The invention discloses an installation and construction method for the arch ring of a special-shaped tied arch bridge, which adopts the method of fewer brackets for installing temporary bracket steel pipe piles only at the joints of the members, including the preparation process before construction, the construction process of temporary brackets in water, the hoisting process of steel arch ribs, the installation process of steel arch rib closure section, the welding process of bridge position, the installation process of arch rib suspenders and the proximity of arch ribs. When the support is dismantled, the prefabricated assembly method is adopted in the construction, which reduces the occupancy and pollution of the water area under the bridge by floating crane; multi-process parallel operation speeds up the construction progress and shortens the construction period; only temporary support is installed at the ring joint of the large section arch rib joint, which occupies a small position, facilitates navigation under the bridge in the construction state, and reduces navigation under the construction bridge and across the lake. The influence of the surrounding social environment; the construction process effectively reduces the error between the steel arch rib segments, to achieve accurate positioning welding, to ensure the linear manufacturing accuracy of the special-shaped arch rib.
【技术实现步骤摘要】
一种异形系杆拱桥拱圈的安装施工方法
本专利技术属于桥梁建筑
,特别是涉及一种异形系杆拱桥拱圈的安装施工方法。
技术介绍
一般的系杆拱桥其吊杆多为竖向布置,荷载通过吊杆传递给主拱,得出合理拱轴线均为对称的曲线。若将吊杆按一个斜率斜向布置,导出的合理拱轴线便是偏态的曲线,由此得出一种新型桥型结构——异型拱桥。异形拱桥的桥跨结构由主拱圈、斜吊杆、系梁及桥面组成其拱压力线是偏态抛物线结构特性仍属于系杆拱形式。不论异型拱和正拱,在荷载的作用下,其压力线与拱轴线一致,都是合理结构形式。对于异形拱桥的施工难点主要表现为:⒈钢拱肋线形控制精度高:在现场拼装时需要同时保证成拱肋平曲线线形和竖曲线线形,还要求空间线形,按线形制造精度要求高,控制难度大;⒉钢拱肋安装在大型湖内施工,现场场地有限,拱肋工料存放、施工受限;⒊在一些水上施工时必须采用对通航影响较小的施工方案;⒋拱桥整体跨度较大,设计、施工难度大。
技术实现思路
针对上述技术问题,本专利技术提供了一种异形系杆拱桥拱圈的安装施工方法。本专利技术采用以下技术方案:一种异形系杆拱桥拱圈的安装施工方法,所述异形系杆拱桥包括所由下至上逐渐向外倾斜的钢拱肋、异形桥面板与桥梁墩柱,所述钢拱肋通过多条沿桥纵向间距分布的吊杆与所述异形桥面板固定连接,所述钢拱肋包括一个中拱肋与两个位于所述中拱肋两端的边拱肋,所述边拱肋分为7个吊装节段,所述中拱肋分为9个吊装节段,所述中拱肋与所述边拱肋分别位于所述异形桥面板的两侧;所述施工方法采用仅在杆件接点处设置临时支架钢管桩的少支架法制作安装,包括以下步骤:(1)施工前准备流程:完成临时支撑架以及钢 ...
【技术保护点】
1.一种异形系杆拱桥拱圈的安装施工方法,其特征在于,所述异形系杆拱桥包括所由下至上逐渐向外倾斜的钢拱肋、异形桥面板(10)与桥梁墩柱(40),所述钢拱肋通过多条沿桥纵向间距分布的吊杆(20)与所述异形桥面板(10)固定连接,所述钢拱肋包括一个中拱肋(31)与两个位于所述中拱肋(31)两端的边拱肋(32),所述边拱肋(32)分为7个吊装节段,所述中拱肋(31)分为9个吊装节段,所述中拱肋(31)与所述边拱肋(32)分别位于所述异形桥面板(10)的两侧;所述施工方法采用仅在杆件接点处设置临时支架钢管桩的少支架法制作安装,包括以下步骤:(1)施工前准备流程:完成临时支撑架以及钢拱肋的预制组装,并按要求完成上下爬梯、焊接平台的准备;(2)水中临时支架施工:用全站仪将桩位测放定位;钢管桩设置在所述拱肋相邻的吊装节段接点处的垂直方向上;(3)钢拱肋吊装流程:先对所述边拱肋(32)进行吊装固定,再对所述中拱肋(31)进行吊装固定;利用浮吊船将预制组装好的钢拱肋节段吊装就位,之后人工拉绳牵引至安装位置上,利用码板完成粗定位,之后采用千斤顶和手拉葫芦进行纵横向调整,采用千斤顶进行竖向调整,完成精确匹配定 ...
