The invention relates to the field of chamber excavation, in particular to an excavation construction method for a special stratum chamber, including the following construction steps: first, preparing construction equipment and personnel, and surveying and lofting the construction area; second, excavating and supporting the small chamber: excavating by blasting or roadheader, and discharging slag in time, and the progress of each cycle. After the slag discharge is completed, steel arch frame and anchor mesh are used to support it in time. Step 3: excavation and support of the middle guide tunnel up the hill: step 4, reverse expansion of the upper steps of the large chamber; step 5, excavation and support of the middle steps of the large chamber: step 6, excavation and support of the lower steps of the large chamber (inverted arch); step 7, lining and backfilling of the large chamber inverted arch. The excavation method has the advantages of reliable excavation and small amount of work.
【技术实现步骤摘要】
一种用于特殊地层硐室的开挖施工方法
本专利技术涉及人防工程领域,尤其涉及了一种用于特殊地层硐室的开挖施工方法。
技术介绍
在人防指挥所指挥大厅的开挖支护过程中,基本的设计类型都是通道小硐室与指挥大厅大硐室呈“十”字相交的形式,其中指挥大厅由于断面设计大,都要跨在通道上面。在由通道小硐室向指挥大厅大硐室扩挖支护成型及由指挥大厅反向扩挖与通道小硐室相交成型的过程中,特殊地质条件下,一旦施工工法不当,很容易造成塌方等失控的局面。我公司由于长期从事人防坑地道工程施工,不断总结成果,最终形成了在特殊地质条件下指挥大厅开挖支护的一种新方法--特殊地层大跨小硐室开挖施工方法。
技术实现思路
本专利技术针对现有技术开挖支护不牢容易塌方,工程量大等缺点,提供了一种用于特殊地层硐室的开挖施工方法。为了解决上述的技术问题,本专利技术通过下述技术方案得以解决:一种用于特殊地层硐室的开挖施工方法,包括如下施工步骤:步骤一、准备施工器械和人员配备,并对施工区域进行测量放样;步骤二、对小硐室进行开挖及支护:采用爆破或者掘进机进行开挖,并及时出渣,每一循环的进度为0.5m-0.75m,出渣完成后,及时采用钢拱架和锚网进行支护,步骤三、中导洞上山的开挖以及支护:在开挖中导洞进口端之前,先按照开挖轮廓线测量放线,然后沿开挖轮廓线搭设超前锚杆或超前小导管注浆,沿开挖线将小硐室支护结构切割拆除,然后进行爆破开挖中导洞的入口端;中导洞沿13度~15度的向上倾角进行开挖及支护;步骤四、大硐室上台阶反向扩挖:中导洞开挖及支护到大硐室远端墙后,中导洞左右两侧交错进行反向扩挖及支护大硐室上台阶,上台阶两侧采用 ...
【技术保护点】
1.一种用于特殊地层硐室的开挖施工方法,其特征在于:包括如下施工步骤:步骤一、准备施工器械和人员配备,并对施工区域进行测量放样;步骤二、对小硐室进行开挖及支护:采用爆破或者掘进机进行开挖,并及时出渣,每一循环的进度为0.5m‑0.75m,出渣完成后,及时采用钢拱架和锚网进行支护,步骤三、中导洞上山的开挖以及支护:在开挖中导洞进口端之前,先按照开挖轮廓线测量放线,然后沿开挖轮廓线搭设超前锚杆或超前小导管注浆,沿开挖线将小硐室支护结构切割拆除,然后进行爆破开挖中导洞的入口端;中导洞沿13度~15度的向上倾角进行开挖及支护;步骤四、大硐室上台阶反向扩挖:中导洞开挖及支护到大硐室远端墙后,中导洞左右两侧交错进行反向扩挖及支护大硐室上台阶,上台阶两侧采用工字钢支撑架结合锚杆或锚垫板进行支撑和支护;步骤五、大硐室中台阶开挖及支护:支护大硐室中台阶,开挖及支护时,左右两侧前后错开进行,走“之”字形路线,一次开挖及支护不能超过2榀钢拱架,防止出现过大沉降变形,开挖后要及时将工字钢支撑到位,底脚不得脱空,拱架支撑好后,立即打设缩脚锚杆,锚杆与钢拱架焊接牢固,然后挂网喷射混凝土;步骤六、大硐室下台阶(仰拱 ...
【技术特征摘要】
1.一种用于特殊地层硐室的开挖施工方法,其特征在于:包括如下施工步骤:步骤一、准备施工器械和人员配备,并对施工区域进行测量放样;步骤二、对小硐室进行开挖及支护:采用爆破或者掘进机进行开挖,并及时出渣,每一循环的进度为0.5m-0.75m,出渣完成后,及时采用钢拱架和锚网进行支护,步骤三、中导洞上山的开挖以及支护:在开挖中导洞进口端之前,先按照开挖轮廓线测量放线,然后沿开挖轮廓线搭设超前锚杆或超前小导管注浆,沿开挖线将小硐室支护结构切割拆除,然后进行爆破开挖中导洞的入口端;中导洞沿13度~15度的向上倾角进行开挖及支护;步骤四、大硐室上台阶反向扩挖:中导洞开挖及支护到大硐室远端墙后,中导洞左右两侧交错进行反向扩挖及支护大硐室上台阶,上台阶两侧采用工字钢支撑架结合锚杆或锚垫板进行支撑和支护;步骤五、大硐室中台阶开挖及支护:支护大硐室中台阶,开挖及支护时,左右两侧前后错开进行,走“之”字形路线,一次开挖及支护不能超过2榀钢拱架,防止出现过大沉降变形,开挖后要及时将工字钢支撑到位,底脚不得脱空,拱架支撑好后,立即打设缩脚锚杆,锚杆与钢拱架焊接牢固,然后挂网喷射混凝土;步骤六、大硐室下台阶(仰拱)开挖及支护:中台阶开挖及支护到大硐室远端墙后,下台阶反向开挖及支护;步骤七、大硐室仰拱衬砌及回填。2.根据权利要求1所述的一种用于特殊地层硐室的开挖施工方法...
【专利技术属性】
技术研发人员:梅树强,朱爱山,汪宏兵,周奎,陈春和,
申请(专利权)人:浙江省隧道工程公司,
类型:发明
国别省市:浙江,33