The invention discloses a construction method for a partial deep foundation pit. The main points of its technical scheme include the following construction steps: S1, use construction machinery to change the soil of the enlarged area in the area of the local deep foundation pit and its surrounding and bottom; S2, the dry cement, the use of construction machinery to stir and stir the dry cement with the soil; S3, dry cement and soil solidify into a whole water. Soil structure; S4; excavation of deep foundation pit in cement soil structure. The invention achieves the water stopping effect of local deep foundation pit excavation by simple steps, and has the advantages of low cost and high efficiency compared with dewatering well technology.
【技术实现步骤摘要】
一种局部深基坑的施工方法
本专利技术涉及建筑基坑的开挖,特别涉及一种局部深基坑的施工方法。
技术介绍
如图1所示,目前,在建筑物基坑1的开挖过程中,均会采取管井降水等方法将地下水水位2降至建筑物底板3以下0.5m,以保证筑物基坑1开挖和建筑结构施工过程中的无水环境。但是由于电梯井等结构的特殊设计,电梯井结构的底部标高比建筑物底板3标高更低,因此会出现局部深基坑4。现有技术中,电梯井局部深基坑4一般采用以下施工方法:1、井点降水施工。在局部基坑开挖前,在其四周插入一定数量的滤水管(井),利用抽水设备抽水,使局部水位降低。此施工方法为井点降水,存在以下缺点:一是该方法需要用到专门的降水井施工设备,造价高;二是降水井点需要钻孔、下管、布网、抽水等多个施工步骤,施工周期长,耽误总工期。三是由于电梯井从基坑开挖到结构施工完成至少也要一个多月,而在些期间降水不能间断,设备使用周期长,抽水量大。四是如果局部深基坑4地层为砂卵石层时,抽水量特别大,抽水效果很难保证。2、沉井施工。沉井是一个无底无盖的混凝土井筒,一般由刃脚、井壁、隔墙等部分组成。在沉井内挖土使其下沉,达到设计标高后 ...
【技术保护点】
1.一种局部深基坑的施工方法,其特征在于:包括以下施工步骤:S1、用施工机械对局部深基坑(4)开挖范围内及其四周和底部的扩大区(6)土体进行翻动;S2、加入干水泥,利用施工机械继续翻搅,使干水泥与土体搅拌充分;S3、干水泥和土体凝固为一块整体水泥土结构(5);S4、在水泥土结构(5)中开挖局部深基坑(4)。
【技术特征摘要】
1.一种局部深基坑的施工方法,其特征在于:包括以下施工步骤:S1、用施工机械对局部深基坑(4)开挖范围内及其四周和底部的扩大区(6)土体进行翻动;S2、加入干水泥,利用施工机械继续翻搅,使干水泥与土体搅拌充分;S3、干水泥和土体凝固为一块整体水泥土结构(5);S4、在水泥土结构(5)中开挖局部深基坑(4)。2.根据权利要求1所述的一种局部深基坑的施工方法,其特征在于:加入的干水泥的重量是被翻动的土体的重量的20%~25%。3.根据权利要求1所述的一种局部深基坑的施工方法,其特征在于:局部深基坑(4)底部扩大区(61)土体的厚度是局部深基坑(4)深度的1/2。4.根据权利要求1所述的一种局部深基坑的施工方法,其特征在于:所述施工...
【专利技术属性】
技术研发人员:王哓磊,仲鑫,赵小勇,
申请(专利权)人:北京城建华夏基础建设工程有限公司,
类型:发明
国别省市:北京,11