The invention discloses a composite Bailey steel bridge for flood control and flood control, and its construction method, which comprises the following steps: the Bailey steel bridge at the head of the gate is assembled with a reinforced chord, an upper reinforced chord and a bottom reinforced oblique chord to partially strengthen the connecting parts of the Bailey plate; the suspension erection system adopts an adjustable horizontal roll with a limited plate and a bowl-buckled limited frame to prevent the lateral derailment of the Bailey steel bridge. The composite flood control system uses embedded bolts and flower basket bolts to tighten the Bailey steel bridge; the suspension method demolishes the system with adjustable rock support guide beams with limit plates. This construction method increases the overall stability of the Bailey steel bridge and the safety of the surrounding environment. The joints of the Bailey steel bridge have high shear strength, strong bearing capacity, and improves the suspension erection and suspension demolition. The anti-overturning performance and anti-scouring performance during flood season ensure the quality and safety of Bailey Steel Bridge, which can achieve better technical and economic benefits in practical engineering.
【技术实现步骤摘要】
复合式防洪度汛闸首贝雷钢桥及施工方法
本专利技术涉及桥梁施工领域,具体涉及复合式防洪度汛闸首贝雷钢桥及施工方法。
技术介绍
随着我国水电建设事业的发展,大部分江河的水电梯级开发已延伸到上游,工程地点多处于地形复杂、交通不便的山区,为主体工程服务的进场便道也多跨越水流湍急的江河。在某些船闸改扩建工程中,为了便于通车和提高施工效率,需要在闸首设置贝雷架桥,连接船闸左右岸,从而延伸施工道路至各施工作业面。目前,常规的贝雷桥安装技术主要采用悬推法,即采取在正桥前端设置鼻架先搭到对岸桥墩后再逐步牵拉正桥到位,一般包括安放滚轴、拼装鼻架、拼装桥节、推桥、拆除鼻架、落桥和铺装桥面等步骤。在悬推过程中,若稳定力矩小于倾覆力矩,还需在贝雷桥桁架后方配重。相反地,常规的贝雷桥拆除技术主要采用悬拉法,即按照与悬推法相反的顺序进行逐步拆除,一般包括拆除桥面板、千斤顶起桥、安放滚轴、安装鼻架、退桥、拆除桥节和拆除鼻架等步骤。然而,无论是采用悬推法安装还是采用悬拉法拆除贝雷桥,因贝雷桥的自重较大,存在发生倾覆的潜在风险,因此需要对现有技术进一步改进以提高其抗倾覆能力或降低倾覆事故的风险等级。此外,针对用于船闸改扩建工程中的贝雷桥施工,还需考虑洪水冲刷这一风险因素,有必要在防洪度汛期间对贝雷桥采取一定的加固措施。
技术实现思路
本专利技术的目的在于提供一种结构合理、节点连接强度高、悬推架设平稳、抗洪水冲刷能力强、悬拉拆除便捷高效和安全系数高等特点的复合式防洪度汛闸首贝雷钢桥的施工方法,及施工完成的复合式防洪度汛闸首贝雷钢桥。为了实现以上任一专利技术目的,本专利技术提供一复合式防洪度汛闸首贝 ...
【技术保护点】
1.复合式防洪度汛闸首贝雷钢桥的施工方法,其特征在于,包括以下步骤:步骤一,拼装贝雷钢桥:采用闸首贝雷钢桥结构拼装贝雷钢桥:将第一贝雷片(1)的公头(8)和第二贝雷片(2)的母头(9)吻合对接,用下加强弦杆(3)和上加强弦杆(4)连接所述第一贝雷片(1)和所述第二贝雷片(2);确保所述下加强弦杆(3)和所述上加强弦杆(4)的中心螺孔与公头(8)和母头(9)对齐,以及两端螺孔对准下弦杆螺栓孔(12)和上弦杆螺栓孔(13)后,依次采用螺栓(14)紧固中心螺孔和两端螺孔;随后,将底部加强斜弦杆(5)斜向搭接所述第一贝雷片(1)和所述第二贝雷片(2)的下弦杆(10)处并紧固,将横梁(6)横跨所述下弦杆(11)和所述底部加强斜弦杆(5)后与所述第一贝雷片(1)和所述第二贝雷片(2)紧固,重复上述步骤,直至完成贝雷钢桥(16)的整体拼装;步骤二,悬推法架设贝雷钢桥:采用悬推法架设体系悬推架设贝雷钢桥:在闸首左岸(17)一侧平行预埋两道整体式锚板(20),将若干可调式平滚(18)沿纵向均匀布置在所述整体式锚板(20)内侧,调节平滚滑动基座(24)间距与所述贝雷钢桥(16)宽度一致后,采用螺栓(14) ...
