The invention discloses a method for replacing the hydraulic support column, which includes: installing lifting equipment; opening the master control valve to open the control valves of each column except the column to be replaced; connecting the movable column to the lifting equipment to be replaced, removing the movable column and lifting it off; closing the master control valve, removing the pipe fittings and valves after pressure relief, sealing the corresponding pipe and valve ports on the hydraulic support; The fixed base of the column to be replaced is connected with the lifting equipment, and the fixed base is dismantled and lifted; the fixed base of the column to be installed is lifted and fixed with the bottom plate of the hydraulic support; the nozzle and valve opening are sealed and the fittings and valves are installed on the column to be installed; the master control valve is opened, and the control valves of each column including the column to be installed are opened to drive the movable column to be installed. Stretch to the roof of the hydraulic support and fix the moving column with the roof. The invention provides a replacement method for the hydraulic support column, which can quickly dismantle and assemble the hydraulic support column to improve the replacement efficiency and operation safety.
【技术实现步骤摘要】
液压支架立柱的更换方法
本专利技术涉及综采工作面开采设备,更具体地,涉及一种液压支架立柱的更换方法。
技术介绍
液压支架是综采工作面开采设备的重要组成部分,液压支架在巷道超前支护中被广泛采用,具有支护强度高、自动化程度高、作业速度快、安全性高等优点,适用于断面大、围岩破碎、变形严重的巷道以及采高大、机械化程度高、推进速度快的高产工作面。立柱作为超前液压支架的主要承载机构,其性能好坏直接影响支护质量,决定了巷道施工安全和开采效率。立柱受到制作材料、工艺水平、井下作业环境、顶板来压、人工操作等原因影响,可能产生串液、漏液等故障甚至完全损坏,难以提供足够的支撑力,对生产安全产生较大威胁。因此,需要及时更换损坏立柱,以保证超前支架具有足够的支撑力。目前,更换超前支架立柱并没有规范的方法,现场一般根据以往经验进行更换作业。由于缺少统一的作业流程和作业标准,难以保证更换立柱的作业质量,造成作业缓慢,甚至更换失败,影响作业效率;同时,还可能造成人员安全问题,影响作业安全。因此,需要一种液压支架立柱的更换方法,来解决上述问题。
技术实现思路
有鉴于此,本专利技术的目的在于提出一种液压支架立柱的更换方法,快速拆装液压支架的立柱,提高更换效率和作业安全性。基于上述目的本专利技术提供的一种液压支架立柱的更换方法,包括:(1)在巷道内安装用于运输立柱的吊接设备;(2)开启液压支架的总控制阀,开启除待更换立柱之外的各个立柱的控制阀;(3)将所述待更换立柱的移动柱与所述吊装设备连接,从所述液压支架上拆卸所述移动柱,所述吊装设备将所述移动柱吊离所述液压支架;(4)关闭所述液压支架的所述总控 ...
【技术保护点】
1.一种液压支架立柱的更换方法,其特征在于,包括:(1)在巷道内安装用于运输立柱的吊接设备;(2)开启液压支架的总控制阀,开启除待更换立柱之外的各个立柱的控制阀;(3)将所述待更换立柱的移动柱与所述吊装设备连接,从所述液压支架上拆卸所述移动柱,所述吊装设备将所述移动柱吊离所述液压支架;(4)关闭所述液压支架的所述总控制阀,泄压后,拆卸与所述待更换立柱配合使用的管件和阀件,并对所述管件和所述阀件在所述液压支架上相应的管口和阀口密封;(5)在所述待更换立柱的固定底座与所述吊装设备连接,从所述液压支架上拆卸所述固定底座,所述吊装设备将所述固定底座吊离所述液压支架;(6)在所述吊装设备上吊接待安装立柱,并吊至所述液压支架上,将所述待安装立柱的固定底座与所述液压支架的底板固定;(7)将所述液压支架的所述管口和所述阀口解密封,将所述管件和所述阀件安装在所述待安装立柱上;(8)开启所述液压支架的所述总控制阀,开启包括所述待安装立柱在内的各个所述立柱的所述控制阀,驱动所述待安装立柱的移动柱伸长至抵接所述液压支架的顶板,将所述移动柱与顶板固定。
【技术特征摘要】
1.一种液压支架立柱的更换方法,其特征在于,包括:(1)在巷道内安装用于运输立柱的吊接设备;(2)开启液压支架的总控制阀,开启除待更换立柱之外的各个立柱的控制阀;(3)将所述待更换立柱的移动柱与所述吊装设备连接,从所述液压支架上拆卸所述移动柱,所述吊装设备将所述移动柱吊离所述液压支架;(4)关闭所述液压支架的所述总控制阀,泄压后,拆卸与所述待更换立柱配合使用的管件和阀件,并对所述管件和所述阀件在所述液压支架上相应的管口和阀口密封;(5)在所述待更换立柱的固定底座与所述吊装设备连接,从所述液压支架上拆卸所述固定底座,所述吊装设备将所述固定底座吊离所述液压支架;(6)在所述吊装设备上吊接待安装立柱,并吊至所述液压支架上,将所述待安装立柱的固定底座与所述液压支架的底板固定;(7)将所述液压支架的所述管口和所述阀口解密封,将所述管件和所述阀件安装在所述待安装立柱上;(8)开启所述液压支架的所述总控制阀,开启包括所述待安装立柱在内的各个所述立柱的所述控制阀,驱动所述待安装立柱的移动柱伸长至抵接所述液压支架的顶板,将所述移动柱与顶板固定。2.根据权利要求1所述的液压支架立柱的更换方法,其特征在于,在步骤(1)之前还包括:在巷道内分隔出作业区域,对所述作业区域内的巷道支护实施监护监测,确定巷道内需要加强区域且对其进行加强支护。3.根据权利要求2所述的液压支架立柱的更换方法,其特征在于,在步骤(1)之前还包括:向所述作业区域通风,监测易燃易爆气体浓度以及有毒有害气体浓度,根据监测结果调节通风量,将...
【专利技术属性】
技术研发人员:杨俊哲,潘金,郭洋楠,刘英杰,高清福,王盛铭,
申请(专利权)人:中国神华能源股份有限公司,神华神东煤炭集团有限责任公司,中国煤炭工业协会咨询中心,
类型:发明
国别省市:北京,11