The invention belongs to the field of high-rise construction, and specifically relates to a construction method of high-altitude steel structure corridor, which includes the following steps: erecting the assembled frame on the plane under the orthographic projection of the corridor position and fixing it with a zipper; assembling the lower truss of the corridor on the frame and removing the zipper after assembling; laying the steel plate on the plane of the lower layer of the corridor and erecting the temporary support on the steel plate vertically. Supporting pole group, which splices the corridor upper truss on the temporary support pole group, removes the steel plate and temporary support pole group after assembling, installs lifting platform on the top of the main building on both sides, installs steel strand lifter, lifts the lower truss and the upper truss to the installation position on the upper part of the main building, installs the construction to the corresponding position after unloading, installs slidable curtain wall construction on the lower truss. Moving hanging basket; the curtain wall construction of lower truss is carried out on the hanging basket, and the hanging basket is removed after the construction is completed; the curtain wall construction of the corridor is completed. This method greatly improves the operation efficiency and construction accuracy, and saves the cost.
【技术实现步骤摘要】
一种高空钢结构连廊施工方法
本专利技术属于建筑高工施工领域,具体涉及一种高空钢结构连廊施工方法。
技术介绍
本公司负责承包建设的主楼钢结构连廊位于标高111.50-123.90m,跨度32.6m,宽度17.6m。由上下两层钢桁架体系构成,分别位于主楼26-28层之间,钢桁架总重量约460T。钢桁架与两侧的两座主楼相应楼层的型钢混凝土结构连接,每层桁架由三榀主桁架及空间支撑体系组成。现有大型钢结构吊装工艺多以单层组装、吊装就位为主,双层乃至多层钢结构的现场组装、吊装就位,经查询(连廊同步串连提升)在国内外尚无先例,(在高空大跨度空间结构施工领域)难寻可借鉴的经验。其拼装工艺、提升单元的成型、深化设计、整体提升控制、就位卸荷、施工监测等方面都需要进行详细的策划研究。钢结构连廊的制作加工、拼装、整体吊装就位等过程主要存在以下重点、难点:(1)钢连廊位于110m至123.9m的高空,跨度32m,高度高、跨度大,整体施工方案难度高;桁架重量大,位于高空,无法在高空拼装。(2)本次施工中的连廊由上下双层空间桁架体系构成,提升平台系统设计在机房层顶部,是提升期间最重要的受力构件 ...
【技术保护点】
1.一种高空钢结构连廊施工方法,其特征在于,包括如下步骤:S1)在连廊位置正投影下方的平面搭建好拼装用的胎架(3)并用拉锁(4)固定;S2)在胎架(3)上拼装连廊的下层桁架(1),拼装完成后拆除拉锁(4);S3)在连廊下层的平面铺设钢板,在钢板上竖直设置临时支撑杆组,在临时支撑杆组上拼接连廊上层桁架(2),拼装完成后拆掉钢板和临时支撑杆组;S4)在两侧主楼顶部安装提升平台,配置钢绞线提升器(11);S5)将下层桁架(1)和上层桁架(2)提升到主楼上部的安装工位,分别卸荷后安装施工到相应位置;S6)在下层桁架(1)上安装用于幕墙施工的可滑动吊篮(5);S7)在吊篮(5)上进行 ...
【技术特征摘要】
1.一种高空钢结构连廊施工方法,其特征在于,包括如下步骤:S1)在连廊位置正投影下方的平面搭建好拼装用的胎架(3)并用拉锁(4)固定;S2)在胎架(3)上拼装连廊的下层桁架(1),拼装完成后拆除拉锁(4);S3)在连廊下层的平面铺设钢板,在钢板上竖直设置临时支撑杆组,在临时支撑杆组上拼接连廊上层桁架(2),拼装完成后拆掉钢板和临时支撑杆组;S4)在两侧主楼顶部安装提升平台,配置钢绞线提升器(11);S5)将下层桁架(1)和上层桁架(2)提升到主楼上部的安装工位,分别卸荷后安装施工到相应位置;S6)在下层桁架(1)上安装用于幕墙施工的可滑动吊篮(5);S7)在吊篮(5)上进行下层桁架(1)的幕墙施工,施工完毕后拆除吊篮(5);S8)完成连廊的幕墙施工。2.根据权利要求1所述高空钢结构连廊施工方法,其特征在于:上述步骤S5)中,将下层桁架(1)和上层桁架(2)的安装施工方法为:S5.1)将提升器(11)的钢绞线连接上层桁架(2)并向上提升2~3.5m;S5.2)下层桁架(1)与上层桁架(2)的用若干组刚性的连杆(9)串联;S5.3)提升器(11)将串联好的下层桁架(1)和上层桁架(2)一同继续向上提升100m,静置至少24小时;检查连杆(9)各处的节点以及下层桁架(1)、上层桁架(2)的拼装节点,若有节点失效现象,降到拼装平面修正,若全部节点均正常则执行下一步骤;S5.4)提升器(11)继续向上提升直到下层桁架(1)的安装工位处,将下层桁架(1)与主楼连接就位后卸荷;拆除连杆(9),提升器(11)继续向上提升,直到上层桁架(2)的安装工位处,将上层桁架(2)与主楼连接就位后卸荷。3.根据权利要求2所述高空钢结构连廊施工方法,其特征在于:上述步骤S5.2)中,每个下层桁架(1)的顶梁(6)两端与对应的上层桁架(2)的底梁(7)两端之间均用连杆(9)铰接,每个所述下层桁架(1)的顶梁(6)两端与对应的上层桁架(2)的底梁(7)两端之间还设有软连钢绞线(10)。4.根据权利要求2所述高空钢结构连廊施工方法,其特征在于,上述步骤S5.4)中,所述下层桁架(1)安装方法为:当下层桁架(1)提升到距离安装工位90~120mm位置时,逐步降低提升速度直至到下层桁架(1)的安装工位,提升器(11)锁死暂停提升,安装完成后下层桁架(1)的负载全部由主楼承受;上层桁架(2)的安装方法为:将上层桁架(2)提升至安装工位,提升器(11)锁死暂停提升,安装完成后上层...
【专利技术属性】
技术研发人员:张泉,文士仆,梁伟,
申请(专利权)人:济南四建集团有限责任公司,
类型:发明
国别省市:山东,37