The invention discloses a construction method for elastic floor of stage steel structure base course, which comprises the following steps: (1) setting-out positioning; (2) installing angle codes; (3) welding skeleton and adjustment and inspection; (4) construction of large core board base course; (5) sticking elastic board and adjusting cracks; (6) welding of cracks. When fixing the skeleton, the bolts used in this method penetrate into the ground 60 mm; the space between the keels is 300*450, so it has enough support and tension, and the quality is reliable; in safety, this method only uses small machinery, and does not require large safety investment.
【技术实现步骤摘要】
舞台钢结构基层弹性地板施工工法
本专利技术涉及一种舞台钢结构基层弹性地板施工工法,属于建筑施工
技术介绍
学术报告厅是一个集研讨、大型会议、活动于一体的多功能厅,其中涉及到新型的钢结构舞台的施工,传统施工工艺具有施工工期长、工序复杂等缺点,并且由于本身的重量较大,大大增加了建筑的荷载。
技术实现思路
本专利技术所要解决的技术问题是:提供一种舞台钢结构基层弹性地板施工工法。为解决上述技术问题,本专利技术采用的技术方案是:舞台钢结构基层弹性地板施工工法,包括下列步骤:(1)放线定位;(2)安装角码;(3)焊接骨架及调整、检查;(4)大芯板基层施工;(5)粘贴弹性板并调整缝隙;(6)缝隙焊接。进一步的,步骤(1)放线定位:根据结构的基准点,用激光仪在距墙面450mm处设置控制线。(3)焊接骨架及调整、检查:固定龙骨,地面打孔用螺栓固定,焊接竖向龙骨,上层龙骨间距为300﹡450。(4)大芯板基层施工:安装大芯板基层,用燕尾丝固定于骨架上;(5)粘贴弹性板并调整缝隙:在弹性地板到达现场后,检验有无变形、损坏;核对尺寸并预拼无误,方可粘贴。(6)缝隙焊接:安装完成后,检查表面平整度并调整缝宽一致,待稳定后进行焊缝处理。所有龙骨安装,加工前必须进行防锈处理,加工后对断面也要进行防锈处理;不同种类、规格的材料,分别堆放,严禁相互堆叠;安装龙骨前,应明确水平线。质量标准如下:项目允许偏差(㎜)缺陷类型三级未焊满(指不足设计要求)≤0.2+0.04t,且≤0.2根部收缩≤0.2+0.04t,且≤0.2咬边≤0.1t且≤1.0,长度不限弧坑裂纹允许存在个别长度≤5.0的 ...
【技术保护点】
1.舞台钢结构基层弹性地板施工工法,其特征在于,包括下列步骤:(1)放线定位:根据结构的基准点,用激光仪在距墙面450mm处设置控制线;(2)安装角码;(3)焊接骨架及调整、检查:固定龙骨,地面打孔用螺栓固定,焊接竖向龙骨,上层龙骨间距为300*450;(4)大芯板基层施工:安装大芯板基层,用燕尾丝固定于骨架上;(5)粘贴弹性板并调整缝隙:在弹性地板到达现场后,检验有无变形、损坏;核对尺寸并预拼无误,方可粘贴;(6)缝隙焊接:安装完成后,检查表面平整度并调整缝宽一致,待稳定后进行焊缝处理;所有龙骨安装,加工前必须进行防锈处理,加工后对断面也要进行防锈处理;不同种类、规格的材料,分别堆放,严禁相互堆叠;安装龙骨前,应明确水平线。质量标准如下:
【技术特征摘要】
1.舞台钢结构基层弹性地板施工工法,其特征在于,包括下列步骤:(1)放线定位:根据结构的基准点,用激光仪在距墙面450mm处设置控制线;(2)安装角码;(3)焊接骨架及调整、检查:固定龙骨,地面打孔用螺栓固定,焊接竖向龙骨,上层龙骨间距为300*450;(4)大芯板基层施工:安装大芯板基层,用燕尾丝固定于骨架上;(5)粘贴...
【专利技术属性】
技术研发人员:李尊强,迟庆娟,
申请(专利权)人:青岛华联装饰工程有限公司,
类型:发明
国别省市:山东,37