With closed cover with prefabricated cable insulation, including wire rod is arranged on the drop switch, lightning arrester and transformer connected by the connecting wire, which is connected into the main line in the first line including copper plastic wire, copper line side wall connected electricity grounding ring, electricity testing grounding ring including grounding ring tube and the main outer wall of the copper pipe line coated silicon rubber insulation layer, electricity testing grounding ring under bare ground electricity, the first plastic copper head is connected with the first connecting head and drop switch connected between the first terminal and the main line of the first head of copper plastic copper wire wrapped first silicon rubber insulation layer, a first plastic copper wire even the second head chief wiring connected with the transformer, between the second and the main line of the first copper wiring head plastic copper wire wrapped second silicon rubber insulation layer, the first is located in the main section of internal plastic copper brass for strip Plastic wrapping wire with third plastic copper wire core, third plastic copper wire wrapped third silicon rubber insulation layer.
【技术实现步骤摘要】
带封闭绝缘罩的配变预制连接线
本技术涉及电线杆上的跌落式开关与变压器之间的连接线,特别是涉及带封闭绝缘罩的配变预制连接线。
技术介绍
已有电线杆上的跌落式开关、变压器和避雷器之间通常是直接用普通的连接线进行连接,由于国家电网颁布10KV变压器台区要求,根据全国统一10KV配变台区典型设计安装和10KV配变台区绝缘化要求,普通连接线绝缘性能差,现场安装、施工麻烦,工人接线时穿刺线夹容易发生触点不牢挂接地后造成导线损伤,存在的安全隐患较大。
技术实现思路
本技术的目的是为了克服已有技术存在的缺点,提供一种工厂化生产,导电不佳,减少接点,降低事故发生点,降低制造成本,安装方便,简化操作,减少现场操作工作量,工人安装安全性高的带封闭绝缘罩的配变预制连接线。本技术带封闭绝缘罩的配变预制连接线的技术方案是:包括电线杆,电线杆上设置跌落式开关、避雷器和变压器,跌落式开关、避雷器和变压器经连接线相连,其特征在于:所述的连接线包括主线铜管,主线铜管中穿入第一塑铜线,在主线铜管的侧壁连接验电接地环,所述的验电接地环包括接地环铜管,接地环铜管与主线铜管焊接连接,在接地环铜管和主线铜管的外壁包覆主线硅橡胶绝缘层,主线硅橡胶绝缘层位于验电接地环的下端有裸露验电接地点,所述的第一塑铜线一头穿过主线铜管的上端连接第一接线头子,第一接线头子与跌落式开关相连接,在第一接线头子与主线铜管之间的第一塑铜线外壁包覆第一硅橡胶绝缘层,第一塑铜线的另一头穿过主线铜管的下端连接第二接线头子,第二接线头子与变压器相连接,在第二接线头子与主线铜管之间的第一塑铜线外壁包覆第二硅橡胶绝缘层,所述第一塑铜线位于主线 ...
【技术保护点】
带封闭绝缘罩的配变预制连接线,包括电线杆(1),电线杆上设置跌落式开关(2)、避雷器(3)和变压器(4),跌落式开关、避雷器和变压器经连接线(5)相连,其特征在于:所述的连接线(5)包括主线铜管(6),主线铜管中穿入第一塑铜线(7),在主线铜管(6)的侧壁连接验电接地环(8),所述的验电接地环包括接地环铜管(9),接地环铜管与主线铜管焊接连接,在接地环铜管和主线铜管的外壁包覆主线硅橡胶绝缘层(10),主线硅橡胶绝缘层位于验电接地环(8)的下端有裸露验电接地点(11),所述的第一塑铜线(7)一头穿过主线铜管(6)的上端连接第一接线头子(12),第一接线头子与跌落式开关(2)相连接,在第一接线头子与主线铜管之间的第一塑铜线(7)外壁包覆第一硅橡胶绝缘层(13),第一塑铜线的另一头穿过主线铜管(6)的下端连接第二接线头子(14),第二接线头子与变压器(4)相连接,在第二接线头子与主线铜管(6)之间的第一塑铜线(7)外壁包覆第二硅橡胶绝缘层(15),所述第一塑铜线(7)位于主线铜管段内部为剥去塑料包皮的线芯,线芯连接第三塑铜线(16)的线芯,第三塑铜线外壁包覆第三硅橡胶绝缘层(17),第三塑铜 ...
【技术特征摘要】
1.带封闭绝缘罩的配变预制连接线,包括电线杆(1),电线杆上设置跌落式开关(2)、避雷器(3)和变压器(4),跌落式开关、避雷器和变压器经连接线(5)相连,其特征在于:所述的连接线(5)包括主线铜管(6),主线铜管中穿入第一塑铜线(7),在主线铜管(6)的侧壁连接验电接地环(8),所述的验电接地环包括接地环铜管(9),接地环铜管与主线铜管焊接连接,在接地环铜管和主线铜管的外壁包覆主线硅橡胶绝缘层(10),主线硅橡胶绝缘层位于验电接地环(8)的下端有裸露验电接地点(11),所述的第一塑铜线(7)一头穿过主线铜管(6)的上端连接第一接线头子(12),第一接线头子与跌落式开关(2)相连接,在第一接线头子与主线铜管之间的第一塑铜线(7)外壁包覆第一硅橡胶绝缘层(13),第一塑铜线的另一头穿过主线铜管(6)的下端连接第二接线头子(1...