Aiming at the problem of supporting pile in foundation pit at present, in order to achieve better theoretical analysis and simulation teaching, and to complete reasonable supporting design and optimal economic benefit, the invention discloses a simulation method of excavation process of foundation pit with reasonable design, flexible use and low cost; according to the presumed soil of side wall of supporting pile before excavation of foundation pit Pressure distribution forms are used to pressurize the pressure components at any height, and then unload the load of the pressure components at one side of the simulator step by step according to the design conditions. The pressure components at other positions automatically realize the corresponding stress and displacement changes through the springs in the pressure components, and simulate the excavation of foundation pit soil in real time. The invention can be widely used in the field of civil engineering design and construction.
【技术实现步骤摘要】
一种基坑开挖过程的模拟方法
本专利技术一种基坑开挖过程的模拟方法,属于土木工程设计与施工
技术介绍
现代城市在不断发展过程中,建筑物趋于密集化,高层建筑及地下设施增多,在建筑密集区高层建筑下部结构施工中将存在着深基坑开挖及稳定问题。由于支护工程计算随土层的变化而更趋复杂,设计过程中常将多个土层简化,而且深基坑施工和支护往往以经验和工程类比法为主,尤其对支护方案的优选和支护构件的优化研究的并不深入系统。实际上,在基坑支护结构内力计算中,首先需要确定支护结构的计算简化模型、假定支护结构外侧土压力的分布、基坑开挖过程中土压力的变化,现有的《建筑基坑支护技术规程》(JGJ120)在计算悬臂支档结构和锚拉式支档结构时,把支护桩外侧的土压力看作是主动土压力,把基坑内侧土反力采用线弹性模型,支护桩看着弹性梁进行计算,在计算中也没有考虑土压力是动态变化。如何采用物理模型直观地、可视化地表现这种计算过程中,而且合理的考虑基坑开挖过程土压力的变化,是土木工程教学和工程计算必须面对的问题。
技术实现思路
本专利技术针对目前基坑支护桩的问题,为了实现更好的理论分析和模拟教学,也为了完成合理支护设计和最优的经济效益,公开一种设计合理、使用灵活、成本低的基坑开挖过程的模拟方法。为了解决上述技术问题,本专利技术采用的技术方案为:一种基坑开挖过程的模拟方法,按下述步骤实施:第一步:安装反力框架;将反力框架固定于地面,确保底部横梁水平布置,侧梁垂直布置;第二步:模型桩参数的确定;确定模型桩的桩长,其中桩长=桩顶预留长度+计算桩长+桩端预留长度,计算桩长为支护桩的桩顶到桩底之间的距离按 ...
【技术保护点】
1.一种基坑开挖过程的模拟方法,其特征在于,按下述步骤实施:第一步:安装反力框架(1);将反力框架(1)固定于地面,确保底部横梁(12)水平布置,侧梁(13)垂直布置;第二步:模型桩(5)参数的确定;确定模型桩(5)的桩长,其中桩长=桩顶预留长度+计算桩长+桩端预留长度,计算桩长为支护桩的桩顶到桩底之间的距离按比例确定的长度,以及用于施加侧向土压力面的桩的宽度、桩侧土层开挖前的沿计算桩长侧向土压力曲线形态和静止土压力的形态;第三步:安装定位调节组件(4);支撑板(42)布置于顶部横梁(11)和底部横梁(12)之间,且支撑板(42)的上、下端均固定于凹槽(14)内,并确保支撑板(42)的竖向轴线与铅垂线重合;在每个横梁槽口内的插孔(47)内安装调节杆(46),调节杆(46)穿过调节螺母(45),调节杆(46)上端固定在定位横梁(44)上,通过旋转调节螺母(45)使同一高度的所有定位横梁(44)在同一水平面;第四步:在模型桩(5)侧安装施压组件(2)和传压组件(3);预先加工施压组件(2),把套筒(23)两端穿过反力框架(1)的侧梁(13),定位杆(28)外置弹簧(22),且定位杆(28) ...
【技术特征摘要】
1.一种基坑开挖过程的模拟方法,其特征在于,按下述步骤实施:第一步:安装反力框架(1);将反力框架(1)固定于地面,确保底部横梁(12)水平布置,侧梁(13)垂直布置;第二步:模型桩(5)参数的确定;确定模型桩(5)的桩长,其中桩长=桩顶预留长度+计算桩长+桩端预留长度,计算桩长为支护桩的桩顶到桩底之间的距离按比例确定的长度,以及用于施加侧向土压力面的桩的宽度、桩侧土层开挖前的沿计算桩长侧向土压力曲线形态和静止土压力的形态;第三步:安装定位调节组件(4);支撑板(42)布置于顶部横梁(11)和底部横梁(12)之间,且支撑板(42)的上、下端均固定于凹槽(14)内,并确保支撑板(42)的竖向轴线与铅垂线重合;在每个横梁槽口内的插孔(47)内安装调节杆(46),调节杆(46)穿过调节螺母(45),调节杆(46)上端固定在定位横梁(44)上,通过旋转调节螺母(45)使同一高度的所有定位横梁(44)在同一水平面;第四步:在模型桩(5)侧安装施压组件(2)和传压组件(3);预先加工施压组件(2),把套筒(23)两端穿过反力框架(1)的侧梁(13),定位杆(28)外置弹簧(22),且定位杆(28)一端依次与活塞(26)和传力杆(24)连接,传力杆(24)穿过限位板(25)插入连接板(32)的U型槽(34)内,且与U型槽(34)底平面接触,并通过连接销与连接板(32)固定,定位杆(28)另一端插入空心螺纹杆(21)中,且空心螺纹杆(21)通过丝扣与套筒(23)连接,并在外端加装加载把手(27);在传压组件(3)的承压板(31)几何中心预留位置安装压力传感器,压力传感器面向模型桩(5)表面与承压板(31)表面齐平,然后在承压板(31)面向模型桩(5)一侧表面安装垫块(35),把每一个传压组件(3)均通过定位板(41)连...