The invention relates to a pipe jacking construction method of municipal sewage pipeline, which is suitable for the construction of municipal sewage pipeline with short distance and short construction period, and is suitable for the construction situation with complex soil topography. The concrete pipe is always connected with the front end of the drill pipe, so as to locate the concrete pipe through the drill pipe, reduce the deviation of the concrete pipe and the sudden collapse of the soil, and make the concrete pipe more easily run through the receiving well along the predetermined route. The combination of reamer and high-pressure water gun improves the excavation and transportation efficiency of the earthwork in the concrete pipeline, so as to improve the overall construction efficiency of pipe jacking construction and shorten the construction period, which is suitable for the short-term and geological complex construction conditions with poor soil support.
【技术实现步骤摘要】
市政排污管道顶管施工方法
本专利技术涉及隧道挖掘技术的
,尤其是涉及一种市政排污管道顶管施工方法。
技术介绍
目前顶管施工方法是一种非开挖的施工方法,通过该施工方法可以在少开挖或者不开挖的情况下进行管道埋设。顶管施工方法在工作时,顶管机产生的顶力用于克服管道与周围土壤的摩擦力,以将管道按设计的坡度顶入至土层中,并将土方运走。把工具管或顶管机从工作坑内穿过土层一直推进到接收坑内吊起,随着顶管机的工作,管道将由工作井内穿过土层进入接收井内。管道紧随工具管或掘进机后,埋设在两坑之间。但是在实际施工时,由于施工现场地理环境的差异,较多地方在实施顶管施工时都较为麻烦,如土壤松散的流沙地质,机头顶进后稳定性差,而且在顶管时易出现机头移位和顶管偏差的问题,顶管之间还极易损坏,给顶管施工带来诸多不便,降低施工效率,因此存在改进空间。
技术实现思路
针对现有技术存在的不足,本专利技术的目的在于提供一种市政排污管道顶管施工方法,具有提高对顶管的定位效果和施工效率。为实现上述目的,本专利技术提供了如下技术 ...
【技术保护点】
1.一种市政排污管道顶管施工方法,其特征是:包括以下步骤:/na. 开挖工作井(1)和接收井(2):根据设计管道中心线和两端位置,在选定的施工位置向下挖掘工作井(1)和接收井(2);/nb. 起重机(3)安装:在工作井(1)和接收井(2)上方搭设可移动的起重机(3);/nc. 工作井(1)内顶管顶进设备(11)安装:在工作井(1)底部铺设碎石,碎石内埋设枋木,枋木上安装储水槽(12),在储水槽(12)上水平安装顶管导轨(13),并沿顶管导轨(13)方向安装顶管顶进设备(11),顶管顶进设备(11)设置有第一千斤顶(14),所述工作井(1)侧墙上设置用于支撑第一千斤顶(14) ...
【技术特征摘要】
1.一种市政排污管道顶管施工方法,其特征是:包括以下步骤:
a.开挖工作井(1)和接收井(2):根据设计管道中心线和两端位置,在选定的施工位置向下挖掘工作井(1)和接收井(2);
b.起重机(3)安装:在工作井(1)和接收井(2)上方搭设可移动的起重机(3);
c.工作井(1)内顶管顶进设备(11)安装:在工作井(1)底部铺设碎石,碎石内埋设枋木,枋木上安装储水槽(12),在储水槽(12)上水平安装顶管导轨(13),并沿顶管导轨(13)方向安装顶管顶进设备(11),顶管顶进设备(11)设置有第一千斤顶(14),所述工作井(1)侧墙上设置用于支撑第一千斤顶(14)的后背墙;
d.接收井(2)内钻杆顶进设备安装:在接收井(2)底部铺设碎石,碎石内埋设枋木,枋木上安装钻头(41)顶进设备(21),钻头(41)顶进设备(21)设置有第二千斤顶(22),所述接收井(2)侧墙上设置用于支撑第二千斤顶(22)的后背墙,第二千斤顶(22)朝向工作井(1)方向顶进,第二千斤顶(22)伸出端固定有驱动电机(23);
e.首节钻杆单体(4)顶进:将首节安装有钻头(41)的钻杆单体(4)与驱动电机(23)的驱动端固定,并通过钻头(41)顶进设备(21)顶进,在位于首节钻杆单体(4)前端的接收井(2)侧墙上挖掘一个深30~50厘米的定位孔,通过钻头(41)顶进设备(21)和驱动电机(23)配合将首节钻杆单体(4)顶进坑道,如此重复顶进,直至将首节钻杆单体(4)完全顶进接收井(2)侧墙;
f.钻杆贯穿工作井(1):首节钻杆单体(4)顶进后再在驱动电机(23)和首节钻杆单体(4)之间放置下一节钻杆单体(4),将新的钻杆单体(4)两端分别与驱动电机(23)和首节钻杆单体(4)固定连接,并重复钻头(41)顶进设备(21)和驱动电机(23)配合顶进钻杆单体(4),直至首节钻杆单体(4)贯穿工作井(1)侧墙;
g.首节混凝土管道(5)顶进:将首节混凝土管道(5)放置在顶管导轨(13)上,并通过顶管顶进设备(11)顶进,在位于首节混凝土管道(5)前端的工作井(1)侧墙上挖掘一个深30~50厘米、断面形状与首节混凝土管道(5)相同的坑道,坑道与钻杆同心设置,通过顶管顶进设备(11)将首节混凝土管道(5)顶进坑道;
h.混凝土管道(5)内土方开挖:驱动首节混凝土管道(5)内安装的铰刀(51)转动,配合顶管顶进设备(11)将首节混凝土管道(5)持续顶进,并且首节混凝土管内高压水枪(52)朝向铰刀(51)喷水,此时钻杆在钻杆顶进设备和驱动电机(23)的配合下向远离工作井(1)的方向移动,混凝土管道(5)和钻杆的移动速率相同;
i.混凝土管道(5)贯穿接收井(2):首节混凝土管道(5)顶进后再在顶管导轨(13)上放置下一节混凝土管道(5),并重复顶进管道和退出...
【专利技术属性】
技术研发人员:曾建锋,
申请(专利权)人:广东凯厦建设工程有限公司,
类型:发明
国别省市:广东;44