The tunnel foundation bearing capacity inspection device is used to detect the bearing capacity of the tunnel foundation conveniently, so as to provide a scientific basis for the design of the tunnel foundation reinforcement, so as to ensure the rationality and safety of the reinforcement design for the tunnel foundation. It includes the check section steel pipe erected on the fixed bearing capacity of tunnel foundation, the lower part of the pipe through the invert filling layer, the two tunnel lining structure and tunnel initial support into the support structure of tunnel bottom, the port is located at the invert filling layer above the surface, and is provided with a removable cover.
【技术实现步骤摘要】
隧道基础承载力检查装置
本技术涉及隧道,特别涉及一种隧道基础承载力检查装置。
技术介绍
在现代经济高速发展的大环境下,伴随着西部开发力度逐渐加大,铁路交通建设必将先行。随着我国铁路隧道工程技术的迅速发展,越来越多隧道穿越艰险地质复杂山区。隧道通过昔格达等软弱围岩地层时基底可能会发生软化、泥化,基底承载力在施工前后能否满足要求逐渐受到工程施工、设计、研究学者的高度重视。目前我国铁路隧道施工中基础承载力的测定方法有平板载荷试验、静力触探、动力触探、标准贯入等方法,由于可靠性、隧道洞内施工场地限制等因素,常采用动力触探方法测定隧道基底承载力。随着隧道的掘进施工,仰拱封闭后将很难再测得基础承载力,如果在运营期间基底承载力不足,易发生翻浆冒泥,仰拱隆起破坏等危害,影响铁路正常运营,后期维修成本也将增大。目前,隧道施工中常测量仰拱开挖前的基础承载力,仰拱开挖封闭后基础承载力的测试、研究较少,没有形成一套隧道基础承载力的检查装置。这对地基处理加固技术的设计与优化带来了较大困难,对基础加固的可靠性和安全性将产生重大影响。
技术实现思路
本技术所要解决的技术问题是提供一种隧道基础承载力检查装置,以方便的对隧道基础承载力进行检测,为隧道基底加固的设计提供科学依据,以保证隧道基底加固设计的合理性和安全性。本技术解决其技术问题所采用的技术方案如下:本技术的隧道基础承载力检查装置,其特征是:它包括隧道基础承载力检查断面上竖立固定设置的钢管,该钢管的下部穿过仰拱填充层、隧道二次衬砌结构和隧道初期支护结构进入隧底基础,其上端口位于仰拱填充层表面之上,并设置有可拆卸的端盖。本技术的有益效果是,设 ...
【技术保护点】
隧道基础承载力检查装置,其特征是:它包括在隧道基础承载力检查断面上竖立固定设置的钢管(20),该钢管(20)的下部穿过仰拱填充层(13)、隧道二次衬砌结构(11)和隧道初期支护结构(10)进入隧底基础(D),其上端口位于仰拱填充层(13)表面之上,并设置有可拆卸的端盖(21)。
【技术特征摘要】
1.隧道基础承载力检查装置,其特征是:它包括在隧道基础承载力检查断面上竖立固定设置的钢管(20),该钢管(20)的下部穿过仰拱填充层(13)、隧道二次衬砌结构(11)和隧道初期支护结构(10)进入隧底基础...
【专利技术属性】
技术研发人员:杨建民,王志杰,余大龙,张涵,李现宾,李煜川,王磊,岳磊,舒东利,
申请(专利权)人:中铁二院工程集团有限责任公司,
类型:新型
国别省市:四川,51