The utility model provides a high temperature geothermal tunnel cooling system, which comprises a cooling water pipe, which is arranged along the tunnel, and a plurality of sprinklers are arranged evenly at intervals on the cooling water pipe, each of which can be controlled separately. By laying cooling water pipes in high temperature geothermal tunnel, there are several sprinklers on the cooling water pipes evenly spaced. Each sprinkler can be controlled independently. Therefore, the temperature of the sprinkler can be controlled independently in which part of the tunnel, which makes the temperature of the location drop rapidly, making the cooling more targeted and the effect more obvious. At the same time, avoid large-scale water spraying to cool down, thereby saving water.
【技术实现步骤摘要】
一种高温地热隧道冷却系统
本技术涉及高温隧道施工
,具体而言,涉及一种高温地热隧道冷却系统。
技术介绍
隧道施工时环境复杂,特别是在部分隧道段存在地热高温,对施工造成一定困难,如下:1.乳化炸药在40℃~50℃会熔化、产生拒爆;普通毫秒导爆管雷管在80℃以上会产生热反应爆炸、失效等,导致现场施工作业人员存在较大安全隐患。2.高温条件下施工作业人员易发生中暑、头晕、呕吐等现象以及热气、热喷水、烫伤及其他综合病症。3.因温度较高,施工人员及设备降效明显,导致钻爆作业时间长,钻爆作业人员疲劳程度大,影响施工进度。4.高温条件下施工设备施工降效,直接影响施工进度。5.高温条件下测量仪器精确性受影响较大,影响开挖质量。6.高温条件下围岩表面易产生不利影响,岩面喷射混凝土后立即脱落,无法粘结;且高温条件下混凝土凝结时间快,导致混凝土与岩面不能可靠粘接,影响施工质量。
技术实现思路
本技术的主要目的在于提供一种高温地热隧道冷却系统,以解决现有技术中的高温地热隧道温度难以控制的问题。为了实现上述目的,本技术提供了一种高温地热隧道冷却系统,包括冷却水管,冷却水管沿隧道布置,冷却水管上面均匀间隔设置有多个喷水装置,每个喷水装置可以单独控制。进一步地,高温地热隧道冷却系统包括多条冷却水管,冷却水管布置在隧道的不同部位。进一步地,多条冷却水管沿隧道壁布置。进一步地,喷水装置上设置有控制喷水装置启闭的电磁阀和用于检测喷水装置所在部位温度的温度传感器,电磁阀根据温度传感器的检测值自动进行启闭。进一步地,当温度传感器的检测值大于设定值时,电磁阀开启,喷水装置进行喷水降温,当温度传感器 ...
【技术保护点】
1.一种高温地热隧道冷却系统,其特征在于,包括冷却水管(10),所述冷却水管(10)沿所述隧道布置,所述冷却水管(10)上面均匀间隔设置有多个喷水装置(20),每个喷水装置(20)可以单独控制。
【技术特征摘要】
1.一种高温地热隧道冷却系统,其特征在于,包括冷却水管(10),所述冷却水管(10)沿所述隧道布置,所述冷却水管(10)上面均匀间隔设置有多个喷水装置(20),每个喷水装置(20)可以单独控制。2.根据权利要求1所述的高温地热隧道冷却系统,其特征在于,所述高温地热隧道冷却系统包括多条所述冷却水管(10),所述冷却水管(10)布置在所述隧道的不同部位。3.根据权利要求2所述的高温地热隧道冷却系统,其特征在于,多条所述冷却水管(10)沿隧道壁布置。4.根据权利要求1所...
【专利技术属性】
技术研发人员:杨贵春,杨发智,孙建新,卢高辉,彭代枫,韩涛,刘保中,
申请(专利权)人:中国水利水电第四工程局有限公司,