The invention relates to the field of metro construction technology, in particular to the synchronous construction method of shield tunneling through piston duct and the upper structure of piston duct. The negative two-layer side wall is constructed by sectional flow water, which reasonably completes the transformation of internal support force system, and provides a reliable reaction support system for shield tunneling; the dewatering well in pit is drawn out during soil moulding construction to ensure the piston wind during construction. The stability of the tunnel floor structure; after the construction of the middle plate, the sealing plate is used to block the holes in the middle plate, so that the piston airway and the lower structure are completely isolated, which not only provides a closed space for the shield to cross the piston airway, but also forms an effective counterforce support, avoids the end reinforcement process, and achieves the synchronous construction of the upper structure of the piston airway. The invention effectively solves the difficult problem that shield tunneling through piston airway can not be synchronized with the construction of the upper structure of piston airway, and has the advantages of reasonable working procedure, safety, reliability, effective avoidance of pit work and effective shortening of construction period.
【技术实现步骤摘要】
盾构穿越活塞风道与活塞风道上部结构同步施工的方法
本专利技术涉及城市轨道交通地铁施工
,更具体而言,涉及盾构穿越活塞风道与活塞风道上部结构同步施工的方法。
技术介绍
随着我国城市轨道交通建设的快速发展,地铁建设力度持续加大。城市地铁施工受管线迁改、交通导改、征地拆迁等影响因素多,造成地铁施工工期紧。活塞风井主体结构一般埋深比较大,而且面临着在短距离内盾构施工的多次接收、始发,施工作业风险大,端头加固空间受限且加固周期长,给施工安全带来了风险,施工工期按期完成造成了困难。
技术实现思路
为了克服现有技术中所存在的不足,本专利技术提供一种盾构穿越活塞风道与活塞风道上部结构同步施工的方法,解决现有技术中盾构穿越活塞风井时,由于地下空间受限无法进行端头加固,工期紧张而又不能上下同步施工等问题。为了解决上述技术问题,本专利技术所采用的技术方案为:盾构穿越活塞风道与活塞风道上部结构同步施工的方法,包括以下步骤:S1、施工活塞风道底板防水及钢筋混凝土;S2、施工活塞风道坑外端头降水井;S3、拆除活塞风道左线第三道钢支撑,安装右线洞门钢环,施工活塞风道左线负二层侧墙防水、钢筋、混凝土;施工左线混凝土导台;S4、拆除左线负二层侧墙模板,架设左线侧墙对撑;S5、拆除活塞风道右线第三道钢支撑,安装右线洞门钢环,施工活塞风道右线负二层侧墙防水、钢筋、混凝土;施工右线混凝土导台;S6、拆除右线负二层侧墙模板,架设右线侧墙对撑;S7、对左、右线架设的左线侧墙对撑、右线侧墙对撑施加预应力;S8、接长活塞风道内降水井至中板,分层回填压实三七灰土至负二层侧墙顶。,中板孔位置回填至孔底下2 ...
【技术保护点】
1.盾构穿越活塞风道与活塞风道上部结构同步施工的方法,其特征在于:包括以下步骤:S1、施工活塞风道底板(14)防水及钢筋混凝土;S2、施工活塞风道坑外端头降水井(3);S3、拆除活塞风道左线第三道钢支撑(13),安装左线洞门钢环,施工活塞风道左线负二层侧墙防水、钢筋、混凝土;施工左线混凝土导台(4);S4、拆除左线负二层侧墙模板,架设左线侧墙对撑(1);S5、拆除活塞风道右线第三道钢支撑(13),安装右线洞门钢环,施工活塞风道右线负二层侧墙防水、钢筋、混凝土;施工右线混凝土导台(5);S6、拆除右线负二层侧墙模板,架设右线侧墙对撑(2);S7、对左、右线架设的左线侧墙对撑(1)、右线侧墙对撑(2)施加预应力;S8、接长活塞风道内降水井(6)至中板,分层回填压实三七灰土至负二层侧墙顶;S9、安装中板腋角下侧墙模板(7),在中板腋角下侧墙模板(7)与活塞风道基坑围护结构(15)间设置中板腋角下侧墙内马镫(8),施工中板孔封孔板(9)钢筋、模板、混凝土;S10、回填其余部分至中板底下15mm,并压实平整,铺设15mm竹胶板作为中板底模(10);S11、安装中板及腋角钢筋,支设中板孔洞模板,浇 ...
【技术特征摘要】
1.盾构穿越活塞风道与活塞风道上部结构同步施工的方法,其特征在于:包括以下步骤:S1、施工活塞风道底板(14)防水及钢筋混凝土;S2、施工活塞风道坑外端头降水井(3);S3、拆除活塞风道左线第三道钢支撑(13),安装左线洞门钢环,施工活塞风道左线负二层侧墙防水、钢筋、混凝土;施工左线混凝土导台(4);S4、拆除左线负二层侧墙模板,架设左线侧墙对撑(1);S5、拆除活塞风道右线第三道钢支撑(13),安装右线洞门钢环,施工活塞风道右线负二层侧墙防水、钢筋、混凝土;施工右线混凝土导台(5);S6、拆除右线负二层侧墙模板,架设右线侧墙对撑(2);S7、对左、右线架设的左线侧墙对撑(1)、右线侧墙对撑(2)施加预应力;S8、接长活塞风道内降水井(6)至中板,分层回填压实三七灰土至负二层侧墙顶;S9、安装中板腋角下侧墙模板(7),在中板腋角下侧墙模板(7)与活塞风道基坑围护结构(15)间设置中板腋角下侧墙内马镫(8),施工中板孔封孔板(9)钢筋、模板、混凝土;S10、回填其余部分至中板底下15mm,并压实平整,铺设15mm竹胶板作为中板底模(10);S11、安装中板及腋角钢筋,支设中板孔洞模板,浇筑中板混凝土;S12、中板混凝土养护至设计强度的80%,便可进行盾构穿越活塞道施工;活塞风道上部结构可同时进行正常施工。2.根据权利要求1所述的盾构穿越活塞风道与活塞风道上部结构同步施工的方法,其特征在于:所述左线侧墙对撑(1)、右线侧墙对撑(2)采用钢支撑,回填土前施加预应力。3.根据权利要求1所述的盾构穿越活塞风道与活塞风道上部结构同步施工的方法,其特征在于:所述左线混凝土导台(4)、右线混凝土导台(5)与活塞风道左线负二层侧墙(16)、活塞风道右线负二层侧墙(17)进行交叉同步施工,具体施工步骤为:首先拆除左线第三道钢支撑(13)施工活塞风道负二层左线侧墙(16),架设左线侧墙...
【专利技术属性】
技术研发人员:武锐,余浩,屈海磊,支卫东,任巍杰,苑申,贺栋栋,吴金燕,
申请(专利权)人:中铁十二局集团有限公司,中铁十二局集团第二工程有限公司,
类型:发明
国别省市:山西,14