The invention provides a replacement method for the coiler roll of an underground coiler, which includes the following steps: the special tooling is hoisted to the unloading trolley, the unloading car is moved into the coiler, the cover plate assembly is opened, and the maintenance personnel carry the tool station on the special tooling, check the reel and grind the work; The reel roll needs to be replaced with the hand hoist on the support body of the special tooling. After closing the baffle module, the reel trolley is pulled out of the coiler; the roll roll is unloaded and the new roll roll is suspended to the unloaded car; then the unloading trolley is pulled into the coiler; and the baffle module is opened again to check. The new coiling rolls are installed on the coiler on the special tooling, and the reeling trolley is pulled out of the coiler after the shutter is closed again; that is, the reel roll replacement work is completed. The replacement method can reduce the workload of construction personnel, ensure the safety of construction personnel, and improve the replacement efficiency.
【技术实现步骤摘要】
一种地下卷取机助卷辊更换方法
本专利技术涉及地下卷取机检修,特别是涉及一种地下卷取机助卷辊更换方法。
技术介绍
热轧薄板带钢生产线在产线末端必须布置地下卷取机,对精轧后的板带进行卷取。地下式卷取机设备结构复杂,上下设备落差较大,临边坑洞较多,特别是助卷辊周围进行检修作业时,交叉作业较多。通常卷取机设计有三组助卷辊,助卷辊均分在卷取机芯轴周围。芯轴上部有斜导板、运输辊道、卷取牌坊等装置,因此,助卷辊在拆装时,倒运比较困难。目前,卷取机助卷辊更换方法为:设备停机后,在卷筒下方搭设脚手架平台,并拉设安全网,封堵孔洞。使用手拉葫芦封锁助卷辊,拆除助卷辊后,使用手拉葫芦配合钢丝绳将助卷辊慢慢倒出卷取机牌坊,使用行车吊走。助卷辊安装过程与拆除过程相反。在助卷辊更换中,所需人力较多,且存在高处临边坠落的风险;另外,更换前需要搭建脚手架平台,以及更换后需要拆卸脚手架平台,劳动强度大,且费时。
技术实现思路
鉴于以上所述现有技术的缺点,本专利技术的目的在于提供一种地下卷取机助卷辊更换方法,用于解决现有技术中存在的上述问题。为实现上述目的及其他相关目的,本专利技术提供一种地下卷取机助卷辊更换方法,包括如下步骤:1)将专用工装吊至卸卷小车上;所述专用工装包括支撑本体和通过合页对称设在所述支撑本体两侧的遮挡板组件;2)关闭所述遮挡板组件,且将所述支撑本体底面与所述卸卷小车可拆卸地相连接在一起;3)将所述卸卷小车驶入卷取机,且位于卷筒下方;4)打开所述遮挡板组件,使得所述遮挡板组件与所述支撑本体顶面位于同一平面,且所述遮挡板组件外端搭接在卷取机边缘;5)检修人员携带工具站在所述专用工装 ...
【技术保护点】
一种地下卷取机助卷辊更换方法,其特征在于,包括如下步骤:1)将专用工装(1)吊至卸卷小车(2)上;所述专用工装(1)包括支撑本体(11)和通过合页对称设在所述支撑本体(11)两侧的遮挡板组件(12);2)关闭所述遮挡板组件(12),且将所述支撑本体(11)底面与所述卸卷小车(2)可拆卸地相连接在一起;3)将所述卸卷小车(2)驶入卷取机,且位于卷筒下方;4)打开所述遮挡板组件(12),使得所述遮挡板组件(12)与所述支撑本体(11)顶面位于同一平面,且所述遮挡板组件(12)外端搭接在卷取机边缘;5)检修人员携带工具站在所述专用工装(1)上,对卷筒进行检查,打磨作业;6)利用手拉葫芦将需要更换的助卷辊放置在所述支撑本体(11)上;7)关闭所述遮挡板组件(12)后,将卸卷小车(2)驶出卷取机;8)利用行车将卸卷小车(2)上的助卷辊吊至指定位置后,再将新的助卷辊吊至所述卸卷小车(2)上;9)确认所述遮挡板组件(12)处于关闭状态,将载有新助卷辊的卸卷小车(2)驶入卷取机,且使得新助卷辊位于卷筒下方;10)再次打开所述遮挡板组件(12),使得所述遮挡板组件(12)与所述支撑本体(11)顶面位于同 ...
【技术特征摘要】
1.一种地下卷取机助卷辊更换方法,其特征在于,包括如下步骤:1)将专用工装(1)吊至卸卷小车(2)上;所述专用工装(1)包括支撑本体(11)和通过合页对称设在所述支撑本体(11)两侧的遮挡板组件(12);2)关闭所述遮挡板组件(12),且将所述支撑本体(11)底面与所述卸卷小车(2)可拆卸地相连接在一起;3)将所述卸卷小车(2)驶入卷取机,且位于卷筒下方;4)打开所述遮挡板组件(12),使得所述遮挡板组件(12)与所述支撑本体(11)顶面位于同一平面,且所述遮挡板组件(12)外端搭接在卷取机边缘;5)检修人员携带工具站在所述专用工装(1)上,对卷筒进行检查,打磨作业;6)利用手拉葫芦将需要更换的助卷辊放置在所述支撑本体(11)上;7)关闭所述遮挡板组件(12)后,将卸卷小车(2)驶出卷取机;8)利用行车将卸卷小车(2)上的助卷辊吊至指定位置后,再将新的助卷辊吊至所述卸卷小车(2)上;9)确认所述遮挡板组件(12)处于关闭状态,将载有新助卷辊的卸卷小车(2)驶入卷取机,且使得新助卷辊位于卷筒下方;10)再次打开所述遮挡板组件(12),使得所述遮挡板组件(12)与所述支撑本体(11)顶面位于同一平面,且...
【专利技术属性】
技术研发人员:高健,李伟光,马玉丛,周晓峰,杨晨筠,
申请(专利权)人:中冶宝钢技术服务有限公司,
类型:发明
国别省市:上海,31