The invention provides an earthwork excavation method for long and narrow deep foundation pit in rainy weather. Its characteristics include excavation at the bottom of the pit once to form a slope, construction of a transport ramp for dump trucks, replacement of the transport ramp with schist or weathered rock, installation of drainage open ditches, slope catchment wells, closure sewers and steel. Structural support, installation and erection of rainproof roof, earthwork of foundation pit is filled by excavator, transportation of dump truck to and fro ramp is carried out, and inconvenient areas of dump truck in foundation pit are transported by bulldozer pushing and filling of small excavator; the technical scheme provided by the invention can effectively solve the problem of rainy weather. The problem of grouting in foundation pit under weather can be solved by slope solidification and drainage treatment to reduce sand slope and silt pit bottom. In addition, a rainproof roof is set up to prevent rainwater from the top tribe of foundation pit, to protect slope stability, to maximize the dryness of the bottom of deep foundation pit, and to avoid the influence of rainwater on the construction progress of deep foundation pit.
【技术实现步骤摘要】
一种多雨天气下狭长深基坑土方开挖方法
本专利技术属于建筑施工
,具体地,涉及一种多雨天气下狭长深基坑土方开挖方法。
技术介绍
目前,为应对建筑高层化发展,狭长深基坑土方开挖技术日趋成熟,许多竣工的项目施工方案可供借鉴,但对于雨季地区或多雨天气下的狭长深基坑土方开挖技术并无现有技术可供参考,施工单位往往避开雨季施工或在多雨天气时暂停施工,这大大影响了工程计划及竣工时效,因此急需一种行之有效的能够解决上述问题的的方案。
技术实现思路
专利技术目的:为了克服现有技术的不足,本专利技术的目的是提供一种多雨天气下不停工、不影响工期的应对狭长深基坑土方开挖的施工方法。技术方案:本专利技术提供了一种多雨天气下狭长深基坑土方开挖方法,其特征在于,包括下列施工步骤:1)利用挖掘机将基坑土方从一侧一次见底方式开挖形成边坡,开挖同时对边坡进行支护,并对边坡侧壁及坡面喷浆硬化处理,随后在边坡上修建一条供自卸汽车通行的运输坡道,所述运输坡道采用片岩或风化岩进行换填;2)在运输坡道两侧设置排水明沟,并在排水明沟上每间隔一定距离设置坡道集水井,所述坡道集水井内配备通过水管向基坑外排水的坡道潜水泵;3)在运输坡道底部挖设一条连通两道排水明沟的截流阴沟,截流阴沟内配备通过水管向基坑外排水的阴沟潜水泵;4)在进行第3)步骤同时,进行基坑钢结构支撑安装,所述钢支撑顶部露出地表,并在基坑两侧钢支撑间搭设防雨棚顶,随着基坑开挖推进,防雨棚顶同步跟进搭建;5)基坑土方采用挖掘机填装,自卸汽车往返运输坡道输送的方式进行,基坑内自卸汽车不便通行的区域由推土机推送至运输车到附近,再由小型挖掘机填装至自卸 ...
【技术保护点】
1.一种多雨天气下狭长深基坑土方开挖方法,其特征在于,包括下列施工步骤:1)利用挖掘机将基坑土方从一侧一次见底方式开挖形成边坡,开挖同时对边坡进行支护,并对边坡侧壁及坡面喷浆硬化处理,随后在边坡上修建一条供自卸汽车通行的运输坡道,所述运输坡道采用片岩或风化岩进行换填;2)在运输坡道两侧设置排水明沟,并在排水明沟上每间隔一定距离设置坡道集水井,所述坡道集水井内配备通过水管向基坑外排水的坡道潜水泵;3)在运输坡道底部挖设一条连通两道排水明沟的截流阴沟,截流阴沟内配备通过水管向基坑外排水的阴沟潜水泵;4)在进行第3)步骤同时,进行基坑钢结构支撑安装,所述钢结构支撑顶部露出地表,并在基坑两侧钢结构支撑间搭设防雨棚顶,随着基坑开挖推进,防雨棚顶同步跟进搭建;5)基坑土方采用挖掘机填装,自卸汽车往返运输坡道输送的方式进行,基坑内自卸汽车不便通行的区域由推土机推送至运输车到附近,再由小型挖掘机填装至自卸汽车的方式进行。
【技术特征摘要】
1.一种多雨天气下狭长深基坑土方开挖方法,其特征在于,包括下列施工步骤:1)利用挖掘机将基坑土方从一侧一次见底方式开挖形成边坡,开挖同时对边坡进行支护,并对边坡侧壁及坡面喷浆硬化处理,随后在边坡上修建一条供自卸汽车通行的运输坡道,所述运输坡道采用片岩或风化岩进行换填;2)在运输坡道两侧设置排水明沟,并在排水明沟上每间隔一定距离设置坡道集水井,所述坡道集水井内配备通过水管向基坑外排水的坡道潜水泵;3)在运输坡道底部挖设一条连通两道排水明沟的截流阴沟,截流阴沟内配备通过水管向基坑外排水的阴沟潜水泵;4)在进行第3)步骤同时,进行基坑钢结构支撑安装,所述钢结构支撑顶部露出地表,并在基坑两侧钢结构支撑间搭设防雨棚顶,随着基坑开挖推进,防雨棚顶同步跟进搭建;5)基坑土方采用挖掘机填装,自卸汽车往返运输坡道输送的方式进行,基坑内自卸汽车不便通行的区域由推土机推送至运输车到附近,再由小型挖掘机填装至自卸汽车的方式进行。2.根据权利要求1所述的一种多雨天气下狭长深基坑土方开挖...
【专利技术属性】
技术研发人员:周伟恒,王李珍,沈建军,夏正高,
申请(专利权)人:江苏东珠景观股份有限公司,
类型:发明
国别省市:江苏,32