【技术特征摘要】
1.复合式防洪度汛闸首贝雷钢桥的施工方法,其特征在于,包括以下步骤:步骤一,拼装贝雷钢桥:采用闸首贝雷钢桥结构拼装贝雷钢桥:将第一贝雷片(1)的公头(8)和第二贝雷片(2)的母头(9)吻合对接,用下加强弦杆(3)和上加强弦杆(4)连接所述第一贝雷片(1)和所述第二贝雷片(2);确保所述下加强弦杆(3)和所述上加强弦杆(4)的中心螺孔与公头(8)和母头(9)对齐,以及两端螺孔对准下弦杆螺栓孔(12)和上弦杆螺栓孔(13)后,依次采用螺栓(14)紧固中心螺孔和两端螺孔;随后,将底部加强斜弦杆(5)斜向搭接所述第一贝雷片(1)和所述第二贝雷片(2)的下弦杆(10)处并紧固,将横梁(6)横跨所述下弦杆(11)和所述底部加强斜弦杆(5)后与所述第一贝雷片(1)和所述第二贝雷片(2)紧固,重复上述步骤,直至完成贝雷钢桥(16)的整体拼装;步骤二,悬推法架设贝雷钢桥:采用悬推法架设体系悬推架设贝雷钢桥:在闸首左岸(17)一侧平行预埋两道整体式锚板(20),将若干可调式平滚(18)沿纵向均匀布置在所述整体式锚板(20)内侧,调节平滚滑动基座(24)间距与所述贝雷钢桥(16)宽度一致后,采用螺栓(14)紧固,平滚滚轮(25)置于所述平滚滑动基座(24)上;架设贝雷钢桥(16)置于所述平滚滚轮(25)上,安装碗扣式限位架(19),贝雷钢桥(16)的前端在闸首右岸(21)的卷扬机(22)牵引下推进架设;步骤三,建立防洪度汛体系:利用贝雷钢桥复合式防洪度汛体系建立防洪度汛体系:在闸首两岸分别平行预埋两道整体式锚板(20),同时在闸首两岸的上游位置安装预埋螺栓(28),在防洪度汛期间,通过钢丝绳(27)连接所述预埋螺栓(28)和所述贝雷钢桥(16)的下弦杆(10),拉紧所述钢丝绳(27);在洪水淹没桥体之前,安装碗扣式限位架(19)与所述整体式锚板(20)固接,拆除部分桥面板(7),并停止所述贝雷钢桥(16)的使用;步骤四,悬拉法拆除贝雷钢桥:采用贝雷钢桥悬拉法拆除体系拆除贝雷钢桥:在闸首左岸(17)一侧将若干可调式平滚(18)沿纵向均匀布置在所述整体式锚板(20)内侧;在闸首右岸(21)沿纵向均匀布置若干可调式摇滚(31),导梁(30)倾斜连接在所述贝雷钢桥(16)前端并放置于所述可调式摇滚(31)上,;调节所述可调式摇滚(31)间距与所述导梁(30)宽度一致后,采用螺栓(14)紧固;拆除桥面板(7)和底座(15),将闸首左岸(17)一侧的贝雷钢桥(16)置于所述可调式平滚(18)上,随后安装碗扣式限位架(19);在闸首左岸(17)上的卷扬机(22)的牵引下悬拉所述贝雷钢桥(16),逐节拆除所述贝雷钢桥(16);最后,依次拆除所述碗扣式限位架(19)、所述可调式平滚(18)和所述可调式摇滚(31)。2.根据权利要求1所述的复合式防洪度...
【专利技术属性】
技术研发人员:蔡贤俊,杨帆,王大华,张岱瑛,徐勇,
申请(专利权)人:四川港航建设工程有限公司,
类型:发明
国别省市:四川,51