The invention provides a method for connecting a new sewage interception sub-branch pipe with an existing sewage pipe network, which comprises the following steps: (1) geophysical verification of the existing sewage pipe network to determine the structure of the existing sewage pipe network; (2) construction of a working well and a receiving well, which are constructed by reverse construction method; (3) construction of a new sewage interception sub-branch pipe by reverse construction method; (3) construction of a new sewage interception sub-branch pipe by a geophysical examination of the existing sewage pipe network The working well is pipe jacked to the receiving well, and then connected with the existing sewage pipe network; (4) After the connection between the new sewage interception sub-branch pipe and the existing sewage pipe network is completed, the existing sewage pipe network is diverted and the incision is made after the diversion is completed to ensure the existing sewage pipe network and the new sewage interception sub-branch. Guan Liantong. The connecting method provided by the invention can not only ensure the normal water supply of the existing sewage pipe network, but also reduce the impact on the surrounding environment. Overall, the process is simple, the construction efficiency is high, and the construction cost is low. It is of great significance for the connection of the newly built sewage interception secondary branch pipe and the existing sewage pipe network.
【技术实现步骤摘要】
新建截污次支管与既有污水管网接驳工法
本专利技术属于污水管接驳领域,尤其涉及一种新建截污次支管与既有污水管网接驳工法。
技术介绍
目前国内大部分城市地下污水管网在建工程均为截污次支管网建设,需与前期城市已建既有污水管网连接,并将污水集中至污水处理厂,处理达标后排放或重复利用。常规接驳方式均为沉井接驳工艺,但传统接驳工艺具有以下缺点:(1)普通顺序沉井过程中无法保护既有管道,容易对周围建筑和管线造成破坏;(2)施工时需搭建工作平台,施工进度慢、施工时间长、安全隐患高;(3)污水导排工程量巨大,施工成本高;(4)施工噪音大、风尘多,对周围居民生活影响较大。因此,亟需一种工序简单、工效高、安全隐患小、对周围居民生活干扰小的接驳工法。
技术实现思路
本专利技术的目的在于提供一种工序简单、工效高、安全隐患小的新建截污次支管与既有污水管网的接驳工法。为实现上述目的,本专利技术提供一种新建截污次支管与既有污水管网接驳工法,包括以下步骤:(1)对既有污水管网进行物探核实,确定既有污水管网的结构;(2)对工作井与接收井进行施工,所述接收井采用逆作法施工,所述工作井用于顶管新建截污次支管至所述接收井,所述接收井用于接收与所述既有污水管网接驳的所述新建截污次支管;(3)将所述新建截污次支管由所述工作井顶管至所述接收井,随后与所述既有污水管网进行接驳;(4)在所述新建截污次支管与所述既有污水管网接驳完成后,将所述既有污水管网进行导流,导流完成后进行切口,确保所述既有污水管网与所述新建截污次支管连通。具体地,采用金刚石绳锯与金刚石水钻的配合以工字钢临时支顶条件下对接驳处进行切口,相比较 ...
【技术保护点】
1.一种新建截污次支管与既有污水管网接驳工法,其特征在于,包括以下步骤:(1)对既有污水管网进行物探核实,确定所述既有污水管网的结构;(2)对工作井与接收井进行施工,所述接收井采用逆作法施工,所述工作井用于顶管新建截污次支管至所述接收井,所述接收井用于接收与所述既有污水管网接驳的所述新建截污次支管;(3)将所述新建截污次支管由所述工作井顶管至所述接收井,随后与所述既有污水管网进行接驳;(4)在所述新建截污次支管与所述既有污水管网接驳完成后,将所述既有污水管网进行导流,导流完成后进行切口,确保所述既有污水管网与所述新建截污次支管连通。
【技术特征摘要】
1.一种新建截污次支管与既有污水管网接驳工法,其特征在于,包括以下步骤:(1)对既有污水管网进行物探核实,确定所述既有污水管网的结构;(2)对工作井与接收井进行施工,所述接收井采用逆作法施工,所述工作井用于顶管新建截污次支管至所述接收井,所述接收井用于接收与所述既有污水管网接驳的所述新建截污次支管;(3)将所述新建截污次支管由所述工作井顶管至所述接收井,随后与所述既有污水管网进行接驳;(4)在所述新建截污次支管与所述既有污水管网接驳完成后,将所述既有污水管网进行导流,导流完成后进行切口,确保所述既有污水管网与所述新建截污次支管连通。2.如权利要求1所述的接驳工法,其中,步骤(1)与步骤(2)之间还包括:(11)分析核查所述既有污水管网的地质状况,了解地下管线的详细情况;(12)测量放线,确保工作井与接收井的位置;(13)基坑施工,做好基坑安全围护。3.如权利要求2所述的接驳工法,其中,步骤(13)中,所述基坑四周设置有排水沟。4.如权利要求1所述的接驳工法,其中,所述接收井的护壁呈梯形结构。5.如权利要求1所述的接驳工法,其中,步骤(2)中,所述接收井施工方法包括:(2a)进行高压旋喷桩施工,形成所述接收井外壁的止水墙;(2b)在所述止水墙内部开挖第一节土坑,在所述第一节土坑内壁设置第一节护壁;(2c)重复步骤(2b),在所述止水墙内部开挖第二节土坑,在所述第二节土坑内壁设置第二节护壁,如此重复,直至完成最后一节护壁;(2d)所有护壁施工完成后,进行封底,形成所述接收井。6.如权利要求5所述的接驳工法,其中,所述护壁的施工步骤包括:在各所述土坑内...
【专利技术属性】
技术研发人员:韩龙伟,文杰,田锦虎,刘正刚,张彤炜,周书东,
申请(专利权)人:中国水利水电第七工程局有限公司,
类型:发明
国别省市:四川,51