【技术特征摘要】
1.一种异形系杆拱桥拱圈的安装施工方法,其特征在于,所述异形系杆拱桥包括所由下至上逐渐向外倾斜的钢拱肋、异形桥面板(10)与桥梁墩柱(40),所述钢拱肋通过多条沿桥纵向间距分布的吊杆(20)与所述异形桥面板(10)固定连接,所述钢拱肋包括一个中拱肋(31)与两个位于所述中拱肋(31)两端的边拱肋(32),所述边拱肋(32)分为7个吊装节段,所述中拱肋(31)分为9个吊装节段,所述中拱肋(31)与所述边拱肋(32)分别位于所述异形桥面板(10)的两侧;所述施工方法采用仅在杆件接点处设置临时支架钢管桩的少支架法制作安装,包括以下步骤:(1)施工前准备流程:完成临时支撑架以及钢拱肋的预制组装,并按要求完成上下爬梯、焊接平台的准备;(2)水中临时支架施工:用全站仪将桩位测放定位;钢管桩设置在所述拱肋相邻的吊装节段接点处的垂直方向上;(3)钢拱肋吊装流程:先对所述边拱肋(32)进行吊装固定,再对所述中拱肋(31)进行吊装固定;利用浮吊船将预制组装好的钢拱肋节段吊装就位,之后人工拉绳牵引至安装位置上,利用码板完成粗定位,之后采用千斤顶和手拉葫芦进行纵横向调整,采用千斤顶进行竖向调整,完成精确匹配定位;(4)钢拱肋合拢段安装流程:采用浮吊吊装,辅以人工手拉葫芦进行调整,完成定位固定后,将合拢段与相邻边节段进行码板焊接;(5)完成桥位焊接后,分批安装边拱肋吊杆、中拱肋吊杆,并在拱肋焊接完成报检合格后,进行拱肋支架拆除,再逐步进行钢管桩临时支架的拆除。2.根据权利要求1所述的一种异形系杆拱桥拱圈的安装施工方法,其特征在于,所述步骤(2)水中临时支架施工方法具体如下:1)放线定位:钢管桩设置在所述拱肋相邻的吊装节段接点处的垂直方向上,并根据工地现场导线控制点,用全站仪将桩位测放定位;2)轴线复核:施工前,对已放线定位的各轴线及桩位置重新复核一次;3)采用振动桩锤对钢管桩进行打桩,第一节桩沉至桩顶高出水面60~80cm时,停止振动,进行接桩,在钢管桩对接接头处要增加加劲板,加劲板在与上下节桩要焊接牢固,待加劲板焊接完毕之后,应冷却5分钟后方可沉桩;在所述钢管桩支架顶端设置钢拱肋仿形定位架。3.根据权利要求2所述的一种异形系杆拱桥拱圈的安装施工方法,其特征在于,步骤(2)中所述加劲板宽度为300mm,厚14mm。4.根据权利要求1所述的一种异形系杆拱桥拱圈的安装施工方法,其特征在于,所述步骤(3)钢拱肋吊装流程具体如下:1)粗定位:A、根据拱肋节段就位姿态,配备调节好钢丝绳长度,再采用浮吊实施刚拱肋节段吊装,钢拱肋节段离开支承面30cm后,确认块体姿态合理、吊装安全;B、将钢拱肋节段提升至一定高度稳定后,浮吊慢慢旋转至安装位置上方,将钢拱肋节段缓慢下放,人工拉绳牵引至支架顶端标高调节小柱上方,利用钢拱肋仿形定位架进行辅助定位;C、根据限位侧向挡板或前一节段块体底部、侧向码板作为参考导向,配合测控点测量,进行接下来钢拱肋节段的就位,对测控点进行复测,满足粗定位;2...
【专利技术属性】
技术研发人员:杨枫,余晓耀,高仙凤,丁中才,
申请(专利权)人:合肥市公路桥梁工程有限责任公司,
类型:发明
国别省市:安徽,34