The invention relates to a construction method for building a wall opening and preroof restoration of masonry structure, which includes the following steps: (1) cleaning the hole and preprocessing the hole; 2. Building a new wall in the hole; (3) the top surface and hole of the new masonry wall when the distance between the top of the new wall of the masonry and the top of the hole reaches the set value. An embedded controllable unloading device is installed between the top of the mouth; (4) filling the new wall of the masonry and the gap between the old walls around the hole. The invention can ensure the dense connection of the new and old wall of the hole, and by setting the embedded controllable unloading device to preload the new wall masonry in the hole, effectively restore the load transfer path of the building wall, improve the safety and reliability of the restoration of the hole, so as to ensure the structure safety of the building and effectively eliminate the hidden danger of the safety.
【技术实现步骤摘要】
一种砌体结构破墙开洞预顶恢复施工工法
本专利技术属于建筑施工
,尤其涉及一种砌体结构破墙开洞预顶恢复施工工法。
技术介绍
目前在砌体结构的建筑物(特别是居民楼)的承重墙上进行破墙开洞的现象还是比较多的,这种无序、多次拆改承重墙的行为严重影响房屋质量,甚至最终导致房屋的倒塌,造成人员伤亡事故。为确保居住人员安全,对破墙开洞进行有效恢复是非常必要的。住宅房屋破墙开洞一般都是直接将砖墙进行凿除形成矩形门洞或窗洞,未经考虑的恢复就是直接安排工人从洞口底部进行平砌,平砌到离洞口顶部还有20公分左右开始斜砌,斜砌至封闭洞口即告完成。这种采用砌体简单将洞口封闭的方法并不意味着墙体已砌筑密实,洞口上部墙体的荷载(重量)并不能有效传递到后砌墙体上,建筑物的结构安全未恢复到原有水平,因此建筑物仍存在结构安全隐患。
技术实现思路
本专利技术为了解决上述技术问题,提供一种砌体结构破墙开洞预顶恢复施工工法,其能确保洞口新老墙体的密实连接,恢复建筑物墙体荷载传递路径,确保建筑物的结构安全,提高洞口恢复的安全性和可靠性。本专利技术的上述技术问题主要是通过下述技术方案得以解决的:本专利技术的一种砌体结构破墙开洞预顶恢复施工工法,包括下列步骤:①清理洞口,并对洞口进行预处理;②在洞口中砌筑新墙体;③当砌筑的新墙体的顶面和洞口的顶部之间的距离到达设定值时,在砌筑的新墙体的顶面和洞口的顶部之间安装埋入式可控卸荷器;④对砌筑的新墙体和洞口周围老墙体之间的空隙进行灌浆封闭;⑤最后对封闭好的洞口进行拆模养护。埋入式可控卸荷器包括底板和顶板,底板中心设置有一个空心管,空心管内插入一根螺杆,螺杆的中部 ...
【技术保护点】
1.一种砌体结构破墙开洞预顶恢复施工工法,其特征在于包括下列步骤:①清理洞口,并对洞口进行预处理;②在洞口中砌筑新墙体;③当砌筑的新墙体的顶面和洞口的顶部之间的距离到达设定值时,在砌筑的新墙体的顶面和洞口的顶部之间安装埋入式可控卸荷器;④对砌筑的新墙体和洞口周围老墙体之间的空隙进行灌浆封闭;⑤最后对封闭好的洞口进行拆模养护。
【技术特征摘要】
1.一种砌体结构破墙开洞预顶恢复施工工法,其特征在于包括下列步骤:①清理洞口,并对洞口进行预处理;②在洞口中砌筑新墙体;③当砌筑的新墙体的顶面和洞口的顶部之间的距离到达设定值时,在砌筑的新墙体的顶面和洞口的顶部之间安装埋入式可控卸荷器;④对砌筑的新墙体和洞口周围老墙体之间的空隙进行灌浆封闭;⑤最后对封闭好的洞口进行拆模养护。2.根据权利要求1所述的一种砌体结构破墙开洞预顶恢复施工工法,其特征在于所述的步骤①包括下列步骤:(11)对位于洞口四周边缘部位的老墙体进行切割;(12)拆除洞口及切割范围内装饰层,露出老墙体的原砖砌体,清理洞口四周疏松的材料,对破损部位采用聚合物修补砂浆进行填补;(13)洞口底部安装模板,并采用灌浆料浇筑找平。3.根据权利要求1所述的一种砌体结构破墙开洞预顶恢复施工工法,其特征在于所述的步骤②包括下列步骤:(21)将砖砌体洒水湿润后,采用一顺一丁和一皮一灌浆的砌筑方法在洞口中用聚合物修补砂浆分皮砌筑新墙体,保证灰缝饱满,砌筑的新墙体的左右两侧留设马牙槎,马牙槎上凸出的侧面和与之相对的洞口边缘老墙体之间预留一段空隙;(22)砌筑的新墙体到达设定高度时,在洞口左右两侧的老墙体上各植入两根前后分布的拉结钢筋,拉结钢筋的一端位于老墙体中,拉结钢筋的另一端跨过马牙槎伸入到新墙体中;(23)植筋完毕继续向上砌筑,重复步骤(22),直到砌筑的新墙体的顶面和洞口的顶部之间的距离到达设定值。4.根据权利要求1或2或3所述的一种砌体结构破墙开洞预顶恢复施工工法,其特征在于所述的步骤③包括下列步骤:(31)确定埋入式可控卸荷器的安装位置:根据砌筑的新墙体长度确定埋入式可控卸荷器的个数,埋入式可控卸荷器的安装位置在砌筑的新墙体上均匀分布,对埋入式可控卸荷器的安装位置的上下墙面进行检查,如不平整则进行找平处理;(32)安装并调试埋入式可控卸荷器:放入埋入式可控卸荷器和与之相连的压力传感器,压力传感器通过通讯接口与电脑连接,测得的压力值实时传输至电脑并实时显示;采用扭力扳手旋转埋入式可控卸荷器上的第一螺母,使埋入式可控卸荷器的顶板与洞口顶部接触,继续转动第一螺母进行缓慢加载,并注意观察电脑上显示的压力值的变化,直到显示的压力值到达预定加载值。5.根据权利要求4所述的一种砌体结构破墙开洞预顶恢复施工工...
【专利技术属性】
技术研发人员:杨军龙,李静,倪宏演,
申请(专利权)人:浙江核力建筑特种技术有限公司,
类型:发明
国别省市:浙江,33