The invention relates to a design technology of uplift bearing capacity of shallow buried short pile foundation in transmission line construction engineering, a design method of uplift bearing capacity of short pile foundation of transmission line. According to the soil mechanics and the principle of soil shear strength index, the side friction of pile is established, which changes linearly along the pile buried depth, the standard value of friction around pile is calculated according to the standard value of soil shear strength index, and the standard value of soil is introduced Based on the theory of probability, the design model of uplift bearing capacity of short pile foundation is established. Finally, according to the shear strength index of soil under different geological conditions, the curve of uplift bearing capacity of short pile under different pile diameter and pile length is drawn, and the design parameters of short pile foundation are obtained. The invention has the advantages that: according to the actual pile foundation stress mechanism, the calculation error caused by a constant friction resistance is avoided, the design error is effectively reduced, the accuracy is improved, and the working efficiency is greatly improved.
【技术实现步骤摘要】
一种输电线路短桩基础上拔承载力设计方法
本专利技术涉及一种输电线路施工过程中浅埋短桩基础抗拔承载力的设计技术,一种输电线路短桩基础上拔承载力设计方法,其适用于通过对桩埋深小于5倍桩径的短桩上拔承载力分析设计短桩基础。
技术介绍
短桩是指桩埋深小于5倍桩径的桩基。架空输电线路上人工挖孔桩基础受到人力的限制,一般情况下埋深较浅,特别是对于覆盖层较薄的丘陵及山地地区;而考虑输电线路上桩基础的重要性,短桩最重要的设计包括下压承载力和上拔承载力(或称“抗拔承载力”)的设计。目前,电力行业规范《架空输电线路基础设计技术规程》(DL/T5219-2014)中未出现关于短桩抗拔的设计说明,而特高压线路工程设计原则中提及:为保证桩侧摩阻力的发挥,桩长应大于5倍桩径,从而避免形成短桩的破坏机理。当前对于短桩基础的上拔承载力Tu设计是采用现行国家行业规范《建筑桩基技术规范》(JGJ94-2008)推荐的方法:其中:qsik为桩侧极限摩阻力标准,与桩下压稳定取值相同;ui为桩周长;λi为抗拔系数,0.5-0.8之间取值;Gp为桩身自重;K为安全系数,取2.0。然而上述方法存在以下不足之处:1)所述方法未考虑输电线路工程设计中桩埋深与桩径比值的影响,参照附图1,qsik为仅与地质相关的极限摩阻力,实际上对于桩埋深小于5倍桩径的短桩,桩侧摩阻力沿埋深成线性变化,很难达到极限摩阻力,这将会引起短桩的上拔承载力计算误差,使设计只具经验性而无法符合输电线路工程中短桩的受力机理,导致设计误差大,精确度不足。2)所述方法中的安全系数K与下压安全系数取值相同,且为定值2.0。当短桩受压时属于端承 ...
【技术保护点】
1.一种输电线路短桩基础上拔承载力设计方法,其特征在于,包括如下步骤:1)短桩基础所在土体的抗剪强度τf为:τf=σtanφ+c;其中σ即为桩土接触面的正应力,φ为土的内摩擦角,c为土的粘聚力,φ、c值称土的抗剪强度指标;2)桩土接触面的正应力σ为竖向自重应力乘以侧压力系数:σ=γhK0;γ为土的重度,h为计算点至地表深度,K0为静止土压力系数,K0=1‑sinφ;3)结合步骤1)和步骤2)可得τf=γh(1‑sinφ)tanφ+c;4)对桩土抗剪强度τf沿着桩土界面积分即可得桩周上拔承载力:
【技术特征摘要】
1.一种输电线路短桩基础上拔承载力设计方法,其特征在于,包括如下步骤:1)短桩基础所在土体的抗剪强度τf为:τf=σtanφ+c;其中σ即为桩土接触面的正应力,φ为土的内摩擦角,c为土的粘聚力,φ、c值称土的抗剪强度指标;2)桩土接触面的正应力σ为竖向自重应力乘以侧压力系数:σ=γhK0;γ为土的重度,h为计算点至地表深度,K0为静止土压力系数,K0=1-sinφ;3)结合步骤1)和步骤2)可得τf=γh(1-sinφ)tanφ+c;4)对桩土抗剪强度τf沿着桩土界面积分即可得桩...
【专利技术属性】
技术研发人员:吴勤斌,陆洲,陈允清,陈孝湘,张礼朝,吴征,杨巡莺,翁兰溪,叶琦棽,吴培贵,李宏进,池金明,林晗,
申请(专利权)人:中国电建集团福建省电力勘测设计院有限公司,
类型:发明
国别省市:福建,35