A kind of assembled steel structure node energy consumption, including steel I-COLUMN, two relative flange steel column is respectively connected to the first and second beam steel bolts, steel columns on both sides of web relative bolts are respectively connected with a steel pipe, third steel and fourth steel beam connection in steel tube webs on both sides; in the earthquake when the steel tube is conducive to the development of plastic hinge, and the protection of steel columns of the utility model can not only protect, not by the deformation of the column, but also can make the beam plastic hinge to meet energy requirements.
【技术实现步骤摘要】
一种装配式钢结构耗能节点
本技术涉及一种节点,具体涉及一种装配式钢结构耗能节点。
技术介绍
随着我国经济的快速发展,钢产量已经成为世界第一,使的大量的钢结构建筑问世。并且,我国现在推行装配式建筑,而钢结构又特别适用装配式的工艺,加速了钢结构建筑的发展。但是,在考虑到结构的抗震性能,往往要满足强节点的要求,要做到“强柱弱梁”。而传统的装配式钢结构节点,往往在结构抗震时,由于梁要出现塑性铰,以此来消耗地震的能量,而使的梁柱连接处由于塑性铰的出现使的柱子出现变形,严重的影响其抗震性能。
技术实现思路
:为了克服上述现有技术的不足,本技术的目的在于提供了一种装配式钢结构耗能节点,既能保护柱子不受到变形影响,又能使其梁出现塑性铰满足耗能要求。为了达到上述目的,本技术采用的技术方案是:一种装配式钢结构耗能节点,包括工字钢柱3,工字钢柱3的两个相对的翼缘上分别用螺栓连接第一钢梁2和第二钢梁6,工字钢柱3相对的腹板两侧用螺栓各连接一个钢方管5,第三钢梁4和第四钢梁1连接在腹板两侧钢方管5上。本技术的有益效果是:第三钢梁4和第四钢梁1连接在腹板两侧钢方管5上,在地震作用时,钢方管5有利于有利于塑性铰的开展,并且保护工字钢柱3。附图说明图1为本技术实施例的结构示意图。具体实施方式下面结合附图和实施例对技术作进一步描述。参照图1,一种装配式钢结构耗能节点,包括工字钢柱3,工字钢柱3的两个相对翼缘上分别用螺栓连接第一钢梁2和第二钢梁6,工字钢柱3的相对腹板两侧用螺栓各连接一个钢方管5,第三钢梁4和第四钢梁1连接在腹板两侧钢方管5上,钢方管5有利于塑性铰的开展,这样第三钢梁4和第四钢梁 ...
【技术保护点】
一种装配式钢结构耗能节点,包括工字钢柱(3),其特征在于:工字钢柱(3)的两个相对的翼缘上分别用螺栓连接第一钢梁(2)和第二钢梁(6),工字钢柱(3)相对的腹板两侧用螺栓各连接一个钢方管(5),第三钢梁(4)和第四钢梁(1)连接在腹板两侧钢方管(5)上。
【技术特征摘要】
1.一种装配式钢结构耗能节点,包括工字钢柱(3),其特征在于:工字钢柱(3)的两个相对的翼缘上分别用螺栓连接第一钢梁(2)和第二...