The invention discloses a complex geology high slope grade slope reinforcement reverse construction method, the method for short-term natural stability of cutting slope by slope, slope cutting after a first set of climbing scaffolding, reverse reinforcement construction technology of grid beam anchorage anchor closed after the first time. The construction feature includes the following steps: preparation of construction; construction slag road; slope rock broken zone and surface disposal; preliminary anchor closed; layer blasting, classification of cutting slope excavation; erection climbing frame; side slope disposal and protection; cable (rod) construction; deep drainage pipe construction; grid beam anchor pier construction; monitoring and evaluation of slope reinforcement. High slope classification provides slope reinforcement reverse construction method is applicable to complex geological conditions, complex terrain slope multi level slope reinforcement construction, with high efficiency, saving time, reverse construction reinforcement effect is safe and reliable, good economic performance.
【技术实现步骤摘要】
本专利技术涉及一种复杂地质高边坡分级放坡加固逆序施工方法,尤其适用于复杂地质条件、复杂地形、高边坡多级放坡条件下,破碎带、尾矿渣堆积体边坡、深坑的边坡加固施工。
技术介绍
山体高大边坡、尾矿渣堆积体边坡、带水深坑等复杂地形、复杂地质条件下,边坡的开挖、加固、支护等关系到边坡的稳定与安全,涉及边坡的开挖方法、降水方法、加固方法、支护方法、施工平台构建、边坡稳定监测与评价、后期维护与施工安全等诸多技术问题。开展边坡加固施工技术研究,特别是逆序施工方法的研究,对于缩短工期,降低成本,提高工效,降低能耗,缩短边坡削坡后的暴露时间,提高边坡的稳定性和安全性等,有重要的工程应用前景。
技术实现思路
本专利技术提供一种复杂地质高边坡分级放坡加固逆序施工方法,目的是开发出一种适宜复杂地质与地形条件下的高边坡多级放坡的边坡加固施工技术,满足破碎带、尾矿渣堆积体边坡、深坑的边坡加固施工。为实现上述目的,复杂地质高边坡分级放坡加固逆序施工方法,利用边坡削坡后短期的自然稳定,先削坡后一次搭设爬坡脚手架,先初次喷锚封闭后网格梁锚固加固的逆序施工技术。本专利技术按以下技术方案实现:一种复杂地质高边坡分级放坡加固逆序施工方法,该方法包括以下步骤,步骤一:施工准备;步骤二:修建出渣道路;步骤三:坡面破碎带、危岩处置;步骤四:逐层爆破、分级削坡开挖;步骤五:面层初步喷锚封闭;步骤六:搭设爬坡操作架;步骤七:不良边坡处置与防护;步骤八:锚索、锚杆施工;步骤九:深层排水管施工;步骤十:网格梁、锚墩施工;步骤十一:边坡监测与加固评价。优选的是,所述步骤一具体为:利用边坡开挖之短期的自然稳定,采用边 ...
【技术保护点】
一种复杂地质高边坡分级放坡加固逆序施工方法,其特征在于:该方法包括以下步骤,步骤一:施工准备;步骤二:修建出渣道路;步骤三:坡面破碎带、危岩处置;步骤四:逐层爆破、分级削坡开挖;步骤五:面层初步喷锚封闭;步骤六:搭设爬坡操作架;步骤七:不良边坡处置与防护;步骤八:锚索、锚杆施工;步骤九:深层排水管施工;步骤十:网格梁、锚墩施工;步骤十一:边坡监测与加固评价。
【技术特征摘要】
1.一种复杂地质高边坡分级放坡加固逆序施工方法,其特征在于:该方法包括以下步骤,步骤一:施工准备;步骤二:修建出渣道路;步骤三:坡面破碎带、危岩处置;步骤四:逐层爆破、分级削坡开挖;步骤五:面层初步喷锚封闭;步骤六:搭设爬坡操作架;步骤七:不良边坡处置与防护;步骤八:锚索、锚杆施工;步骤九:深层排水管施工;步骤十:网格梁、锚墩施工;步骤十一:边坡监测与加固评价。2.根据权利要求1所述的一种复杂地质高边坡分级放坡加固逆序施工方法,其特征在于,所述步骤一具体为:利用边坡开挖之短期的自然稳定,采用边坡逆序施工技术方案,先削坡然后搭设施工脚手架再施工带锚索的网格梁的逆序施工方法。3.根据权利要求1所述的一种复杂地质高边坡分级放坡加固逆序施工方法,其特征在于,所述步骤二具体为:高边坡多级放坡修建出渣道路和平台、后期道路结合;削坡到预定标高之后,满足后期结构施工;所述步骤三具体为:先对坡面松动岩块人工清除,拆除障碍物;对边坡局部不稳定处进行清刷;对裂缝进行灌浆或勾缝处理;然后支护施工。4.根据权利要求1所述的一种复杂地质高边坡分级放坡加固逆序施工方法,其特征在于,所述步骤四具体为:削坡施工阶段,分段分层施工,同步进行削坡支护施工,减少边坡坡面无支护暴露的时间;选用爆破作业,近接建筑区域采用浅孔微差分层爆破方法,严格控制单段装药量和爆破震动,保证近接建筑的安全;边坡部分,采用边坡轮廓爆破法,保证边坡的稳定和平整;爆破台阶高度根据地质情况取5m~12m;钻孔采用多排孔,钻孔方向保持平行,钻孔形式采用倾斜孔,布孔方式采用梅花形;设置多级平台开挖,土石方开挖顺序自上而下施工,渣石削落至出渣平台,从平台两侧道路运出。5.根据权利要求1所述的一种复杂地质高边坡分级放坡加固逆序施工方法,其特征在于,所述步骤五具体为:对坡面进行挂网喷射砼处理;分两次喷射,分级削坡开挖之后进行初次初步喷锚封闭;待后续网格梁完成后,挂网进行第二次喷锚封闭。6.根据权利要求1所述的一种复杂地质高边坡分级放坡加固逆序施工方法,其特征在于,所述步骤六具体为:采用钢管扣件式综合爬坡脚手架体系作为施工平台;搭设脚手架立杆纵距、横距及步距均需满足预应力锚索2000mm操作平台的施工需要;按从下至上顺序分有若干个台阶坡,从底至上开始搭设脚手架,横向立杆每上一级台阶坡自外向内收1~2根杆;在台阶部位设置钢管...
【专利技术属性】
技术研发人员:王军强,
申请(专利权)人:江苏建筑职业技术学院,
类型:发明
国别省市:江苏;32