46),支撑橫杆(46)上安装有滑轨(34),滑轨超出悬吊装置外框架部分为外伸轨(41),悬吊装置停在基坑(3)外边缘,外伸轨(41)伸至基坑(3)上方;滑轨(34)上设有滑动收束机(35),滑动收束机(35)设有吊绳(37)、吊钩(44)和吊环(40)用于起吊旧污水管(1);支柱(39)底部设有滑行轮(38)。2.根据权利要求1所述的新老污水管道深井点连接结构,其特征在于,所述排水沟(11)包括排水板(13)、支撑杆(14)和排水坡(12),排水板(13)为U形结构,排水板(13)上端设有排水坡(12),排水板(13)上部的杆槽(15)内安装有支撑杆(14);排水板(13)两端分别设置有拼接凸起(16)及拼接凹槽(17),拼接凸起(16)与拼接凹槽(17)相契合。3.根据权利要求1所述的新老污水管道深井点连接结构,其特征在于,所述新管联通管(30)和旧管联通管(29)的拼接口(2)处均设有与堵塞管...
【专利技术属性】
技术研发人员:刘要武,杜海峰,孙学军,彭申凯,任杰,钱申春,崔健,
申请(专利权)人:安徽省公路桥梁工程有限公司,
类型:发明
国别省市:安徽,34