An underground drainage ditch, including along the basement on both sides of the wall and set up the first ditch, second ditch, ditch, ditch and connected to the first second of the Sanming Sanming across the ditch, the ditch lane, the Sanming groove for the arc groove, the groove is provided with Sanming Steel pipe, the pipe ends extending to the first ditch, second ditch, the ditch is arranged in Sanming Steel. The utility model aims to provide an underground parking lot drainage ditches, can strengthen the structural strength across the ditch lane, prolong the service life of the drainage ditch. The utility model has the following advantages: strengthening the drainage ditch across the lane, prolong the service life of the drainage ditch, and reduce traffic resistance.
【技术实现步骤摘要】
一种地下停车场排水明沟
本技术涉及一种排水明沟,特别涉及一种地下停车场排水明沟。
技术介绍
排水明沟即露天的下水道,一般靠近勒脚下部设置,防止因积水渗入地基而造成建筑物的下沉。地下停车场过车道两侧的排水明沟有时会横跨过车道连接,而车辆对排水明沟的碾压和破坏使得排水明沟的使用寿命大大缩短。
技术实现思路
本技术的目的在于提供一种地下停车场排水明沟,可加强横跨过车道的排水明沟的结构强度,延长排水明沟的使用寿命。本技术的上述目的是通过以下技术方案得以实现的:一种地下室排水明沟,包括分别沿地下室两侧墙体而设的第一明沟、第二明沟,以及连接第一明沟、第二明沟的第三明沟,第三明沟横跨过车道而设,所述第三明沟为弧形沟槽,第三明沟内设有钢管,钢管两端伸至第一明沟、第二明沟内,钢管凸出第三明沟设置。通过采用上述技术方案,通过将第三明沟设计成弧形的较浅沟槽,可提高第三明沟的基础强度,而在第三明沟内放置将第一明沟、第二明沟连通的钢管,钢管凸出第三明沟,汽车通过时从钢管上碾过,跳过了车轮先从第三明沟顶部一侧压下,再从第三明沟顶部另一侧开出沟槽的过程,从而对第三明沟顶部两侧形成了较好的保护,且钢管可 ...
【技术保护点】
一种地下停车场排水明沟,包括分别沿地下室两侧墙体而设的第一明沟(1)、第二明沟(2),以及连接第一明沟(1)、第二明沟(2)的第三明沟(3),第三明沟(3)横跨过车道(8)而设,其特征在于:所述第三明沟(3)为弧形沟槽,第三明沟(3)内设有钢管(4),钢管(4)两端伸至第一明沟(1)、第二明沟(2)内。
【技术特征摘要】
1.一种地下停车场排水明沟,包括分别沿地下室两侧墙体而设的第一明沟(1)、第二明沟(2),以及连接第一明沟(1)、第二明沟(2)的第三明沟(3),第三明沟(3)横跨过车道(8)而设,其特征在于:所述第三明沟(3)为弧形沟槽,第三明沟(3)内设有钢管(4),钢管(4)两端伸至第一明沟(1)、第二明沟(2)内。2.根据权利要求1所述的一种地下停车场排水明沟,其特征在于:所述钢管(4)底部固定设有与第三明沟(3)的槽壁贴合的弧形板(5)。3.根据权利要求2所述的一种地下停车场排水明沟,其特征在于:所述弧形板(5)两侧...
【专利技术属性】
技术研发人员:仝威,费腾,张天朋,
申请(专利权)人:无锡市天宇民防建筑设计研究院有限公司,
类型:新型