The utility model discloses a new type of water leakage sealing structure for foundation pit, which mainly includes: foundation pit, water stop curtain, retaining structure, well point pipe and Larsen steel sheet pile. The well point pipe is arranged evenly on the outside of water stop curtain, and the distance between the well point pipe and the water stop curtain is 1 to 2m, and the Larsen steel sheet pile is set on the inside of the foundation pit. The spacing between the steel sheet pile and the retaining structure is D2 to 1 to 2m, and there is a plain concrete between the Larsen steel sheet pile and the retaining structure. Through the above way, the utility model can solve the problems of insufficient leakage and high cost of the existing foundation pit.
【技术实现步骤摘要】
一种新型的基坑漏水封堵结构
本技术涉及建筑领域,特别是涉及一种新型的基坑漏水封堵结构。
技术介绍
在地下水丰富的地区,为了确保地下结构施工的安全,除了采取可靠的挡土措施以外,通常还需要采取可靠的止水措施,常规的止水措施主要采用深层搅拌桩和高压旋喷桩,由于地质条件的差异,若施工过程中对于搅拌桩(或高压旋喷桩)成桩质量把控不严,搅拌桩(或高压旋喷桩)搭接部位容易发生渗漏水等事故。目前常见的渗漏水堵漏措施主要采用以下方法:一、基坑迎土侧采用机械成孔后灌混凝土;二、基坑背面注浆。目前常规处理措施存在以下问题:1、混凝土用量较大,造价较高;2、由于浆液流动性较大,凝固时间较长,很难短时间封堵漏水部位。
技术实现思路
本技术主要解决的技术问题是提供一种新型的基坑漏水封堵结构,能够解决现有基坑堵漏不足、成本高的问题。为解决上述技术问题,本技术采用的一个技术方案是:提供一种新型的基坑漏水封堵结构,主要包括:基坑、止水帷幕、挡土结构、井点管、拉森钢板桩,所述井点管均匀设置于止水帷幕外侧,且井点管与止水帷幕之间的间距d1为1~2m,所述拉森钢板桩设置于基坑内侧,且拉森钢板桩与挡土结构之间的间距d2为1~2m,在所述拉森钢板桩与挡土结构之间填充有素砼。优选的,所述井点管的长度设置为6~10m,且相邻井点管之间的间距d3设置为1~2m。优选的,所述井点管的顶部设置有弯头管用于连接外部真空管。优选的,所述井点管的底部设置有滤管,所述滤管的长度不小于2m。优选的,所述拉森钢板桩的材质采用PC材质。优选的,所述素砼的强度不小于C30。本技术的有益效果是:1、在围护结构与拉森钢板桩之间填筑素砼, ...
【技术保护点】
1.一种新型的基坑漏水封堵结构,其特征在于,主要包括:基坑、止水帷幕、挡土结构、井点管、拉森钢板桩,所述井点管均匀设置于止水帷幕外侧,且井点管与止水帷幕之间的间距d1为1~2m,所述拉森钢板桩设置于基坑内侧,且拉森钢板桩与挡土结构之间的间距d2为1~2m,在所述拉森钢板桩与挡土结构之间填充有素砼。
【技术特征摘要】
1.一种新型的基坑漏水封堵结构,其特征在于,主要包括:基坑、止水帷幕、挡土结构、井点管、拉森钢板桩,所述井点管均匀设置于止水帷幕外侧,且井点管与止水帷幕之间的间距d1为1~2m,所述拉森钢板桩设置于基坑内侧,且拉森钢板桩与挡土结构之间的间距d2为1~2m,在所述拉森钢板桩与挡土结构之间填充有素砼。2.根据权利要求1所述的一种新型的基坑漏水封堵结构,其特征在于,所述井点管的长度设置为6~10m,且相邻井点管之间的间距d3设置为...