The invention relates to a bridge static load test device, in particular to a long span simple beam prestressed self balanced static load test platform, which comprises an experimental beam, a jack, a counterforce beam, an upper crossbeam, a vertical pull rod, a bearing pier, a lever beam and a ground reaction pier. The reaction beam in test beam above, between the jack in the reaction beam and the test beam, beam in the reaction beam ends; on both ends of the beam is provided with a vertical rod, the lower end of the pull rod and vertical lever beam rear end of the lever beam connected by a pin shaft through the bearing lever of the front beam and pier, ground reaction force contact force test pier. The counterforce beam adopts segmental assembled prestressed structure, which can save a large amount of material. The test is carried out without the bridge plate drilled through the vertical tie rod. The structure of the test platform is scientific, affordable, convenient on-site beam relocation transition, eradication of the current 40m foundation concrete beam by using the heavy force type test platform to blow up the rehabilitation problem, static load test, suitable for various span beam.
【技术实现步骤摘要】
一种桥梁静载试验用预应力钢管混凝土自平衡式静载试验台
本专利技术涉及一种桥梁静载试验装置,尤其是指一种大跨度简支箱梁静载试验用预应力钢管混凝土自平衡式静载试验台。
技术介绍
ZL98248613.8号专利文献公开了一种预制预应力混凝土简支梁用静载试验装置,利用万能杆件拼装桁梁抵抗试验荷载,从而实现在施工现场对预应力混凝土简支梁进行静载试验。但是该装置具有以下缺点:1、其反力架是由万能杆件桁架梁构成,因杆件及节点板种类繁多、拼装、拆卸复杂,成本高昂。2、万能杆件桁梁张拉,因在杆件节点生成张拉锚固点构造复杂,施作受限,且节点设计为刚性节点,实际可能存在铰接点,故桁梁张拉压缩变形量大、反拱变形大,截面抗弯能力与张拉预应力大小难以恰当控制。又因反拱变形大,千斤顶横梁随之倾斜而不能保持水平,试验时极易造成千斤顶滑出。3、仅适用于T梁,若扩展延伸用于箱梁静载试验,则需增设上、下横梁。由于下横梁位于支座下面,致使竖拉杆需要穿过桥面板的钻孔才能与上横梁联结,钻孔困难且对梁体造成破坏。
技术实现思路
本专利技术所要解决的技术问题就是针对上述缺陷,提供一种高刚度、少耗材、低成本、结构简单、组装方便,并且不需桥面板钻孔的、适应于各种梁型、各种跨度的预应力混凝土简支梁静载试验台。本专利技术是通过以下技术方案实现的:一种桥梁静载试验用预应力钢管混凝土自平衡式静载试验台,包括试验梁、千斤顶、反力梁、上横梁、竖拉杆、支座墩、杠杆梁及地面反力墩,所述反力梁位于试验梁上方,千斤顶位于反力梁和试验梁之间,反力梁两端设有上横梁,上横梁两端设有竖拉杆,竖拉杆一端和上横梁连接,另端与杠杆梁后端部连接。 ...
【技术保护点】
一种桥梁静载试验用预应力钢管混凝土自平衡式静载试验台,包括试验梁、千斤顶、反力梁、上横梁、竖拉杆、支座墩、杠杆梁及地面反力墩,所述反力梁位于试验梁上方,千斤顶位于反力梁和试验梁之间,反力梁两端设有上横梁,上横梁两端设有竖拉杆,竖拉杆一端和上横梁连接,另端与杠杆梁后端部连接。杠杆梁通过销轴联结穿过支座墩,杠杆梁前端与地面反力墩接触提供试验反力。其特征是试验荷载——反力梁——上横梁——竖拉杆——支座墩及杠杆梁——地面反力墩,实现试验梁的试验荷载与试验台的反力组成的闭合力系自平衡。
【技术特征摘要】
1.一种桥梁静载试验用预应力钢管混凝土自平衡式静载试验台,包括试验梁、千斤顶、反力梁、上横梁、竖拉杆、支座墩、杠杆梁及地面反力墩,所述反力梁位于试验梁上方,千斤顶位于反力梁和试验梁之间,反力梁两端设有上横梁,上横梁两端设有竖拉杆,竖拉杆一端和上横梁连接,另端与杠杆梁后端部连接。杠杆梁通过销轴联结穿过支座墩,杠杆梁前端与地面反力墩接触提供试验反力。其特征是试验荷载——反力梁——上横梁——竖拉杆——支座墩及杠杆梁——地面反力墩,实现试验梁的试验荷载与试验台的反力组成的闭合力系自平衡。2.如权利要求1所述的桥梁静载试验用预应力钢管混凝土自平衡式静载试验台,其特征是所述反力梁由预应力钢管混凝土矩形梁与钢管预应力拱架构成的组合梁,节段拼装装法兰盘联结后实施预应力张拉,组成反力梁整体,拱架高度及双向预应力提供了足够的抗...
【专利技术属性】
技术研发人员:孙金更,姜会增,张彩亮,周兆春,
申请(专利权)人:北京华横新技术开发公司,北京国铁桥梁技术咨询有限公司,北京中铁房山桥梁有限公司,
类型:发明
国别省市:北京,11
还没有人留言评论。发表了对其他浏览者有用的留言会获得科技券。