The utility model relates to a stabilizing system for a pull rod, in particular to a steel bar lower edge pull rod stabilizing system which is used for the construction of cast-in-situ concrete large section beams. Including slotsteel two alternate distribution, channel beam between the support frame is fixed by a pull rod, the steel beam with steel support left fixed, the steel beam and the right end is provided with a brace fixed, the head and the tail of the steel beam and the groove are respectively provided with a fixed steel hole. Cast in place concrete large section beam construction of the bottom of the steel structure of the stability of the tension rod system, shorten the construction period, while reducing the cost of investment, easy to operate, strong bearing capacity, high stability.
【技术实现步骤摘要】
本技术涉及一种拉杆稳定系统,尤其涉及一种现浇砼大截面梁施工的型钢下缘拉杆稳定系统。
技术介绍
现代建筑设计中大批高层塔楼下加大底盘(大面积裙房)的形式很常见,因大底盘裙房建筑设计用途一般需要大空间,这就要求结构设计时其竖向的承重砼墙尽量少,但上部塔楼为住宅或办公设计,不需要大空间,且高层结构必须要有一定的竖向承重砼墙,这样就导致上部有一批砼墙无法直接落在基础上,必须在裙房顶或某层设置转换层结构,把上部的砼墙落在转换大梁上。按结构设计要求,此转换大梁一般截面均较大,截面高度一般在2000mm以上,有的超过3000mm,且梁截面宽度较大,大多数为500mm以上。这样大截面现浇梁的施工荷载会很大,但建筑结构设计时设计人员往往不会考虑这个施工荷载,施工时就要采取措施来解决或规避这个问题。目前为止主要有如下这些方案:1、普通方法支模,采用分层浇筑减荷的方法,把大梁按水平方向分两次浇捣,等第一次砼强度达到一定强度后再浇捣第二次砼,这样可以利用第一次砼的强度,减轻荷载,此方法必须要设计人员计算后同意;2、按超重模板普通钢管或型钢支模,施工荷载通过钢管或型钢传递到下层,为安全考虑,下面几层必须层层设支撑,直到荷载传到建筑物基础为止,这样的话施工投入会很大,且施工不方便;3、利用框架柱临时搭设钢结构水平承重构件,把大梁的施工荷载通过钢结构层传递到建筑物的框架柱,这样可以避免荷载传到下面几层楼面,但投入的钢结构量会很大,且要等框架柱达到设计强度后才能施工下一步,会延长工期,在框架柱上还要附加设置一些牛腿和埋件,在一定程度上会影响原结构。
技术实现思路
本技术主要是解决现有技术中 ...
【技术保护点】
一种现浇砼大截面梁施工的型钢下缘拉杆稳定系统,其特征在于:包括二根相间隔分布的槽钢梁(1),所述的槽钢梁(1)间通过拉杆架(2)相支撑固定,所述的槽钢梁(1)的左端设有钢梁支撑固定位(3),所述的槽钢梁(1)的右端设有斜撑固定位(4),所述的槽钢梁(1)的头部与尾部分别设有槽钢固定孔(5)。
【技术特征摘要】
1.一种现浇砼大截面梁施工的型钢下缘拉杆稳定系统,其特征在于:包括二根相间隔分布的槽钢梁(I),所述的槽钢梁⑴间通过拉杆架⑵相支撑固定,所述的槽钢梁⑴的左端设有钢梁支撑固定位(3),所述的槽钢梁(I)的右端设有斜撑固定位(4),所述的槽钢梁(I)的头部与尾部分别设有槽钢固定孔(5)。2.根据权利要求1所述的...
【专利技术属性】
技术研发人员:周明海,李德军,章泽锋,
申请(专利权)人:浙江宝盛建设集团有限公司,
类型:实用新型
国别省市:
还没有人留言评论。发表了对其他浏览者有用的留言会获得科技券。