The invention discloses a combined deviation rectification method for pile-raft foundation buildings, which includes: S1, construction of class C pile-pressing piles on the side of larger settlement of foundation floor and prestressing sealing piles; S2, construction of class A pile-pressing piles on the side of smaller settlement of foundation floor, and reduction of bearing capacity of original engineering piles on the side of smaller settlement; S3, construction of class B pile-pressing piles on the side of smaller settlement, and increase settlement ratio. Small side deformation; S4, type A pile and type B pile are sealed. The method not only has good rectifying effect, high rectifying speed, but also has good safety in rectifying construction.
【技术实现步骤摘要】
一种桩筏基础建筑物联合纠偏方法
本专利技术涉及建筑工程
,尤其涉及一种桩筏基础建筑物联合纠偏方法。
技术介绍
采用桩基础的高层建筑物,由于勘察、设计、施工或环境等方面的原因,造成工程桩偏位或者损坏,灌注桩沉渣过厚,工程桩承载力不足,建筑物上部结构施工或者使用过程中产生不均匀沉降,导致倾斜。由于高层建筑自重大,高度远大于宽度,水平变形控制要求高,进行主动纠偏难度大风险高。常规的射水法、掏土法、堆载迫降等被动纠偏法多适应于多层建筑,对于采用桩基的高层建筑,此类方法实施困难,射水和掏土深度有限,且很难控制建筑沉降变形。因此一般不进行高层建筑物纠偏,仅进行基础加固。
技术实现思路
本专利技术主要是解决现有技术中所存在的技术问题,从而提供一种纠偏效果好、安全性高的桩筏基础建筑物联合纠偏方法。本专利技术的上述技术问题主要是通过下述技术方案得以解决的:本专利技术提供的桩筏基础建筑物联合纠偏方法,其包括:S1、在基础底板的沉降较大侧施工C类桩压桩,并进行预应力封桩;S2、在基础底板的沉降较小侧施工A类桩压桩,并降低沉降较小侧的原工程桩的承载力;S3、在沉降较小侧交叉施工B类桩压 ...
【技术保护点】
1.一种桩筏基础建筑物联合纠偏方法,其特征在于,包括:S1、在基础底板的沉降较大侧施工C类桩压桩,并进行预应力封桩;S2、在基础底板的沉降较小侧施工A类桩压桩,并降低沉降较小侧的原工程桩的承载力;S3、在沉降较小侧交叉施工B类桩压桩,并增大沉降较小侧的变形;S4、对A类桩和B类桩进行封桩。
【技术特征摘要】
1.一种桩筏基础建筑物联合纠偏方法,其特征在于,包括:S1、在基础底板的沉降较大侧施工C类桩压桩,并进行预应力封桩;S2、在基础底板的沉降较小侧施工A类桩压桩,并降低沉降较小侧的原工程桩的承载力;S3、在沉降较小侧交叉施工B类桩压桩,并增大沉降较小侧的变形;S4、对A类桩和B类桩进行封桩。2.如权利要求1所述的桩筏基础建筑物联合纠偏方法,其特征在于,所述步骤S2中,降低沉降较小侧的原工程桩的承载力包括:在A类桩上安装排气管和注浆管,高压注水形成注浆体。3.如权利要求1所述的桩筏基础建筑物联合纠...
【专利技术属性】
技术研发人员:顾国荣,李晓勇,李明,刘冬,杨明义,陈晖,王克文,
申请(专利权)人:上海勘察设计研究院集团有限公司,上海长凯岩土工程有限公司,
类型:发明
国别省市:上海,31